Morning Report for April 12, 1999
Headquarters Daily Report
APRIL 12, 1999
***************************************************************************
REPORT NEGATIVE NO INPUT
ATTACHED INPUT RECEIVED RECEIVED
HEADQUARTERS X
REGION I X
REGION II X
REGION III X
REGION IV X
PRIORITY ATTENTION REQUIRED MORNING REPORT - HEADQUARTERS APRIL 12, 1999
MR Number: H-99-0033
NRR DAILY REPORT ITEM
GENERIC COMMUNICATIONS
Subject: Issuing IN 99-10, dated April 13, 1999
NRC INFORMATION NOTICE 99-10: DEGRADATION OF PRESTRESSING TENDON SYSTEMS
IN PRESTRESSED CONCRETE CONTAINMENTS, dated April 13, 1999
The U.S. Nuclear Regulatory Commission is issuing this information notice
to alert addressees to degradation of prestressing systems components of
prestressed concrete containments (PCCs).
Technical Contacts: H. Ashar, NRR G. Hatchett, NRR
301-415-2851 301-415-3315
E-mail: hga@nrc.gov E-mail: gxh@nrc.gov
_
REGION II MORNING REPORT PAGE 2 APRIL 12, 1999
Licensee/Facility: Notification:
Carolina Power & Light Co. MR Number: 2-99-0008
Harris 1 Date: 04/12/99
Raleigh,North Carolina
Dockets: 50-400
PWR/W-3-LP
Subject: MANAGEMENT CHANGES
Discussion:
Carolina Power & Light (CP&L) announced on April 9, 1999, that Chris
Burton will become the new director of site operations for the Harris
Plant effective April 19, 1999, filling the position which had previously
been vacant. Cris Burton had been serving as acting plant manager at
Sequoyah Plant since February, 1999. Previously he was Engineering and
Support Services Manager at Sequoyah since 1997. He spent 22 years with
Florida Power & Light where he held numerous management positions.
Regional Action:
For information only.
Contact: G. MACDONALD (404)562-4543