Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Event Notification Report for July 5, 2002

                         
                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           07/04/2002 - 07/05/2002

                              ** EVENT NUMBERS **

39033  39041  
.
+------------------------------------------------------------------------------+
|General Information or Other                     |Event Number:   39033       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| REP ORG:  MARYLAND DEPT OF THE ENVIRONMENT     |NOTIFICATION DATE:
07/01/2002|
|LICENSEE:  NEUTRON PRODUCTS                     |NOTIFICATION TIME: 08:16[EDT]|
|    CITY:  ROCKVILLE                REGION:  1  |EVENT DATE:        06/27/2002|
|  COUNTY:  MONTGOMERY                STATE:  MD |EVENT TIME:        08:00[EDT]|
|LICENSE#:  MD 3102501            AGREEMENT:  Y  |LAST UPDATE DATE:  07/01/2002|
|  DOCKET:                                       |+----------------------------+
|                                                |PERSON          ORGANIZATION |
|                                                |MICHAEL MODES        R1      |
|                                                |FRED BROWN           NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  ALAN JACOBSON                |                             |
|  HQ OPS OFFICER:  JOHN MacKINNON               |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          NON EMERGENCY         |                             |
|10 CFR SECTION:                                 |                             |
|NAGR                     AGREEMENT STATE        |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| RADIATION ALARM AT A WASTE TRANSFER STATION WAS ACTIVATED BY A TUCK         
|
| CONTAINING REFUSE.                                                           |
|                                                                              |
|                                                                              |
| A truck containing a roll off refuse container set off the radiation monitor |
| at the Montgomery County Waste Transfer Station located in Rockville, MD at  |
| 0800 hours on 06/27/02.  The  refuse container was searched and a bag        |
| containing paper towels and rags found to be contaminated with cobalt-60     |
| with a radiation reading of 0.5 mr/hr.  The load was rejected and sent back  |
| to Neutron Products Incorporated, Dickerson, MD.  The load was evaluated and |
| the radioactive material was removed and placed into storage with            |
| radioactive waste.   Neutron Products was cited by the State of Maryland for |
| improper disposal of radioactive waste and inadequate surveying and          |
| monitoring.                                                                  |
+------------------------------------------------------------------------------+
.
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   39041       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: CLINTON                  REGION:  3  |NOTIFICATION DATE: 07/04/2002|
|    UNIT:  [1] [] []                 STATE:  IL |NOTIFICATION TIME: 05:57[EDT]|
|   RXTYPE: [1] GE-6                             |EVENT DATE:        07/04/2002|
+------------------------------------------------+EVENT TIME:        01:33[CDT]|
| NRC NOTIFIED BY:  MERRIKEN                     |LAST UPDATE DATE:  07/04/2002|
|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          NON EMERGENCY         |PATRICK HILAND       R3      |
|10 CFR SECTION:                                 |                             |
|ARPS 50.72(b)(2)(iv)(B)  RPS ACTUATION - CRITICA|                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE  
|
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     A/R        Y       95       Power Operation  |0        Hot Shutdown     |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| REACTOR SCRAM FROM 94.6% POWER DUE TO TURBINE TRIP CAUSED BY
GENERATOR TRIP  |
| AND LOCKOUT                                                                  |
|                                                                              |
| On July 4, 2002, at 0133, Clinton Power Station scrammed from 94.6% due to a |
| Turbine Trip from a Generator Trip and Lockout.  The initiating event for    |
| the scram is not presently known at this time but it is believed to be a     |
| problem with the Main Power Transformer (MPT) B.   The Sudden Pressure MPT B |
| alarm came simultaneously with the reactor scram.  The Sudden Pressure MPT B |
| alarm is brought in by the Sudden Pressure Fault Relay, which initiates a    |
| Main Generator trip and lockout, which trips the Main Turbine and initiates  |
| a reactor scram.                                                             |
|                                                                              |
| The MPT B deluge system initiated, however, there was no  physical evidence  |
| of any damage to MPT B.  After conducting a visual inspection of MPT B, the  |
| deluge system was secured.  A clearance is being applied to MPT B for        |
| investigation.                                                               |
|                                                                              |
| The plant is presently in Mode 3, maintaining reactor pressure within a      |
| pressure band of 550 to 650 psig and level between Level 3 and Level 8,      |
| which is the normal level band.                                              |
|                                                                              |
| The plant responded normally on the scram.  All rods fully inserted, no ECCS |
| injection occurred and no relief valves lifted.                              |
|                                                                              |
| The NRC Resident Inspector and the State were notified.                      |
|                                                                              |
|                                                                              |
| -                                                                            |
+------------------------------------------------------------------------------+
.

Page Last Reviewed/Updated Thursday, March 25, 2021