The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Plant Operations Subcommittee Meeting - January 20, 2000

REVISED 1/6/2000

ADVISORY COMMITTEE ON REACTOR SAFEGUARDS
MEETING OF THE SUBCOMMITTEE ON PLANT OPERATIONS
ROOM T-2B3, 11545 ROCKVILLE PIKE, ROCKVILLE, MD
JANUARY 20, 2000

ACRS Contact: Michael T. Markley, (301) 415-6885

- PROPOSED SCHEDULE -

  TOPIC SPEAKER TIME
       
1) Introduction 8:30-8:40 am

Review goals and objectives for this meeting:
technical components of the reactor oversight process

- significance determination process (SDP)
- performance indicators (PIs)
- industry pilots

J. Barton, ACRS  
Review previous deliberations and issues identified in ACRS report dated June 10, 1999 J. Barton, ACRS  
       
2) NRC Presentation 8:40-9:00 am

Introductory remarks and overview of the planned presentation

- goals and objectives of SDP and PIs
- success criteria for pilots and results
- lessons learned: workshop and key issues
- long-term implementation issues

F. Gillespie, NRR
M. Johnson, NRR
 
       
3) Industry Presentation 9:00-10:15 am
Discussion of NEI 99-02, "Regulatory Assessment Performance Indicator Guideline"

- integration of PIs and inspection findings
- validation process

T. Houghton, NEI
S. Floyd, NEI
 
       
  ** BREAK ** 10:15-10:30 am
       
4) NRC Presentation 10:30-12:00 noon
SDP - Draft Inspection Manual Chapter including discussion of Quad Cities Risk Information Matrix (RIM) D. Coe, NRR  
PIs - Proposed NRC approach for use of NEI 99-02 D. Hickman, NRR  
       
  ** LUNCH ** 12:00-1:00 pm
       
5) NRC Presentation - continued 1:00-2:00 pm
SDP - Draft Inspection Manual Chapter including discussion of Quad Cities Risk Information Matrix (RIM) D. Coe, NRR  
PIs - Proposed NRC approach for use of NEI 99-02 D. Hickman, NRR  
Comments on final report of pilot program evaluation panel dated December 17, 1999 F. Gillespie, NRR
M. Johnson
 
6) Public Presentation 2:00-2:15 pm
Comments on proposed reactor oversight process - SDP and PIs J. Riccio, Public Citizen  
7) General Discussion and Adjournment 2:15-3:00 pm
General discussion and comments by Members of the Subcommittee, items for discussion by the full ACRS J. Barton, ACRS  

Note: Presentation time should not exceed 50% of the total time allocated for a specific item. Number of copies of presentation materials to be provided to the ACRS - 35.

Page Last Reviewed/Updated Monday, October 02, 2017