Status of Initial License Renewal Applications and Industry Initiatives

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

On this page:

Plant Applications for License Renewal

Future Submittals of Applications:

Fiscal Year

License Renewal Application (LRA)

Applicant

Letter of Intent
(ADAMS Accession No.)

Submission Date

2027

Watts Bar Nuclear Plant, Unit 1

Tennessee Valley Authority

ML24085A212

Oct. to Dec. 2026

To top of page

Applications Received and Under Acceptance Review:

Plant Name and Unit(s)

Application Received

Currently No Applications Received and Under Acceptance Review

To top of page

Applications Currently Under Review:

Plant Name and Unit(s)

Application Received

Diablo Canyon Power Plant, Units 1 and 2

11/07/2023

Clinton Power Station, Unit 1

02/14/2024

To top of page

Completed Applications:

(Includes application, review schedule, supplemental environmental impact statement, and safety evaluation report.)

Plant Name and Unit(s)

Application Received

Renewed License Issued

Date Entering Extended Operation

Calvert Cliffs 1 & 2

04/10/98

03/23/00

07/31/14 (Unit 1)
08/13/16 (Unit 2)

Oconee 1, 2 & 3

07/07/98

05/23/00

02/06/13 (Unit 1)
10/06/13 (Unit 2)
07/19/14 (Unit 3)

Arkansas Nuclear One 1

02/01/00

06/20/01

05/20/14

Turkey Point 3 & 4

09/11/00

06/06/02

07/19/12 (Unit 3)
04/10/13 (Unit 4)

Edwin I. Hatch 1 & 2

03/01/00

06/15/02

08/06/14 (Unit 1)
06/13/18 (Unit 2)

North Anna 1 & 2

05/29/01

03/20/03

04/01/18 (Unit 1)
08/21/20 (Unit 2)

Surry 1 & 2

05/29/01

03/20/03

05/25/12 (Unit 1)
01/29/13 (Unit 2)

Peach Bottom 2 & 3

07/02/01

05/07/03

08/08/13 (Unit 2)
07/02/14 (Unit 3)

St. Lucie 1 & 2

11/30/01

10/02/03

03/01/16 (Unit 1)
04/06/23 (Unit 2)

Fort Calhoun*

01/11/02

11/04/03

08/09/13

McGuire 1 & 2

06/14/01

12/05/03

06/12/21 (Unit 1)
03/03/23 (Unit 2)

Catawba 1 & 2

06/14/01

12/05/03

12/05/23 (Unit 1)
12/05/23 (Unit 2)

H.B. Robinson 2

06/17/02

04/19/04

07/31/10

V.C. Summer

08/06/02

04/23/04

08/06/22

R.E. Ginna

08/01/02

05/19/04

09/18/09

Dresden 2 & 3

01/03/03

10/28/04

12/22/09 (Unit 2)
01/12/11 (Unit 3)

Quad Cities 1 & 2

03/03/03

10/28/04

12/14/12 (Unit 1)
12/14/12 (Unit 2)

Joseph M. Farley 1 & 2

09/15/03

05/12/05

06/25/17 (Unit 1)
03/31/21 (Unit 2)

Arkansas Nuclear One 2

10/15/03

06/30/05

07/17/18

D.C. Cook 1 & 2

10/31/03

08/30/05

10/25/14 (Unit 1)
12/23/17 (Unit 2)

Millstone 2 & 3

01/22/04

11/28/05

07/31/15 (Unit 2)
11/25/25 (Unit 3)

Point Beach 1 & 2

02/26/04

12/22/05

10/05/10 (Unit 1)
03/08/13 (Unit 2)

Browns Ferry 1, 2 & 3

01/02/04

05/04/06

12/20/13 (Unit 1)
06/28/14 (Unit 2)
07/02/16 (Unit 3)

Brunswick 1 & 2

10/18/04

06/26/06

09/08/16 (Unit 1)
12/27/14 (Unit 2)

Nine Mile Point 1 & 2

05/27/04

10/31/06

08/22/09 (Unit 1)
10/31/26 (Unit 2)

Monticello

03/24/05

11/08/06

09/08/10

Palisades

03/31/05

01/17/07

03/24/11

FitzPatrick

07/01/06

09/08/08

10/17/14

Wolf Creek 1

10/04/06

11/20/08

03/11/25

Harris 1

11/16/06

12/17/08

10/24/26

Oyster Creek******

07/22/05

04/08/09

04/09/09

Vogtle 1 & 2

06/29/07

06/03/09

01/16/27 (Unit 1)
02/09/29 (Unit 2)

Three Mile Island 1

01/08/08

10/22/09

04/19/14

Beaver Valley 1 & 2

08/28/07

11/05/09

01/29/16 (Unit 1)
05/27/27 (Unit 2)

Susquehanna 1 & 2

09/13/06

11/17/09

07/17/22 (Unit 1)
03/23/24 (Unit 2)

Cooper

09/30/08

11/29/10

01/18/14

Duane Arnold

10/01/08

12/16/10

02/21/14

Kewaunee

08/14/08

02/24/11

**

Vermont Yankee***

01/27/06

03/21/11

03/21/12

Palo Verde 1, 2 & 3

12/15/08

04/22/11

06/01/25 (Unit 1)
04/24/26 (Unit 2)
11/25/27 (Unit 3)

Prairie Island 1 & 2

04/15/08

06/27/11

08/09/13 (Unit 1)
10/29/14 (Unit 2)

Salem 1 & 2

08/18/09

06/30/11

08/13/16 (Unit 1)
04/18/20 (Unit 2)

Hope Creek 1

08/18/09

07/20/11

04/11/26

Columbia Generating Station

01/20/10

05/22/12

12/20/23

Pilgrim 1

01/27/06

05/29/12

 +++

Crystal River 3

12/18/08

****

 

Limerick 1 & 2

06/22/11

10/20/14

10/26/24 (Unit 1)
06/22/29 (Unit 2)

Callaway 1

12/19/11

03/06/15

10/18/24

Sequoyah 1 & 2

01/15/13

09/24/15

09/17/20 (Unit 1)
09/15/21 (Unit 2)

Byron 1 & 2

05/29/13

11/19/15

10/31/24 (Unit 1)
11/06/26 (Unit 2)

Davis-Besse 1

08/30/10

12/08/15

04/22/17

Braidwood 1 & 2

05/29/13

01/27/16

10/17/26 (Unit 1)
12/18/27 (Unit 2)

LaSalle 1 & 2

12/09/14

10/19/16

04/17/22 (Unit 1)
12/16/23 (Unit 2)

Grand Gulf 1

11/01/11

12/01/16

11/02/24

Fermi, Unit 2

04/30/14

12/15/16

03/21/25

South Texas Project 1 & 2

10/28/10

09/28/17

08/21/27 (Unit 1)
12/16/28 (Unit 2)

Diablo Canyon 1 & 2

11/24/09

*****

 

Indian Point 2 & 3

04/30/07

09/17/18

09/17/18 (Unit 1)
09/17/18 (Unit 2)

River Bend

05/31/17

12/20/18

08/30/25

Waterford 3

03/23/16

12/27/18

10/19/24

Seabrook 1

06/01/10

03/12/19

03/15/30

Comanche Peak 1 & 2

10/03/22

07/30/24

02/08/30 (Unit 1)
02/02/33 (Unit 2)

Perry Nuclear Power Plant, Unit 1

07/03/23

07/07/25

11/07/26

* Fort Calhoun Station was permanently shut down on October 24, 2016.

** Kewaunee Power Station was permanently shut down on May 7, 2013.

*** Vermont Yankee Nuclear Power Station was permanently shut down on December 29, 2014.

**** The Crystal River Nuclear Generating Plant, Unit 3 application was withdrawn by the licensee on February 6, 2013.  The facility was permanently shut down on February 20, 2013.

***** The previous Diablo Canyon 1 & 2 license renewal application was submitted on November 7, 2018 and withdrawn by the licensee on March 7, 2018. On October 31, 2022, Pacific Gas and Electric sent in a letter to “Request to Resume Review of the Diablo Canyon Power Plant License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application.”  On March 2, 2023, the NRC granted the exemption.

****** Oyster Creek Nuclear Generating Station was permanently shut down on September 7, 2018.

 +++ Pilgrim 1 permanently shut down on May 31, 2019

To top of page

Industry Activities

Nuclear Energy Institute (NEI) -- Industry representatives also participate in working groups and technical committees, coordinated by the Nuclear Energy Institute, to address generic technical and process issues, and to develop additional guidance related to scoping and aging management programs. The NRC has established a formal feedback process by which the resolution of the generic renewal issues and lessons learned during the review of the initial renewal applications is documented and included in revisions to the implementation guidance. These activities are expected to improve the efficiency and effectiveness of future license renewal reviews.

To top of page

Subscribe to License Renewal Correspondence for a Specific Plant

To subscribe to all outgoing public correspondence for a specific license renewal application by e-mail, simply go to our Operating Reactors Correspondence page enter your email address, name, select the plant(s) of interest and Subscribe. This correspondence will include all publicly available information for a specific plant.

To top of page

Page Last Reviewed/Updated Tuesday, September 16, 2025