Date |
Description |
Status |
08/12/2022 |
Abilene Christian University Construction Permit Application for the MSRR, Preliminary Safety Analysis Report and Environmental Report |
Accepted for review on 11/18/2022 |
10/14/2022 |
Abilene Christian University Response to NRC Request for Supplemental Information |
Accepted for review on 11/18/2022 |
11/18/2022 |
Acceptance for Docketing of the ACU MSRR Non-power Test Reactor Construction Permit Application |
Acceptance Letter |
11/28/2022 |
Federal Register Notice: Construction permit application; acceptance for docketing - Published |
Published |
12/16/2022 |
Abilene Christian University Molten Salt Research Reactor Construction Permit Application Review Schedule and Resource Estimate |
Issued |
01/13/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Technical Topics |
Issued |
02/06/2023 |
Abilene Christian University Audit Questions Regarding the ACU Construction Permit Technical Topics Audit |
Issued |
03/02/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics |
Issued |
03/02/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 2 and 3 |
Issued |
03/02/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 4, 6, and 9.6 |
Issued |
03/02/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 7 |
Issued |
03/02/2023 |
Abilene Christian University Audit Plan for the Molten Salt Research Reactor Construction Permit Application Primarily Regarding Chapters 9.2 and 13 |
Issued |
03/09/2023 |
Abilene Christian University Environmental Audit Plan and Information Needs for the Molten Salt Research Reactor Construction Permit Application |
Issued |
03/14/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 7 |
Issued |
03/16/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 9.2 and 13 |
Issued |
03/21/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics (Batch 1) |
Issued |
03/24/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 2 and 3 (Batch 1) |
Issued |
03/24/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 4, 6, and 9.6 |
Issued |
04/05/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 2 and 3 (Batch 2) |
Issued |
04/26/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 1, 5, 8, 9 (Except 9.2 and 9.6), 10, 11, 12, 14-18, and General Topics (Batch 2) |
Issued |
05/02/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 4 |
Issued |
05/02/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 9.2 and 13 |
Issued |
05/09/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapters 1.7 and 9.5 |
Issued |
06/22/2023 |
Interim Report on Regulatory Audit of the Abilene Christian University Preliminary Safety Analysis Report |
Issued |
07/03/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 10 |
Issued |
07/11/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 11.3 |
Issued |
07/13/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 16 |
Issued |
08/02/2023 |
Abilene Christian University Audit Questions Regarding ACU CP PSAR Chapter 2.3 (Batch 2) |
Issued |
8/17/2023 |
Abilene Christian University Construction Permit Application Information Related to the Nuclear Waste Policy Act |
Docketed |
09/14/2023 |
Abilene Christian University – Update to Construction Permit Application Technical Review Schedule |
Issued |
09/27/2023 |
ACU MSRR – Environmental Review Requests for Confirmatory Information – Closure Confirmation |
Issued |
10/05/2023 |
ACU MSRR PSAR Section 2.5 Audit Questions (Round 2) |
Issued |
10/24/2023 |
ACU MSRR PSAR Section 9.8 Audit Question |
Issued |
10/26/2023 |
Response to ACU's Request for Non-Public Documents Related to Security |
Issued |
11/14/2023 |
Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report, Revision 1 |
Docketed |
12/01/2023 |
ACU MSRR PSAR Chapter 3 Audit Questions on Structural Engineering |
Issued |
12/11/2023 |
ACU MSRR PSAR Chapter 3 Audit Questions on Structural Engineering |
Issued |
12/20/2023 |
ACU MSRR PSAR Section 4.3 and 9.2 Audit Questions (Related to Material Degradation) |
Issued |
12/21/2023 |
Abilene Christian University - Transmittal of Requests for Additional Information (EPID L-2022-NFW-0002) |
Issued |
01/08/2024 |
ACU MSRR PSAR Section 4.3 Audit Questions (Related to Material Degradation) |
Issued |
01/11/2024 |
ACU MSRR PSAR Section 4.3 Audit Question (Related to Material Degradation) |
Issued |
01/17/2024 |
ACU MSRR PSAR Section 4.3 Audit Question (Related to Material Degradation) |
Issued |
01/22/2024 |
ACU MSRR PSAR Section 4.3 Audit Question (4.3-23 and 4.3-24 on Material Degradation) |
Issued |
01/22/2024 |
Abilene Christian University Molten Salt Research Reactor Environmental Audit Closeout |
Issued |
01/23/2024 |
ACU MSRR PSAR Section 4.3 Audit Question (4.3-25 on Material Degradation) |
Issued |
01/23/2024 |
ACU's Construction Permit Application Partial Response to Audit Questions 3.5-4, 4.2-9, and 4.3-3 |
Docketed |
01/26/2024 |
NEXT, Abilene Christian University Molten Salt Research Reactor Regulatory Engagement Plan, Revision 1 |
Docketed |
01/29/2024 |
ACU's Request for Extension of the MSRR RAI Response Date |
Docketed |
01/31/2024 |
Abilene Christian University, Response to RAI Extension Request |
Issued |
02/05/2024 |
NRC Response to Request for Withholding Information from Public Disclosure for ACU |
Issued |
02/27/2024 |
NRC Documentation of its Section 106 Environmental Assessment Review Findings |
Issued |
02/29/2024 |
Request For Extension of the Abilene Christian University (ACU) Molten Salt Research Reactor (MSRR) Requests for Additional Information (RAI) Response Date |
Docketed |
03/01/2024 |
Abilene Christian University, Response to Request for Additional Information (RAI) Extension Request |
Issued |
03/07/2024 |
Environmental Assessment for the Construction Permit Application for the Abilene Christian University Molten Salt Research Reactor |
Issued |
03/14/2024 |
Federal Register Notice on Abilene Christian University; Molten Salt Research Reactor; Environmental Assessment and Finding of No Significant Impact |
Published |
03/28/2024 |
Request For Extension of the Abilene Christian University (ACU) Molten Salt Research Reactor (MSRR) Request for Additional Information (RAI 2) Response Date |
Docketed |
03/28/2024 |
ACU Response to Request for Additional Information 1 |
Docketed |
03/29/2024 |
NRC Response to RAI Extension Request (RAI 2) |
Issued |
04/05/2024 |
Request for Confirmation of Information for the MSRR PSAR |
Issued |
04/18/2024 |
ACU Response to Request for Confirmation of Information |
Docketed |
04/30/2024 |
ACU Response to Request for Additional Information 2 |
Docketed |
05/30/2024 |
Request for Confirmation of Information on Materials’ Degradation |
Issued |
06/12/2024 |
ACU's Response to Request for Confirmation of Information on Materials' Degradation |
Docketed |
06/12/2024 |
Revised Review Schedule Letter to ACU |
Issued |
7/30/2024 |
Abilene Christian University Construction Permit Application Preliminary Safety Analysis Report, Revision 2 |
Docketed |
09/06/2024 |
Issuance of Audit Reports for Abilene Christian University's (ACU) Construction Permit Application Review |
Issued |
09/16/2024 |
Safety Evaluation Related to the Abilene Christian University Construction Permit Application for the Molten Salt Research Reactor |
Issued |
09/16/2024 |
Abilene Christian University, Molten Salt Research Reactor Construction Permit No. CPRR-124 |
Issued |