12/14/2023 |
Kairos Hermes Test Reactor Construction Permit No. CPTR-6 |
Issued |
12/14/2023 |
Kairos Hermes Test Reactor Summary Record of Decision |
Issued |
12/12/2023 |
CLI-23-05, Memorandum and Order directing the staff to issue the Hermes construction permit |
Issued |
09/05/2023 |
Federal Register Notice: Construction permit application; notice of hearing |
Published |
08/23/2023 |
Staff's Statement in Support of the Uncontested Hearing for Issuance of a Construction Permit for the Kairos Hermes Test Reactor |
issued |
08/17/2023 |
Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor |
Issued |
06/20/2023 |
Response to ACRS Letter on the Kairos Non-Power Reactor Hermes Construction Permit Application |
Issued |
06/13/2023 |
Safety Evaluation Related to the Kairos Power LLC Construction Permit Application for the Hermes Test Reactor |
Issued |
06/09/2023 |
Summary Report for the Regulatory Audit of Kairos Power LLC Hermes Construction Permit Preliminary Safety Analysis Report Chapters 4 and 13 (Accident Analysis) |
Issued |
06/09/2023 |
Summary Report for the Regulatory Audit of Kairos Power LLC Hermes Construction Permit Preliminary Safety Analysis Report General Audit |
Issued |
05/31/2023 |
Hermes Non-Power Reactor Preliminary Safety Analysis Report, Revision 3 |
Received |
05/16/2023 |
ACRS Letter on Kairos Non-Power Reactor Hermes Construction Permit Application |
Issued |
04/25/2023 |
Summary Report for the Regulatory Audit of Kairos Power LLC Hermes Construction Permit Preliminary Safety Analysis Report Instrumentation and Control (Chapter 7) |
Issued |
04/25/2023 |
Summary Report for the Regulatory Audit of Kairos Power LLC Hermes Construction Permit Preliminary Safety Analysis Report Decay Heat Removal System (Chapter 6, Section 6.3) |
Issued |
04/25/2023 |
Summary Report for the Regulatory Audit of Kairos Power LLC Hermes Construction Permit Preliminary Safety Analysis Report Site Characteristics (Chapter 2) |
Issued |
04/18/2023 |
(Approved SE – a preliminary version) Safety Evaluation Related to the Kairos Power LLC Construction Permit Application for the Hermes Test Reactor |
Available |
02/24/2023 |
Hermes Non-Power Reactor Preliminary Safety Analysis Report, Revision 2 |
Received |
09/29/2022 |
Hermes Non-Power Reactor Preliminary Safety Analysis Report, Revision 1 |
Received |
09/26/2022 |
NUREG-2263 Draft Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor |
Issued |
09/01/2022 |
Response to NRC Request for Additional Information 350 |
Received |
08/31/2022 |
Response to NRC Request for Additional Information 348 |
Received |
08/31/2022 |
Response to NRC Request for Additional Information 339 |
Received |
08/24/2022 |
Summary Report for Environmental Audit of the Kairos Hermes Test Reactor Construction Permit Application |
Issued |
08/19/2022 |
Response to NRC Request for Confirmation of Information 349 |
Received |
08/02/2022 |
Final Request for Additional Information 350 for Air Ingress into the Primary Heat Transport System |
Issued |
08/02/2022 |
Final Request for Additional Information 348 on Shutdown Rod Reliability |
Issued |
08/02/2022 |
Final Request for Additional Information 339 Regarding Inspection of Vessel Internals and the Natural Gas Circulation Flow Path |
Issued |
08/02/2022 |
Final Request for Confirmation of Information 349 on Salt Purity in the Chemistry Control System and the Inert Gas System |
Issued |
08/01/2022 |
Issuance of Environmental Scoping Summary Report |
Issued |
05/27/2022 |
Hermes Construction Permit Preliminary Safety Analysis Report Site Characteristics (Chapter 2) Audit Plan |
Issued |
04/08/2022 |
Plan for an Audit of the Hermes Construction Permit Preliminary Safety Analysis Report Chapter 7 on Instrumentation and Control |
Issued |
02/23/2022 |
Audit Plan for the Hermes Construction Permit Preliminary Safety Analysis Report Chapters 4, Section 4.5 and 13 |
Issued |
02/17/2022
|
Hermes Construction Permit Preliminary Safety Analysis Report Chapter 6, Section 6.3 Audit Plan |
Issued |
02/15/2022
|
Notice of Intent to Conduct Scoping Process and
Prepare Environmental Impact Statement |
Published |
02/10/2022
|
Plan for a General Audit of the Hermes Construction Permit Application |
Issued |
02/04/2022
|
Federal Register Notice: Construction permit application; opportunity to request a hearing and petition for leave to intervene; order imposing procedures |
Published |
02/02/2022
|
Hermes Environmental Report Audit Plan |
Issued |
12/15/2021
|
Hermes Test Reactor Construction Permit Application Review Schedule and Resource Estimate |
Issued |
11/29/2021
|
Acceptance for Docketing of the Hermes Non-power Test Reactor Construction Permit Application |
Acceptance letter |
10/31/2021 |
Kairos Power Construction Permit Application for Hermes Part 2, Environmental Report |
Accepted for review on 11/29/21 |
09/29/2021 |
Kairos Power Construction Permit Application for Hermes Part 1, Preliminary Safety Analysis Report |
Accepted for review on 11/29/21 |