Issued Combined Licenses for Levy Nuclear Plant, Units 1 and 2
On July 30, 2008, Duke Energy Florida, LLC (DEF) submitted its application for combined licenses (COLs) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs) designated as Levy Nuclear Plant, Units 1 and 2.
For detail (including the latest submittal of the application, the related review schedule, and the associated staff documentation), see the following topics on this page:
Reference Documents
In accordance with Title 10, Part 52, of the Code of Federal Regulations (10 CFR Part 52), "Licenses, Certifications, and Approvals for Nuclear Power Plants," a COL application may reference a standard design certification, an early site permit, both, or neither. Many COL applications have referenced an application for design certification, in accordance with 10 CFR 52.55(c). On that basis, the application referenced Westinghouse's application to amend the AP1000 standard design certification and cited the following amended design control document (DCD) in its COL original application for Levy Nuclear Plant, Units 1 & 2:
In Revision 1 to the Levy Nuclear Plant, Units 1 & 2 COL application dated October 2, 2009, Progress Energy Florida updated the application to reflect that its application now incorporates by reference AP1000 DCD Revision 17.
In Revision 3 to the Levy Nuclear Plant, Units 1 & 2 COL application dated October 4, 2011, Progress Energy Florida updated the application to reflect that its application now incorporates by reference AP1000 DCD Revision 19. All subsequent revisions to the COL application also incorporate by reference AP1000 DCD Revision 19.

Application Information
The following table provides access to the COL Application that Progress Energy Florida submitted for Levy Nuclear Plant, Units 1 & 2. Beginning in April 2014, the applicant changed to Duke Energy Florida, Inc. Beginning December 2015, the applicant changed to Duke Energy Florida, LLC.
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Final Safety Analysis Report and associated Technical/Topical Reports would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Review Schedule
Key Milestones |
Completion Date
Actual - A
Target - T |
Application Tendered |
07/30/08 - A |
Acceptance Review |
Acceptance Review Start
|
08/04/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete
|
10/06/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant
|
02/18/09 - A |
Safety Review |
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
(Formerly Phase 1)
|
03/29/10 - A |
Phase B - Advanced Final safety evaluation report (SER) without Open Items
(Formerly Phase 2)
|
09/15/11 - A |
Phase C - ACRS Review of Advanced Final SER
(Formerly Phase 3)
|
01/24/12 - A |
Phase D - Final SER
(Formerly Phase 4)
|
05/31/16 - A |
Environmental Review |
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
|
05/28/09 - A |
Phase 2 - Draft EIS issued to EPA
|
08/06/10 - A |
Phase 3 - Responses to public comments on draft EIS completed*
|
04/27/12 - A |
Phase 4 - Final EIS issued to EPA
|
04/27/12 - A |
Hearing |
Commission holds mandatory hearing
|
07/28/16 - A |
License |
Commission decision on issuance of COL
|
10/20/16 - A |
* NRC staff responses to public comments on the Draft EIS are included in Appendix E of the Final EIS

Safety Evaluations
This section lists the Safety Evaluations that the NRC has issued in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.

Topical Reports
The NRC has issued no Topical Reports in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.

Combined Licenses
This provides the COLs that the NRC issued on October 27, 2016 in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.