Combined License Application for Fermi America President Donald J. Trump Advanced Energy and Intelligence Campus, Units 1-4
subscribe to page updatesOn June 17, 2025, Fermi America submitted Part 1 of its application for 10 CFR Part 52 combined licenses (COLs) for four AP1000 advanced passive pressurized-water reactors, Fermi America Units 1 through 4.
For details (including the latest submittal of the application, the related review schedule, and the associated staff documentation), see the following topics on this page:
Application Information
The following table provides access to the COL Application that Fermi America submitted for Fermi America Units 1 through 4.
Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Final Safety Analysis Report and associated Technical/Topical Reports would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.
Part | Description of COLA (General Information) | Revision |
---|---|---|
0 | Cover Letter | |
1 | General and Financial Information | |
2 | Final Safety Analysis Report (FSAR) | |
3 | Environmental Report | |
4 | Technical Specifications | |
5 | Emergency Plans | |
6 | Security Plans | |
7 | Departures and Exemption Requests | |
8 | Safeguards Information (SGI) and Security-Related Information | |
9 | Withheld Proprietary Information | |
10 | Inspection, Tests, Analyses and Acceptance Criteria (ITAAC) Closure Process | |
11 | Enclosures |
Incorporated by Referenced Documents:
- AP1000 DCD, Revision 19
Part | Description of COLA (Design-Specific Technical) | Revision |
---|---|---|
0 | Clarification Letter | |
0 | Cover Letter | |
1 | Final Safety Analysis Report (FSAR) |
Part | Description of COLA (Site-Specific Technical) | Revision |
---|---|---|
0 | Cover Letter | TBD |
1 | Final Safety Analysis Report (FSAR) | TBD |
Review Schedule
Key Milestones | Completion Date |
---|---|
Application Tendered (Part 1) | 06/17/2025-A |
Application Tendered (Part 2) | 08/20/2025-A |
Application Tendered (Part 3) Draft/Final | 10/31/2026-T 12/31/2026-T |
Acceptance Review | |
Acceptance Review Start | 08/20/2025-A |
Acceptance Review Complete | 09/05/2025-T |
Review Schedule Established/Schedule Letter Issued to Applicant | TBD |
Safety Review | |
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs | TBD |
Phase B - Advanced Final safety evaluation report (SER) without Open Items | TBD |
Phase C - ACRS Review of Advanced Final SER | TBD |
Phase D - Final SER | TBD |
Environmental Review | |
Applicant-prepared Draft EIS (DEIS) | 02/28/2026-T |
Phase 2 Issue DEIS | TBD |
Phase 3 - Response to Public Comments on DEIS completed | TBD |
Phase 4 - Final Environmental Impact Statement | TBD |
Hearing | |
Mandatory Hearing Complete | TBD |
License | |
Commission decision on issuance of COL application | TBD |
Contacts
Current Contacts for the Fermi America, Units 1 through 4 | |
---|---|
Lead Licensing Project Manager | William (Billy) Gleaves |
Sr. Project Manager for Siting | Allen Fetter |
Environmental Project Manager | Mary Richmond |
Contact a Public Affairs Officer |
Page Last Reviewed/Updated Monday, September 15, 2025