Skip to main content

NuScale Power, LLC

subscribe to page updates
Image
image of a blue texted logo displaying NUSCALE

Who:  

NuScale Power, LLC
 

What:  

Pre-Application activities associated with future combined license applications (COLAs) that will reference the NuScale US460 standard design approval (SDA)
 

When:  

August 2025 to Present
 

Website:  

https://www.nuscalepower.com/ 

On this page:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in pre-application activities with NuScale Power, LLC, regarding future combined license applications (COLAs) that will reference the NuScale US460 standard design approval (SDA). 

For more information, please see the NuScale pre-application documents (NRC Docket 99902078).

To subscribe to the NuScale email service, select NuScale from the Advanced Reactors list after entering your email into the GovDelivery system.

Pre-Application Activities

Product

Type

Reference

Status

Regulatory Acceleration Regulatory Engagement Plan, PL-186704, Revision 0

Regulatory Engagement Plan

ML25238A096

Submitted on 08/26/2025
No review requested

TR-182845-NP, Revision 0, Emergency Event Classification Scheme for a NuScale Power Plant

Topical Report

ML25210A619

Under Review

TR-18310-NP, Revision 0, Emergency Response Organization for a NuScale Power Plant

Topical Report

ML25209A575

Under Review

TR-147121-NP, Revision 1, Supplement 1 to TR-1015-18653-P-A, Revision 2 “Design of the Highly Integrated Protection System Platform”

Topical Report

ML25353A608

Under Review

TR-145417-NP-A, Revision 1, NuScale US460 Fuel Storage Rack Design Topical Report

Topical Report

ML25253A493

Approved (-A) Version Issued on 09/10/2025

TR-141299-NP-A, Revision 1, NuScale Power Plant Design Capability to Mitigate Beyond-Design-Basis Events Defined by 10 CFR 50.155, Revision 1

Topical Report

ML25153A538

Approved (-A) version Issued on 06/01/2025

TR-0915-17772-P-A, Revision 3, Methodology for Establishing the Technical Basis for Plume Exposure Emergency Planning Zones at NuScale Small Modular Reactor Plant Sites, Revision 3

Topical Report

ML22299A145

Approved (-A) version Issued on 10/26/202


To top of page

Contacts

Contacts for the Energy Northwest Pre-Application Review

Lead Project Manager

Getachew Tesfaye
301-415-8013

Contact a Public Affairs Officer


To top of page

Page Last Reviewed/Updated Thursday, March 26, 2026