Project Overview
In July 2026, Last Energy, Inc. submitted to the U.S. Nuclear Regulatory Commission (NRC) its Regulatory Engagement Plan, Revision 1.0, for its proposed PWR-20 small modular reactor. The proposed commercial reactor would use uranium dioxide fuel and light water as both the coolant and moderator, and would generate 20 megawatts of gross electrical power. The reactor would be located at Caldwell Site in Caldwell County, Texas. Last Energy engaged in pre-application activities with the NRC prior to a submission of its phased construction permit application in October 2026.
Additional information on pre-application activities can be obtained from ADAMS using a search by docket number Last Energy pre-application documents (NRC Docket 99902140).
To Subscribe to the Last Energy email service, select Last Energy from the Advanced Reactors List after entering your email into the GovDelivery system.
For information related to the NRC staff’s review of Last Energy’s limited work authorization request, submitted as the first part of its phased construction permit application, please see Last Energy – PWR-20 Limited Work Authorization Application.
Pre-Application Activities
| Product | Reference | Status | Type |
|---|---|---|---|
| Last Energy Regulatory Engagement Plan – Feb 2025 | Regulatory Engagement Plan | ML25038A060 | No Review Requested |
| Last Energy White Paper: Hermetically Sealed Containment | White Paper | ML25098A065 | Feedback Provided |
| Revised Last Energy White Paper: Hermetically Sealed Containment | White Paper | ML25146A001 | Feedback Provided |
| NRC-Last Energy initial technical pre-application meeting notice | Public Meeting Notice | ML26120A094 | No Review Requested |
| Last Energy Regulatory Engagement Plan, Revision 1.0 – July 2026 | Regulatory Engagement Plan | ML26217A115 | No Review Requested |
| NRC-Last Energy initial technical pre-application closed meeting summary | Meeting Summary | ML26246B019 | No Review Requested |
Contacts
| Contacts for the Last Energy Pre-Application Review | |
|---|---|
| Lead Project Manager | Zeinab Farahmandfar |
| Contact a Public Affairs Officer | |