Duke Energy Belews Creek, NC

subscribe to page updates

Graphic provided by Duke Energy Business Services displaying May and Propose advanced nuclear site near Belews Creek Stream Station
Graphic provided by Duke Energy Business Services

Who:

Duke Energy (Duke)

What:

Preapplication activities associated with a future ESP under 10 CFR Part 52

When:

Currently in preapplication period with plan for ESP submittal October 2025

Website:

https://www.duke-energy.com/our-company/about-us/power-plants

On this page:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in pre-application activities with Duke regarding a future ESP that would be at the Belews Creek, NC site for a small modular light water reactor (SMR) rated at approximately 300MWe gross electrical output.

Additional information on pre-application activities can be obtained from ADAMS using a search by docket number 99902121.

To subscribe to documents related to this project, visit GovDelivery

To top of page

Public Meeting Materials and Meeting Summaries

Meeting Date

Title

Meeting Materials / Meeting Summary

02/21/2024

Duke Energy Belews Creek Early Site Permit Pre-Application Meeting

ML24057A346
ML24051A023

12/12/2024

Duke Energy Belews Creek Site Environmental Review Progress meeting

ML24344A038
ML24344A268
ML24352A034

04/17/2025

Duke Energy Belews Creek Site Early Site Permit pre-application meeting on Site Selection Process

ML25101A257

04/17/2025

Duke Energy, Summary of Public Meeting with Duke Energy Belews Creek NC Site Selection Process

ML25108A089

To top of page

Audits and Audit Reports

Title

Status/Report

NRC Audit of Subsurface Investigation Activities at the Belews Creek, North Carolina (NC) Nuclear Project Site

ML24214A206

To top of page

Exemption Requests

Title

Reference

Status/Report

There is no content at this time.

To top of page

Inspection Reports

Title

Status/Report

NRC Audit of Subsurface Investigation Activities at the Belews Creek, North Carolina (NC) Nuclear Project Site

ML24214A206

To top of page

Contacts

Contacts for Duke Energy Belews Creek, NC SMR Pre-application Review Activities

Lead Project Manager

Emmanuel Sayoc

Safety Project Manager

TBD

Environmental Project Manager

Mary Richmond

Contact a Public Affairs Officer

To top of page

Page Last Reviewed/Updated Friday, December 12, 2025