TerraPower, LLC -- Kemmerer Power Station Unit 1 Application Documents
The following table provides access to the construction permit application for Kemmerer Power Station and other documents that TerraPower, LLC has submitted to support the review of the application. Key documents published by the NRC as part of the application review are also listed.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
Date |
Description |
Status |
08/13/2024 |
Summary of Scoping Meeting Related to the Environmental Scoping Process for the US SFR Owner, LLC Construction Permit for Kemmerer Unit 1 |
Issued |
07/15/2024 |
US SFR Owner, LLC - Plan for a General Audit of the Kemmerer Unit 1 Construction Permit Application |
Issued |
06/12/2024 |
US SFR Owner, LLC.; Kemmerer Power Station Unit 1; Notice of Intent To Conduct Scoping Process and Prepare Environmental Impact Statement |
Issued |
06/12/2024 |
US SFR OWNER, LLC – Kemmerer Power Station Unit 1 Construction Permit Application Review Schedule and Resource Estimate |
Issued |
06/04/2024 |
Federal Register Notice: General Notice. US SFR Owner, LLC (USO) - Acceptance and Notice of Hearing for Kemmerer Power Station Unit 1 Construction Permit Application |
Issued |
05/21/2024 |
USO - TerraPower - Construction Permit Application - Kemmerer 1 - Acceptance Review Letter |
Issued |
05/14/2024 |
US SFR Owner, LLC; Construction Permit Application Receipt Federal Register Notice |
Issued |
03/28/2024 |
TerraPower, LLC, Submittal of the Construction Permit Application for the Natrium Reactor Plant, Kemmerer Power Station, Unit 1 |
Received |