Duke Energy's, Belews Creek Early, N.C., Site Early Permit Application

Image
Duke Energy’s, Belews Creek, N.C., Site Early Site Permit Application


Photo provided by Duke Energy

Who:   Duke Energy
What:   Application for an Early Site Permit
When:   Application submitted December 30, 2025; application accepted and currently under review,
February 2025 - May 2027 (estimated)
Website:   www.duke-energy.com/stokes

On this page:

For additional detail, see the following related pages:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently reviewing the Duke Energy's Early Site Permit (ESP) application for the Belews Creek Site in Stokes County, North Carolina.

Additional information on pre-application activities can be obtained from ADAMS using a search by docket number 99902121. Additional information on application activities can be obtained from ADAMS using a search by docket number 05200055.

Federal Register Notices related to this ESP application are available on the federal rulemaking website by searching for docket ID NRC-2025-2161.

To top of page

Key Events and Milestones

Key Event or Milestone Completion Date
Actual - A
Target - T
Federal Register Notice of Receipt and Availability Duke Energy Corporation; Belews Creek Early Site Permit Application (91 FR 542) issued. January 7, 2026 – A
Duke Energy - Application for an Early Site Permit for the Duke Energy Belews Creek, NC Site (ML25364A005), Enclosure 2 (ML25364A006) received. December 30, 2025 – A
Federal Register Notice of Receipt and Availability Duke Energy Corporation; Belews Creek Early Site Permit Application (91 FR 5111), week 1, issued. February 4, 2026 – A
Belews Creek Early Site Permit Application Acceptance and Opportunity for Hearing (ML26016A623). February 9, 2026 – A 
Federal Register Notice of Belews Creek Early Site Permit Application Acceptance and Opportunity for Hearing (91 FR 5787) issued (ML26016A625). February 9, 2026 – A 
Federal Register Notice of Receipt and Availability Duke Energy Corporation; Belews Creek Early Site Permit Application (91 FR 6268), week 2, issued. February 11, 2026 – A
Federal Register Notice of Receipt and Availability Duke Energy Corporation; Belews Creek Early Site Permit Application (91 FR 7546), week 3, issued. February 18, 2026 – A
Federal Register Notice of Receipt and Availability Duke Energy Corporation; Belews Creek Early Site Permit Application (91 FR 9303), week 4, issued. February 25, 2026 – A
Safety Review
Draft Safety Evaluation — Safety Evaluation sections drafted, and information gaps identified. August 2026 - T
Advanced Safety Evaluation — Begin NRC management, legal, and Advisory Committee on Reactor Safeguards review of SE sections. March 2027 - T
Final Safety Evaluation — Final Safety Evaluation updated and issued. May 2027 - T
Environmental Review
Issue Draft Environmental Impact Statement. February 2027 - T
Final Environmental Impact Statement. May 2027
Hearing TBD
ESP Decision TBD

To top of page

Topical Reports

Submittal Date Title Reference Status
None at this time.

To top of page

Public Meeting Materials and Meeting Summaries

Meeting Date Title
None at this time.

To top of page

Audits and Audit Reports

Date Title
02/23/2026 Duke Energy Belews Creek Early Site Permit Application Audit Plan (ML26042A256), issued.

To top of page

Exemption Requests

Title Status/Report
None at this time.

To top of page

Contacts

Contacts for Duke Energy’s Belews Creek, N.C., Site
Safety Project Manager (lead) Emmanuel Sayoc
Safety Project Manager (co-lead) India Banks
Environmental Project Manager Bill Burris
Contact a Public Affairs Officer

To top of page

Page Last Reviewed/Updated Thursday, April 30, 2026

Page Last Reviewed/Updated Thursday, April 30, 2026