By default, this page lists all upcoming meetings (From date = today). You can search via keywords as well as date ranges for past or upcoming meetings. Click Reset to return the list to all upcoming meetings.
Displaying 81 - 100 of 110
Discussion between Dominion and NRC staff to identify issues to support timely submittal and review of the North Anna SLRA
Participation: Category 1
The applicant and the agency will be discussing the expected content of the forthcoming application from Dominion Energy for the Subsequent License Renewal for North Anna Power Station, Units 1 and 2.
Participation: Category 1
The U.S. Nuclear Regulatory Commission (NRC) will have a virtual meeting using Skype to discuss the NRC's assessment of safety performance at the Surry and North Anna Power Stations for 2019.
Participation: Category 3
The U.S. Nuclear Regulatory Commission will conduct a scoping process to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the subsequent license renewal of the operating licenses for North Anna Power Station,…
Participation: Category 3
Oral Argument in the Matter of Virginia Electric and Power Company (North Anna Power Station, Units 1 and 2)
Participation: Open
The U.S. Nuclear Regulatory Commission (NRC) will hold a webinar to discuss the NRC's assessment of safety performance at the V. C. Summer, North Anna and Surry Power Stations for 2020.
Participation: Information with Q&A
To discuss Dominion's responses to Select NRC RAIs associated with the safety review of the North Anna Subsequent License Renewal Application. To enable the staff to gain a better understanding of Dominion's approach to aging management and to formulate a pathforward.…
Participation: Observation
To discuss Virginia Electric and Power Company's (Dominion Energy's) responses to select NRC requests for additional information (RAIs) associated with the safety review of the North Anna Power Station, Units 1 and 2 (NAPS) Subsequent License Renewal Application (SLRA).…
Participation: Observation
Meeting Canceled
To discuss Virginia Electric and Power Company's (Dominion Energy's) responses to select NRC requests for additional information (RAIs) associated with the safety review of the North Anna Power Station, Units 1 and 2 (NAPS) Subsequent License Renewal Application (SLRA).…
Participation: Observation
Time Change
To discuss Virginia Electric and Power Company's (Dominion Energy's) responses to select NRC requests for additional information (RAIs) associated with the safety review of the North Anna Power Station, Units 1 and 2 (NAPS) Subsequent License Renewal Application (SLRA).…
Participation: Observation
To discuss Virginia Electric and Power Company's (Dominion Energy's) responses to select NRC requests for additional information (RAIs) associated with the safety review of the North Anna Power Station, Units 1 and 2 (NAPS) Subsequent License Renewal Application (SLRA).…
Participation: Observation
To provide the preliminary results of the NRC staff's environmental review of the Subsequent License Renewal Application for North Anna Power Station, Units 1 and 2, as documented in its draft Supplemental Environmental Impact Statement (DSEIS) and provide an opportunity for…
Participation: Comment-Gathering
ACRS Subcommittee meeting on Review the North Anna Subsequent License Renewal Application
Participation: Open
Affirmation: a)Turkey Pt 3&4 LBP-19-3, LBP-19-6 & LBP-19-8. b)Oconee 1,2,&3; Peach Bottom 2&3; Turkey Pt 3&4; Pt Beach 1&2; North Anna 1&2 Subsequent License Renewals. c) Peach Bottom 2&3 Beyond Nuclear New Contention & Reopen (Tent)
Participation: Open
Affirmation: a)Turkey Pt 3&4 LBP-19-3, LBP-19-6 & LBP-19-8. b)Oconee 1,2,&3; Peach Bottom 2&3; Turkey Pt 3&4; Pt Beach 1&2; North Anna 1&2 Subsequent License Renewals. c) Peach Bottom 2&3 Beyond Nuclear New Contention & Reopen (Tent)
Participation: Open
The U.S. Nuclear Regulatory Commission (NRC) will hold an open forum to discuss the NRC’s assessment of safety performance for 2021 at the North Anna Power Station and Surry Power Station.
Participation: Information with Q&A
Time Change
To discuss a planned Emergency Preparedness submittal for the North Anna Power Station and the Surry Power Station
Participation: Observation
The U.S. Nuclear Regulatory Commission (NRC) will hold an open forum to discuss the NRC’s assessment of safety performance for 2022 at the North Anna Power Station and Surry Power Station.
Participation: Information with Q&A
The meeting is to discuss a license amendment request submitted by Virginia Electric and Power Company that is currently under review. The amendment would revise emergency plan staff augmentation times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1…
Participation: Observation
The meeting is to discuss a license amendment request submitted by Virginia Electric and Power Company that is currently under review. The amendment would revise emergency plan staff augmentation times for North Anna Power Station Units 1 and 2 and Surry Power Station Units 1…
Participation: Observation