By default, this page lists all upcoming meetings (From date = today). You can search via keywords as well as date ranges for past or upcoming meetings. Click Reset to return the list to all upcoming meetings.
Displaying 1 - 20 of 28
The U. S. Nuclear Regulatory Commission (NRC) will meet with PPL to discuss the NRC’s assessment of safety performance at the Susquehanna Steam Electric Station for 2013, as described in the annual assessment letter dated March 4, 2014. PPL will be given the opportunity to…
Participation: Category 1
The purpose of this meeting is to discuss PPL Susquehanna, LLC's plans and schedule regarding a future submittal of a license transfer license amendment request. PPL Susquehanna and Riverstone Holdings, LLC, have announced a definitive agreement to combine their merchant…
Participation: Category 1
To discuss the U.S. Army Corps of Engineers flooding hazard reevaluation for the Susquehanna River associated with Peach Bottom Atomic Power Station Units 2 and 3.
Participation: Category 1
Susquehanna Steam Electric Station Unit 2 to discuss with PPL results of the NRC's Supplemental Inspection Procedure 95002
Participation: Category 1
Affirmation Session (Public Meeting) (Tentative)
a. Final Rule: Revisions to Transportation Safety Requirements and Harmonization with International Atomic Energy Agency Transportation Requirements (RIN 3150-AI11) (Tentative)
b. Nuclear Innovation North America, LLC…
Participation: Open
The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRC’s assessment of safety performance at Susquehanna Steam Electric Station for 2014, as described in the annual assessment letter dated March 4, 2015. The NRC will respond to questions on…
Participation: Category 3
To discuss changes that were made to the Susquehanna Steam Electric Station, Units 1 and 2 Emergency Action Level (EAL) Basis document since the submittal of a license amendment request to adopt an EAL Scheme in accordance with Nuclear Energy Institute (NEI) 99-01, Rev. 6.
Participation: Category 1
The purpose of this meeting is to discuss a Request for Additional Information with Susquehanna Nuclear, LLC related to a license amendment request submitted by letter dated October 27, 2014, requesting the adoption of TSTF-425, "Relocate Surveillance Frequencies to Licensee…
Participation: Category 1
The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRC’s assessment of safety performance at Susquehanna Steam Electric Station for 2015, as described in the annual assessment letter dated March 2, 2016. The NRC will respond to questions on…
Participation: Category 3
Commission Meeting: Affirmation Session: Susquehanna Nuclear, LLC (Susquehanna Steam Electric Station, Units 1 and 2) Appeal of LBP-16-12 (Affirming Denial of Access to SUNSI) and Request for Hearing (Tentative)
Participation: Open
The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRC’s assessment of safety performance at Susquehanna Steam Electric Station for 2016, as described in the annual assessment letter dated March 1, 2017. The NRC will respond to questions on…
Participation: Category 3
The purpose of this pre-submittal meeting with Susquehanna Nuclear, LLC is to discuss a proposed license amendment requests for the proposed incorporation of TSTF-542, "Reactor Pressure Vessel Water Inventory Controls," for the Susquehanna Steam Electric Station, Units…
Participation: Category 1
Meeting Canceled
The purpose of this pre-submittal meeting with Susquehanna Nuclear, LLC is to discuss the license amendment request submittal and the review of the analytical methods regarding the transition to allow the use of Atrium 11 fuel for the Susquehanna Steam Electric Station, Units 1…
Participation: Category 1
The U. S. Nuclear Regulatory Commission (NRC) will meet with the public to discuss the NRC’s assessment of safety performance at Susquehanna Steam Electric Station for 2017, as described in the annual assessment letter dated February 28, 2018. The NRC will respond to questions on…
Participation: Category 3
This is a pre-submittal meeting with Susquehanna Nuclear, LLC to discuss a license amendment request submittal regarding emergency service water piping replacement for the Susquehanna Steam Electric Station, Units 1 and 2.
Participation: Category 1
The purpose of this meeting is for a pre-submittal discussion with the licensee regarding its proposal for a license amendment request related to the use of Framatome Atrium 11 fuel at Susquehanna Steam Electric Station, Units 1 and 2.
Participation: Category 2
NRC staff will host a webinar to present the NRC's assessment of safety performance at Beaver Valley, Limerick, Peach Bottom, Susquehanna, and Three Mile Island for 2018, as described in the 2018 annual assessment letters. Following the presentation, the NRC will respond to…
Participation: Category 3
Discussion with Talen Energy regarding a potential license amendment request for Susquehanna Steam Electric Station, Units 1 and 2, related to emergency response organization staffing and augmentation changes.
Participation: Category 2
This is a pre-submittal meeting with Susquehanna Nuclear, LLC to discuss a license amendment request submittal regarding engineered safety features, Secondary Containment, and Control Room Habitability Envelope for the Susquehanna Steam Electric Station, Units 1 and 2.
Participation: Category 1
The purpose of this meeting is for Talen Energy to discuss with the NRC a Susquehanna Steam Electric Station, Units 1 and 2, proposed license amendment request to create a new condition for an inoperable manual synchronization circuit and institute a completion time of 14 days to…
Participation: Category 1