Meeting Details
Category 1Date
June 29, 2017
Time
9:30 am–11:30 am EDT
Location
NRC One White Flint North
11555 Rockville Pike, 9B-4
Rockville, MD
Agenda
Meeting Info
Purpose
The purpose of this pre-submittal meeting, between FirstEnergy Nuclear Operating Company (FENOC) and the U.S. Nuclear Regulatory Commission (NRC), is to discuss FENOC's planned license amendment request to revise the flooding licensing basis for the Perry Nuclear Power Plant site.
Docket
05000440
-
Perry 1
Documents
| Document Title | Description |
|---|---|
| ML17164A089 | 06/29/2017 Pre-Submittal Meeting with FirstEnergy Nuclear Operating Company Regarding a Planned Change to the Licensing Basis for Flooding |
Participants
NRC Staff
External Participants
FirstEnergy Nuclear Operating Company (FENOC)
Christopher Cook
Barbara Hayes
Phil Lashley
Tom Lentz
Dan Hoang
Ben Huck
Brad Harvey
John Sabo
Kathy Nevins
Kevin Quinlan
Mark Bensi
Steve Osting
Warren Sharp
Contact
Kimberly Green
(301) 415-1627