Meeting Details
Category 1Date
September 29, 2015
Time
10:00 am–11:00 am EDT
Location
NRC One White Flint North
11555 Rockville Pike, O-8B6
Rockville, MD
Agenda
Meeting Info
Purpose
The purpose of this meeting is to discuss Perry Nuclear Power Plant, Unit 1's upcoming license amendment request to change its current emergency action levels using the guidance of NEI 99-01, Revision 6, "Development of Emergency Action Levels for Non-Passive Reactors."
Docket
05000440
-
Perry 1
Documents
| Document Title | Description |
|---|---|
| ML15261A628 | 09/29/2015 Pre-Application Meeting with FENOC Regarding Perry Nuclear Power Plant, Unit 1's Request to Change Emergency Action Levels |
Participants
Office of Nuclear Reactor Regulation
Office of Nuclear Security and Incident Response
External Participants
FirstEnergy Nuclear Operating Company (FENOC)
Phil Lashley
Don Johnson
Kimberly Green
Ray Hoffman
Contact
Kimberly Green
(301) 415-1627
Allison Dietrich
(301) 415-2846