United States Nuclear Regulatory Commission - Protecting People and the Environment

Application Review Schedule for Smith Ranch Highland

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Power Resources, Inc. submitted to renew its license for the Smith Ranch Highland In Situ Recovery (ISR) site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 02/1/2012 – A
Acceptance Review
Acceptance Review Start
02/9/2012 – A
Docketing Decision Letter Issued/Acceptance Review Complete
07/5/2012 – A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
05/02/2013 – A
RAI response received from applicant
04/21/2015 – A
2nd round of RAIs issued to Applicant
08/07/2015 – A
Acceptance Review of Round 1 of RAIs complete
04/29/2016 – A
Receive complete RAI response from Applicant
01/19/2018 – T **
Safety Evaluation Report (SER) completed
09/25/2018 – T **
Environmental Review *
RAIs Issued
05/02/2013 – A
Draft EA issued
07/31/2018 – T **
Final EA issued
09/20/2018 – T **
License
Licensing Action Completed – License Issued
09/27/2018 – T **

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.

** NRC staff identified this as the latest date it could receive the the RAI responses from the licensee and be able to complete its review prior to the relinquishment of oversight of this facility to the State of Wyoming.

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

Page Last Reviewed/Updated Tuesday, December 05, 2017