Application Review Schedule for Lost Creek
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Lost Creek ISR, LLC submitted to obtain a license for its Lost Creek In Situ Recovery site.
Key Milestones | Completion Date Actual - A Target - T |
Application Tendered | 10/30/07 – A |
Application Withdrawn | 2/29/08 – A |
Application Resubmitted | 3/20/08 – A |
Acceptance Review |
Acceptance Review Start | 3/20/08 – A |
Docketing Decision Letter Issued/Acceptance Review Complete | 6/10/08 – A |
Safety Review |
Requests for Additional Information (RAIs) Issued to Applicant | 11/6/08 – A |
Final Safety Evaluation Report (SER) completed | 8/5/11 – T |
Environmental Review |
RAIs Issued to Applicant | 3/16/09 – A |
Draft SEIS issued to EPA | 12/11/09 – A |
Public comment period | 3/31/10 – A |
Final SEIS issued to EPA | 6/24/11 – A |
License |
Licensing Action Completed | 8/5/11 – T |
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.