Key Milestones Completion Date
Actual – A
Target – T
Application Tendered 05/14/14 – A
Acceptance Review
Acceptance Review Start 08/11/14 – A
Supplemental Application received 10/29/14 – A
04/13/15 – A
06/26/15 – A
Docketing Decision Issued/Acceptance Review Complete 08/10/15 – A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant 01/21/16 – A
RAI Acceptance Review complete 09/09/16 – A
Safety Evaluation Report (SER) completed 01/24/17 – A
Environmental Review
RAIs Issued to Applicant 01/21/16 - A
Draft Environmental Assessment (EA) Issued 12/20/16 – A
Final EA issued 03/23/17 – T
License
License Amendment issued 03/31/17 – T

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.