Skip to main content

Safety Evaluations with Open Items

Safety Evaluations with Open Items for Comanche Peak Nuclear Power Plant, Units 3 and 4 Application

The following table provides access to Safety Evaluations with Open Items that the NRC has issued in connection with its review of the COL application that Luminant submitted for Comanche Peak Nuclear Power Plant, Units 3 & 4.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

ChapterDescriptionDate
1Introduction and General Description of PlantTBD
2Sections 2.0 through 2.303/29/13
3Design of Structures, Components, Equipment, and SystemsTBD
4Reactor10/17/12
5Reactor Coolant Connecting Systems04/28/11
6Engineered Safety Features08/02/13
7Instrumentation and Controls Systems03/26/13
8Electric Power07/05/11
9Auxiliary Systems08/02/13
10Steam and Power Conversion Systems07/21/11
11Radioactive Waste Management09/20/11
12Radiation Protection09/28/11
13Conduct of Operations12/06/11
14Initial Test ProgramTBD
15Accident and Analysis06/25/12
16Technical Specifications02/14/13
17Quality Assurance01/04/13
18Human Factors EngineeringTBD
19Probabilistic Risk Assessment and Severe Accident Evaluation02/06/13