Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 0 2021-10-10 Refueling Outage
Calvert Cliffs 1 100 *
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100 *
Limerick 2 100 *
Millstone 2 0 2021-10-08 Refueling Outage *
Millstone 3 100
Nine Mile Point 1 98 Reduced Power due to condenser fouling.
Nine Mile Point 2 100
Peach Bottom 2 100
Peach Bottom 3 0 2021-10-25 Refueling Outage *
Salem 1 100
Salem 2 0 2021-10-02 Refueling Outage
Seabrook 1 7 Increasing Power *
Susquehanna 1 100 *
Susquehanna 2 100 *

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 100
Catawba 1 70 Increasing Power *
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 100
North Anna 2 97 Plant Computer Maintenance
Oconee 1 100
Oconee 2 93 Coastdown To Refueling Outage *
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 0 2021-10-02 Refueling Outage
Summer 0 2021-10-09 Refueling Outage
Surry 1 100
Surry 2 0 2021-10-24 Refueling Outage - Defueled
Turkey Point 3 0 2021-10-09 Refueling Outage
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 0 2021-10-29 Refueling Outage
Watts Bar 2 95 Holding power due to S/G conditions

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 0 2021-10-18 Refueling Outage - Rx startup in progress. Rx is critical in the intermediate range. *
Byron 1 100 *
Byron 2 100 *
Clinton 94 Increasing power after final rod pattern adjustment *
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 80 Coastdown to Refueling Outage
Dresden 3 100
Fermi 2 100
LaSalle 1 100 *
LaSalle 2 100 *
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100
Point Beach 2 47 Chemistry hold *
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 86 De-rated for load following *
Quad Cities 2 91 De-rated for load following *

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 0 2021-09-25 Refueling Outage *
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 0 2021-10-03 Refueling Outage - core reload complete *
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100 *
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 0 2021-10-09 Refueling Outage
Palo Verde 3 100
River Bend Station 1 100
South Texas 1 0 2021-10-09 Refueling Outage
South Texas 2 100
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.