Power Reactor Status Report for September 18, 2021

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 98 Coastdown To Refueling Outage
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 83 Reduced Power For Rod Pattern Adjustment *
Indian Point 2 0 2020-04-30 Reactor defueled for permanent shutdown
Indian Point 3 0 2021-05-01 Reactor defueled for permanent shutdown
Limerick 1 90 Reduced Power For Turbine Valve Testing *
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Peach Bottom 2 77 Reduced Power For Planned Load Drop *
Peach Bottom 3 92 Coastdown To Refueling Outage *
Salem 1 100
Salem 2 92 Coastdown To Refueling Outage *
Seabrook 1 100
Susquehanna 1 100
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 60 Reduced Power For Rod Pattern Adjustment & Testing *
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 94 Reduced Power For Bypass Valve Testing *
Hatch 2 100
McGuire 1 100
McGuire 2 0 2021-09-11 Refueling Outage
North Anna 1 0 2021-09-11 Reduced Power For Planned Maintenance
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 0 2021-08-28 Refueling Outage *
Sequoyah 1 100
Sequoyah 2 85 Coastdown to Refueling Outage
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 0 2021-09-12 Refueling Outage
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 0 2021-09-11 Planned Maintenance Outage

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 0 2021-09-13 Refueling Outage
Byron 2 100
Clinton 94 Coastdown To Refueling Outage
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Fermi 2 100 *
LaSalle 1 100
LaSalle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100
Point Beach 2 93 Coastdown to Refueling Outage *
Prairie Island 1 100
Prairie Island 2 83 Coastdown To Refueling Outage
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 75 Coastdown To Refueling Outage *
Callaway 100
Columbia Generating Station 84 Reduced Power For Rod Pattern Adjustment *
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend Station 1 100
South Texas 1 100
South Texas 2 100
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.