Power Reactor Status Report for April 13, 2021

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 0 2021-04-11 Refueling Outage *
Beaver Valley 2 100 *
Calvert Cliffs 1 100 *
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 75 Coastdown To Refueling Outage *
Indian Point 2 0 2020-04-30 Reactor defueled for permanent shutdown
Indian Point 3 83 Coastdown To Refueling Outage *
Limerick 1 100
Limerick 2 79 Coastdown To Refueling Outage *
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 75 Increasing Power *
Nine Mile Point 2 100
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100 *
Salem 2 100 *
Seabrook 1 100 One contingency from downpower to 1100 MWe.
Susquehanna 1 100 *
Susquehanna 2 0 2021-03-22 Refueling Outage *

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 0 2021-02-26 Refueling Outage
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 98 Holding Power *
Catawba 1 100
Catawba 2 0 2021-03-28 Refueling Outage
Farley 1 0 2021-03-22 Refueling Outage
Farley 2 100
Harris 1 98 Coastdown To Refueling Outage *
Hatch 1 100
Hatch 2 99 Reduced Power For Rod Pattern Adjustment *
McGuire 1 100
McGuire 2 100
North Anna 1 0 2021-03-14 Refueling Outage
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 0 2021-04-10 Refueling Outage *
Saint Lucie 2 100
Sequoyah 1 0 2021-04-10 Refueling Outage *
Sequoyah 2 100
Summer 100
Surry 1 96 Coastdown To Refueling Outage *
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 80 Reduced Power For Planned Maintenance *
Vogtle 2 100
Watts Bar 1 100
Watts Bar 2 90 Max Power until Steam Generator Replacement.

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 0 2021-04-05 Refueling Outage
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 99 Full Electrical Output
D.C. Cook 1 100 *
D.C. Cook 2 100 *
Davis-Besse 100 *
Dresden 2 100 High System Voltage Action
Dresden 3 100 High System Voltage Action
Fermi 2 100
LaSalle 1 100 *
LaSalle 2 0 2021-02-22 Refueling Outage, *
Monticello 81 Coastdown To Refueling Outage
Palisades 100
Perry 1 100 *
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 0 2021-04-10 Refueling Outage *
Arkansas Nuclear 2 100
Callaway 0 2020-12-25 See EN# 55049
Columbia Generating Station 92 Coastdown To Refueling Outage
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 0 2021-02-04 Forced Outage and Refueling Outage
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 0 2021-04-10 Refueling Outage
River Bend Station 1 100
South Texas 1 100
South Texas 2 0 2021-03-20 Refueling Outage
Waterford 3 100 *
Wolf Creek 1 0 2021-03-25 Refueling Outage

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.