UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Beaver Valley 1 |
60 |
|
TESTING SECONDARY SAFETIES |
* |
|
| Beaver Valley 2 |
100 |
|
|
|
|
| Calvert Cliffs 1 |
0 |
2012-02-05 |
REFUELING OUTAGE
HEAT UP IN PROGRESS |
|
|
| Calvert Cliffs 2 |
100 |
|
|
* |
|
| FitzPatrick |
100 |
|
|
|
|
| Ginna |
100 |
|
|
|
|
| Hope Creek 1 |
96 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
| Indian Point 2 |
90 |
|
HOLDING FOR FUEL CONDITIONING |
* |
|
| Indian Point 3 |
100 |
|
138 KV AUX TRANSFORMER OOS |
* |
|
| Limerick 1 |
100 |
|
|
|
|
| Limerick 2 |
100 |
|
|
|
|
| Millstone 2 |
100 |
|
|
|
|
| Millstone 3 |
100 |
|
|
|
|
| Nine Mile Point 1 |
100 |
|
|
|
|
| Nine Mile Point 2 |
95 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
| Oyster Creek |
100 |
|
|
|
|
| Peach Bottom 2 |
100 |
|
|
|
|
| Peach Bottom 3 |
100 |
|
|
|
|
| Pilgrim 1 |
100 |
|
|
|
|
| Salem 1 |
100 |
|
|
|
|
| Salem 2 |
100 |
|
|
|
|
| Seabrook 1 |
85 |
|
HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT |
|
|
| Susquehanna 1 |
0 |
2012-03-31 |
REFUELING OUTAGE |
|
|
| Susquehanna 2 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
* |
|
| Three Mile Island 1 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
|
|
| Vermont Yankee |
100 |
|
|
|
|
Region 2
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Browns Ferry 1 |
100 |
|
|
|
|
| Browns Ferry 2 |
100 |
|
|
|
|
| Browns Ferry 3 |
0 |
2012-04-07 |
REFUELING OUTAGE |
* |
|
| Brunswick 1 |
0 |
2012-02-23 |
REFUELING OUTAGE |
|
|
| Brunswick 2 |
100 |
|
|
|
|
| Catawba 1 |
0 |
2012-04-04 |
SEE EN #47805 |
|
|
| Catawba 2 |
0 |
2012-03-10 |
|
|
|
| Crystal River 3 |
0 |
2009-09-25 |
DEFUELED - CONTAINMENT TENSIONING ON HOLD |
|
|
| Farley 1 |
0 |
2012-04-01 |
REFUELING OUTAGE - OFFLOAD IN PROGRESS |
* |
|
| Farley 2 |
100 |
|
|
|
|
| Harris 1 |
97 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
| Hatch 1 |
100 |
|
|
|
|
| Hatch 2 |
100 |
|
|
|
|
| McGuire 1 |
100 |
|
|
|
|
| McGuire 2 |
100 |
|
|
|
|
| North Anna 1 |
0 |
2012-03-10 |
REFUELING OUTAGE - HIGH SYSTEM VOLTAGE ACTION |
* |
|
| North Anna 2 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
* |
|
| Oconee 1 |
100 |
|
|
|
|
| Oconee 2 |
100 |
|
|
* |
|
| Oconee 3 |
83 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
| Robinson 2 |
100 |
|
|
|
|
| Saint Lucie 1 |
0 |
2012-04-07 |
SHUTDOWN FOR WATERBOX REPAIR |
|
|
| Saint Lucie 2 |
100 |
|
|
|
|
| Sequoyah 1 |
100 |
|
|
|
|
| Sequoyah 2 |
100 |
|
|
|
|
| Summer |
100 |
|
|
|
|
| Surry 1 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
* |
|
| Surry 2 |
98 |
|
CALORIMETRIC NON-FUNCTIONAL WHEN ON EXCESS LETDOWN
HIGH SYSTEM VOLTAGE ACTION |
* |
|
| Turkey Point 3 |
0 |
2012-02-26 |
DEFUELED |
|
|
| Turkey Point 4 |
100 |
|
|
|
|
| Vogtle 1 |
100 |
|
|
|
|
| Vogtle 2 |
100 |
|
|
|
|
| Watts Bar 1 |
100 |
|
|
|
|
Region 3
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Braidwood 1 |
100 |
|
|
|
|
| Braidwood 2 |
100 |
|
|
|
|
| Byron 1 |
100 |
|
FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.6% |
|
|
| Byron 2 |
100 |
|
FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.9% |
|
|
| Clinton |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
| D.C. Cook 1 |
100 |
|
HI VOLTAGE ACTION |
* |
|
| D.C. Cook 2 |
0 |
2012-03-21 |
DEFUELED
HI VOLTAGE ACTION |
* |
|
| Davis-Besse |
100 |
|
|
|
|
| Dresden 2 |
100 |
|
|
|
|
| Dresden 3 |
100 |
|
|
|
|
| Duane Arnold |
100 |
|
|
|
|
| Fermi 2 |
0 |
2012-03-25 |
REFUELING OUTAGE |
|
|
| Kewaunee |
0 |
2012-04-05 |
REFUEL OUTAGE |
|
|
| La Salle 1 |
100 |
|
|
|
|
| La Salle 2 |
100 |
|
|
|
|
| Monticello |
100 |
|
|
|
|
| Palisades |
60 |
|
COOLING TOWER REPLACEMENT |
|
|
| Perry 1 |
100 |
|
|
|
|
| Point Beach 1 |
100 |
|
|
|
|
| Point Beach 2 |
100 |
|
|
|
|
| Prairie Island 1 |
100 |
|
|
|
|
| Prairie Island 2 |
0 |
2012-02-21 |
DEFUELED |
|
|
| Quad Cities 1 |
100 |
|
MONITORING TURBINE VIBRATION |
|
|
| Quad Cities 2 |
0 |
|
REFUELING OUTAGE |
|
|
Region 4
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Arkansas Nuclear 1 |
100 |
|
|
|
|
| Arkansas Nuclear 2 |
100 |
|
|
|
|
| Callaway |
99 |
|
|
* |
|
| Columbia Generating Station |
85 |
|
DOWNPOWER FOR LOAD FOLLOWING |
|
|
| Comanche Peak 1 |
100 |
|
|
|
|
| Comanche Peak 2 |
99 |
|
|
|
|
| Cooper |
100 |
|
|
|
|
| Diablo Canyon 1 |
100 |
|
|
|
|
| Diablo Canyon 2 |
100 |
|
|
|
|
| Fort Calhoun |
0 |
2011-04-09 |
REFUELING OUTAGE |
|
|
| Grand Gulf 1 |
0 |
2012-02-19 |
REFUELING OUTAGE |
|
|
| Palo Verde 1 |
100 |
|
|
|
|
| Palo Verde 2 |
100 |
|
|
|
|
| Palo Verde 3 |
0 |
2012-03-16 |
REFUELING OUTAGE - CORE RELOAD COMPLETED |
|
|
| River Bend 1 |
100 |
|
|
|
|
| San Onofre 2 |
0 |
2012-01-09 |
REFUELING OUTAGE |
|
|
| San Onofre 3 |
0 |
2012-01-31 |
FORCED OUTAGE - S/G REPAIR |
|
|
| South Texas 1 |
100 |
|
|
|
|
| South Texas 2 |
0 |
2011-11-28 |
MAINTENANCE OUTAGE |
|
|
| Waterford 3 |
35 |
|
FW PUMP TRIP |
* |
|
| Wolf Creek 1 |
100 |
|
|
|
|
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.