Power Reactor Status Report for April 02, 2012

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 96 COASTDOWN TO REFUELING OUTAGE
Beaver Valley 2 100
Calvert Cliffs 1 0 2012-02-05 REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION
Calvert Cliffs 2 100 HIGH SYSTEM VOLTAGE ACTION
FitzPatrick 15 REDUCED POWER TO INVESTIGATE LOW LUBE ALARM ON RECIRC PUMP - WILL INCREASE POWER AFTER INERTING IS COMPLETED - GENERATOR ONLINE *
Ginna 100
Hope Creek 1 99 COASTDOWN TO REFUELING OUTAGE - HIGH SYSTEM VOLTAGE ACTION
Indian Point 2 30 HOLDING POWER FOR SECONDARY CHEMISTRY *
Indian Point 3 100
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 97 COASTDOWN TO REFUELING OUTAGE
Oyster Creek 100
Peach Bottom 2 100 #2 STARTUP SOURCE OUTAGE FOR PLANNED MAINTENANCE *
Peach Bottom 3 100 #2 STARTUP SOURCE OUTAGE FOR PLANNED MAINTENANCE *
Pilgrim 1 100
Salem 1 100
Salem 2 100
Seabrook 1 85 HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT.
Susquehanna 1 0 2012-03-31 REFUELING OUTAGE - HIGH SYSTEM VOLTAGE ACTION
Susquehanna 2 100 HIGH SYSTEM VOLTAGE ACTION
Three Mile Island 1 100 HIGH SYSTEM VOLTAGE ACTION *
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 94 COASTDOWN TO REFUELING OUTAGE *
Brunswick 1 0 2012-02-23 REFUELING OUTAGE
Brunswick 2 100
Catawba 1 100
Catawba 2 0 2012-03-10 FUEL LOADED
Crystal River 3 0 2009-09-25 DEFUELED - CONTAINMENT TENSIONING ON HOLD
Farley 1 0 2012-04-01 REFUELING OUTAGE *
Farley 2 100
Harris 1 100
Hatch 1 100 *
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 0 2012-03-10 REFUELING OUTAGE
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 89 COASTDOWN TO REFUELING OUTAGE *
Robinson 2 97 INCREASING POWER TO 100% *
Saint Lucie 1 0 2012-03-30 EXITING REFUELING OUTAGE *
Saint Lucie 2 100
Sequoyah 1 40 INCREASING POWER TO 100% *
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 0 2012-02-26 DEFUELED
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100 FEED WATER FLOW INVESTIGATION
Byron 2 100 FEED WATER FLOW INVESTIGATION
Clinton 97 100% ELECTRICAL CAPABILITY
D.C. Cook 1 100 *
D.C. Cook 2 0 2012-03-21 DEFUELED *
Davis-Besse 100 *
Dresden 2 100
Dresden 3 100
Duane Arnold 100
Fermi 2 0 2012-03-25 REFUELING OUTAGE
Kewaunee 100
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 60 COOLING TOWER REPLACEMENT
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 0 2012-02-21 DEFUELED
Quad Cities 1 100 MONITORING TURBINE VIBRATION
Quad Cities 2 0 REFUELING OUTAGE

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 0 2012-04-01 MAINTENANCE OUTAGE *
Cooper 100
Diablo Canyon 1 55 BACKWASHING MAIN CONDENSER; MORRO BAY MIDWAY #1 230 KV LINE OOS FOR MAINTENANCE TILL JUNE *
Diablo Canyon 2 100 MORRO BAY MIDWAY #1 230 KV LINE OOS FOR MAINTENANCE TILL JUNE *
Fort Calhoun 0 2011-04-09 REFUELING OUTAGE
Grand Gulf 1 0 2012-02-19 REFUELING OUTAGE
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 0 2012-03-16 LOADING FUEL IN CORE *
River Bend 1 100
San Onofre 2 0 2012-01-09 REFUELING OUTAGE
San Onofre 3 0 2012-01-31 FORCED OUTAGE - S/G REPAIR *
South Texas 1 100
South Texas 2 0 2011-11-28 MAINTENANCE OUTAGE
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.