Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 16 INCREASING POWER *
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100 MAIN GENERATOR VOLTAGE REGULATOR IN MANUAL
Ginna 100
Hope Creek 1 99 *
Indian Point 2 100
Indian Point 3 100
Limerick 1 100
Limerick 2 0 2011-03-27 REFUELING OUTAGE
Millstone 2 0 2011-04-02 DEFUELED *
Millstone 3 100
Nine Mile Point 1 0 2011-03-20 REFUELING OUTAGE
Nine Mile Point 2 100
Oyster Creek 100
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 86 COASTDOWN TO REFUELING OUTAGE
Salem 1 100 500 KV LINE OUTAGE
Salem 2 0 2011-04-09 REFUELING OUTAGE. 500 KV LINE OUTAGE
Seabrook 1 0 2011-03-31 DEFUELED *
Susquehanna 1 99 100% ELECTRICAL CAPABILITY
Susquehanna 2 0 2011-04-04 REFUELING OUTAGE
Three Mile Island 1 100
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100 *
Browns Ferry 3 100
Brunswick 1 100
Brunswick 2 23 SYNCED TO THE GRID *
Catawba 1 100
Catawba 2 100
Crystal River 3 0 2009-09-25 MAINTENANCE OUTAGE - CONTAINMENT TENSIONING ON HOLD
Farley 1 100 500 KV OFFSITE LINE OOS FOR PLANNED MAINTENANCE UNTIL 5/6
Farley 2 100 500 KV OFFSITE LINE OOS FOR PLANNED MAINTENANCE UNTIL 5/6
Harris 1 100
Hatch 1 96 ROD PATTERN ADJUSTMENT *
Hatch 2 0 2011-03-28 REFUELING OUTAGE
McGuire 1 49 FEEDWATER PUMP MAINT *
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 0 2011-04-01 REFUELING OUTAGE - DEFUELED
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 0 2011-01-02 EXITING REFUELING OUTAGE
Sequoyah 1 100
Sequoyah 2 100
Summer 0 2011-04-15 ENTERING REFUELING OUTAGE *
Surry 1 100
Surry 2 98 100% ELECTRICAL CAPABILITY
Turkey Point 3 100
Turkey Point 4 0 2011-03-20 REFUELING OUTAGE - FUEL LOAD COMPLETE
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 0 2011-04-03 REFUELING OUTAGE

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 98 COASTDOWN TO REFUELING OUTAGE *
Byron 1 0 2011-03-13 REFUELING OUTAGE - FUEL RELOAD COMPLETED
Byron 2 100
Clinton 97 100% ELECTRICAL CAPABILITY
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Duane Arnold 100
Fermi 2 100
Kewaunee 100
La Salle 1 100
La Salle 2 100
Monticello 0 2011-03-04 REFUELING OUTAGE
Palisades 100
Perry 1 85 COASTDOWN TO REFUELING OUTAGE *
Point Beach 1 98 REDUCED POWER FOR AUX FEED PUMP TESTING *
Point Beach 2 0 2011-02-28 REFUELING OUTAGE
Prairie Island 1 100
Prairie Island 2 50 REDUCED POWER FOR STOP VALVE TESTING - WILL COMMENCE POWER INCREASE TO 100% IN APPROX 10 MINUTES *
Quad Cities 1 100 *
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 0 2011-04-02 REFUELING OUTAGE
Comanche Peak 1 100
Comanche Peak 2 0 2011-04-03 CORE RELOAD COMPLETED *
Cooper 0 2011-03-12 REFUELING OUTAGE
Diablo Canyon 1 100
Diablo Canyon 2 100
Fort Calhoun 0 2011-04-09 REFUELING OUTAGE
Grand Gulf 1 96 POWER LIMITED 2ND STAGE MSR OUT OF SERVICE FOR THE ENTIRE CYCLE
Palo Verde 1 99 REDUCED POWER IN PREPARATION FOR MTC TESTING ON 4/17 *
Palo Verde 2 0 2011-04-01 DEFUELED
Palo Verde 3 100
River Bend 1 66 REDUCED POWER FOR SCHEDULED CONTROL ROD SEQUENCE EXCHANGE *
San Onofre 2 98 REDUCED POWER FOR HIGH PRESSURE STOP AND GOVERNOR VALVE TESTING *
San Onofre 3 100
South Texas 1 0 2011-04-02 DEFUELED *
South Texas 2 100
Waterford 3 0 2011-04-05 REFUELING OUTAGE - CORE OFFLOAD IN PROGRESS *
Wolf Creek 1 0 2011-03-18 DEFUELED

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.