Power Reactor Status Report for February 24, 2010

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 0 2010-02-18 REFUELING OUTAGE *
Calvert Cliffs 2 0 2010-02-18 DUAL UNIT TRIP. SEE EN# 45709
FitzPatrick 88 INCREASING POWER ROD PATTERN ADJUSTMENT *
Ginna 100
Hope Creek 1 100 500KV SWITCHYARD LINE 5023 OOS
Indian Point 2 100
Indian Point 3 100
Limerick 1 99 COASTDOWN TO REFUELING OUTAGE *
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Oyster Creek 100
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 100
Salem 2 100
Seabrook 1 100
Susquehanna 1 82 COASTDOWN TO REFUELING OUTAGE *
Susquehanna 2 94 100% ELECTRICAL CAPABILITY
Three Mile Island 1 100
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 95 COASTDOWN TO REFUELING OUTAGE *
Brunswick 2 100
Catawba 1 60 INCREASING POWER *
Catawba 2 100
Crystal River 3 0 2009-09-25 DEFUELED
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 0 2010-02-07 REFUELING OUTAGE
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 89 HOLDING POWER FOR PLANT TESTING *
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 97 100% ELECTRICAL CAPABILITY
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 92 END OF CYCLE COASTDOWN *
Dresden 2 100
Dresden 3 100 *
Duane Arnold 100
Fermi 2 100
Kewaunee 100
La Salle 1 0 2010-02-07 REFUELING OUTAGE
La Salle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100 345 KV LINE 111 OOS THRU END OF FEBRUARY
Point Beach 2 100 345 KV LINE 111 OOS THRU END OF FEBRUARY
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 50 PLANNED CIRCULATING WATER TUNNEL CLEANING
Diablo Canyon 2 100
Fort Calhoun 100
Grand Gulf 1 82 REPAIR MSR DRAIN TANK DRAIN VALVE STEAM LEAK *
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend 1 100
San Onofre 2 0 2009-09-26 REFUELING OUTAGE
San Onofre 3 100
South Texas 1 100
South Texas 2 100
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.