UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Beaver Valley 1 |
100 |
|
|
|
|
| Beaver Valley 2 |
0 |
2008-04-14 |
REFUELING OUTAGE |
|
|
| Calvert Cliffs 1 |
100 |
|
|
|
|
| Calvert Cliffs 2 |
100 |
|
|
|
|
| FitzPatrick |
100 |
|
|
|
|
| Ginna |
98 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
| Hope Creek 1 |
100 |
|
500 KV LINE #5021 OOS |
|
|
| Indian Point 2 |
8 |
|
HOLDING POWER TO RESOLVE RELAY ISSUE - GENERATOR OFFLINE |
* |
|
| Indian Point 3 |
100 |
|
|
|
|
| Limerick 1 |
100 |
|
|
|
|
| Limerick 2 |
100 |
|
|
|
|
| Millstone 2 |
0 |
2008-04-05 |
DEFUELED |
|
|
| Millstone 3 |
100 |
|
|
|
|
| Nine Mile Point 1 |
100 |
|
|
|
|
| Nine Mile Point 2 |
81 |
|
STARTUP TESTING IN PROGRESS |
* |
|
| Oyster Creek |
92 |
|
HOLDING POWER FOR CONTROL VALVE OSCILLATION PROBLEM AND FEEDWATER HEATER ISSUES |
|
|
| Peach Bottom 2 |
100 |
|
|
|
|
| Peach Bottom 3 |
100 |
|
|
|
|
| Pilgrim 1 |
100 |
|
|
|
|
| Salem 1 |
100 |
|
500 KV LINE OOS FOR MAINTENANCE |
|
|
| Salem 2 |
0 |
2008-03-11 |
DEFUELED - 500 KV LINE OOS FOR MAINTENANCE |
|
|
| Seabrook 1 |
0 |
2008-03-31 |
345 KV (BUS 2) OOS - EXPECT RETURN TO SERVICE ON 4/20 |
* |
|
| Susquehanna 1 |
72 |
|
HOLDING POWER FOR TESTING |
* |
|
| Susquehanna 2 |
100 |
|
VOLTAGE REGULATOR IN MANUAL |
|
|
| Three Mile Island 1 |
100 |
|
MINIMUM GENERATION ALERT FROM PJM - NO IMPACT ON PLANT |
* |
|
| Vermont Yankee |
100 |
|
|
|
|
Region 2
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Browns Ferry 1 |
69 |
|
REDUCED POWER FOR SCRAM TIME TESTING AND SCHEDULED MAINTENANCE |
* |
|
| Browns Ferry 2 |
100 |
|
|
|
|
| Browns Ferry 3 |
0 |
2008-03-18 |
REFUELING OUTAGE |
|
|
| Brunswick 1 |
0 |
2008-03-14 |
REFUELING OUTAGE |
|
|
| Brunswick 2 |
100 |
|
|
|
|
| Catawba 1 |
100 |
|
|
|
|
| Catawba 2 |
100 |
|
|
|
|
| Crystal River 3 |
100 |
|
|
|
|
| Farley 1 |
100 |
|
|
|
|
| Farley 2 |
100 |
|
|
|
|
| Harris 1 |
100 |
|
|
|
|
| Hatch 1 |
97 |
|
INCREASING POWER AT 1%/4-HOURS |
* |
|
| Hatch 2 |
100 |
|
|
|
|
| McGuire 1 |
100 |
|
|
|
|
| McGuire 2 |
95 |
|
HOLDING POWER FOR TESTING |
* |
|
| North Anna 1 |
100 |
|
PLAN TO REMOVE "A" RESERVE STATION TRANSFORMER FROM SERVICE IN THE NEXT 72 HOURS |
* |
|
| North Anna 2 |
100 |
|
|
|
|
| Oconee 1 |
0 |
2008-04-11 |
REFUELING OUTAGE - DEFUELING IN PROGRESS |
* |
|
| Oconee 2 |
100 |
|
|
|
|
| Oconee 3 |
100 |
|
|
|
|
| Robinson 2 |
100 |
|
|
|
|
| Saint Lucie 1 |
100 |
|
|
|
|
| Saint Lucie 2 |
100 |
|
|
|
|
| Sequoyah 1 |
100 |
|
|
|
|
| Sequoyah 2 |
91 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
| Summer |
100 |
|
|
* |
|
| Surry 1 |
0 |
2008-04-16 |
MAINTENANCE OUTAGE - FEEDWATER HEATER REPAIRS COMPLETED |
* |
|
| Surry 2 |
96 |
|
COASTDOWN TO REFUELING |
* |
|
| Turkey Point 3 |
100 |
|
|
|
|
| Turkey Point 4 |
0 |
2008-03-30 |
DEFUELED |
|
|
| Vogtle 1 |
0 |
2008-03-15 |
REFUELING OUTAGE |
|
|
| Vogtle 2 |
98 |
|
100% ELECTRICAL CAPABILITY. |
|
|
| Watts Bar 1 |
100 |
|
|
|
|
Region 3
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Braidwood 1 |
100 |
|
|
|
|
| Braidwood 2 |
92 |
|
COASTDOWN TO REFUELING OUTAGE |
* |
|
| Byron 1 |
95 |
|
HOLDING POWER FOR PRECONDITIONING |
* |
|
| Byron 2 |
100 |
|
|
|
|
| Clinton |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
| D.C. Cook 1 |
0 |
2008-03-25 |
REFUELING OUTAGE |
* |
|
| D.C. Cook 2 |
100 |
|
|
* |
|
| Davis-Besse |
100 |
|
|
|
|
| Dresden 2 |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
| Dresden 3 |
99 |
|
100% ELECTRICAL CAPABILITY |
* |
|
| Duane Arnold |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
| Fermi 2 |
98 |
|
TESTING HP CONTROL VALVES |
* |
|
| Kewaunee |
0 |
2008-03-28 |
DEFUELED |
|
|
| La Salle 1 |
100 |
|
|
|
|
| La Salle 2 |
100 |
|
|
|
|
| Monticello |
100 |
|
|
|
|
| Palisades |
100 |
|
|
* |
|
| Perry 1 |
100 |
|
|
|
|
| Point Beach 1 |
100 |
|
GRID VOLTAGE IS EXPECTED TO DIP WHEN KEWAUNEE ENERGIZES NEW TRANSFORMER ON 04/22 |
* |
|
| Point Beach 2 |
0 |
2008-04-05 |
DEFUELED - TRANSFORMERS 2X03 & 2X04 OOS - GRID VOLTAGE IS EXPECTED TO DIP WHEN KEWAUNEE ENERGIZES NEW TRANSFORMER ON 04/22 |
* |
|
| Prairie Island 1 |
100 |
|
|
|
|
| Prairie Island 2 |
100 |
|
|
|
|
| Quad Cities 1 |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
| Quad Cities 2 |
96 |
|
100% ELECTRICAL CAPABILITY |
* |
|
Region 4
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Arkansas Nuclear 1 |
100 |
|
|
|
|
| Arkansas Nuclear 2 |
100 |
|
|
|
|
| Callaway |
100 |
|
|
|
|
| Columbia Generating Station |
100 |
|
|
|
|
| Comanche Peak 1 |
100 |
|
|
|
|
| Comanche Peak 2 |
27 |
|
HOLDING FOR FLUX MAPPING |
* |
|
| Cooper |
0 |
2008-04-11 |
REFUELING OUTAGE |
|
|
| Diablo Canyon 1 |
100 |
|
|
|
|
| Diablo Canyon 2 |
100 |
|
|
|
|
| Fort Calhoun |
0 |
2008-04-19 |
COMMENCING REFUELING OUTAGE |
* |
|
| Grand Gulf 1 |
100 |
|
|
|
|
| Palo Verde 1 |
100 |
|
|
|
|
| Palo Verde 2 |
0 |
2008-03-28 |
DEFUELED |
|
|
| Palo Verde 3 |
100 |
|
|
|
|
| River Bend 1 |
100 |
|
|
|
|
| San Onofre 2 |
99 |
|
|
|
|
| San Onofre 3 |
0 |
2008-04-16 |
PLANNED SHUTDOWN IN ORDER TO CONSERVE FUEL FOR SUMMER LOADS - WILL MAINTAIN UNIT IN MODE 3 (HOT STANDBY) |
|
|
| South Texas 1 |
0 |
2008-03-29 |
REFUELING OUTAGE |
|
|
| South Texas 2 |
100 |
|
|
|
|
| Waterford 3 |
100 |
|
|
|
|
| Wolf Creek 1 |
0 |
2008-03-17 |
REFUELING OUTAGE |
|
|
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.