Skip to main content

Power Reactor Status Report for April 12, 2008

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 94 HOLDING FOR XENON *
Ginna 100
Hope Creek 1 100 500 KV (5015) LINE OOS *
Indian Point 2 0 2008-03-23 REFUELING OUTAGE. 13.8KV FEEDER 13W92 OOS FOR DESIGN MOD *
Indian Point 3 100 13.8KV FEEDER 13W92 OOS FOR DESIGN MOD
Limerick 1 100
Limerick 2 100
Millstone 2 0 2008-04-05 REFUELING OUTAGE
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 0 2008-03-21 REFUELING OUTAGE
Oyster Creek 92 HOLDING POWER FOR CONTROL VALVE OSCILLATION PROBLEM AND FEEDWATER HEATER ISSUES
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 100 500 KV LINE OOS FOR MAINTENANCE
Salem 2 0 2008-03-11 DEFUELED - 500 KV LINE OOS FOR MAINTENANCE
Seabrook 1 0 2008-03-31 DEFUELED. 345 KV (BUS 2) OOS *
Susquehanna 1 0 2008-03-03 REFUELING OUTAGE
Susquehanna 2 100 VOLTAGE REGULATOR IN MANUAL
Three Mile Island 1 100
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100
Browns Ferry 2 100
Browns Ferry 3 0 2008-03-18 REFUELING OUTAGE
Brunswick 1 0 2008-03-14 REFUELING OUTAGE
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Crystal River 3 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 99 PROCEDURAL LIMIT
Hatch 2 100
McGuire 1 100
McGuire 2 0 2008-03-01 COMING OUT OF REFUELING OUTAGE
North Anna 1 100
North Anna 2 100
Oconee 1 0 2008-04-11 REFUELING OUTAGE *
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 97 COASTDOWN TO REFUELING OUTAGE *
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 0 2008-03-30 DEFUELED
Vogtle 1 0 2008-03-15 REFUELING OUTAGE
Vogtle 2 98 100% ELECTRICAL CAPABILITY.
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 99 COASTDOWN TO REFUELING OUTAGE *
Byron 1 0 2008-03-23 REFUELING OUTAGE - WILL OPEN SWITCHYARD RINGBUS IN PREP OF UNIT 1 STARTUP *
Byron 2 100 WILL OPEN SWITCHYARD RINGBUS IN PREP OF UNIT 1 STARTUP *
Clinton 96 100% ELECTRICAL CAPABILITY
D.C. Cook 1 0 2008-03-25 DEFUELED
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 98 100% ELECTRICAL CAPABILITY *
Dresden 3 80 INCREASING POWER - COMPLETED REPAIRS ON #3 TURBINE CONTROL VALVE *
Duane Arnold 98 100% ELECTRICAL CAPABILITY
Fermi 2 100
Kewaunee 0 2008-03-28 DEFUELED *
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 100
Perry 1 5 STARUP IN PROGRESS - CURRENTLY RAISING PRESSURE IN PREPARATION OF TURBINE STARTUP *
Point Beach 1 100
Point Beach 2 0 2008-04-05 REFUELING OUTAGE - TRANSFORMERS 2X03 & 2X04 OOS *
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 33 REDUCED POWER TO IDENTIFY TUBE LEAK IN MAIN CONDENSER *
Quad Cities 2 97 100% ELECTRICAL CAPABILITY *

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 35 INCREASING POWER TO 68% FOR ADDITIONAL TESTING *
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 0 2008-03-29 REFUELING OUTAGE - CORE RELOADED
Cooper 0 2008-04-11 REFUELING OUTAGE - RCS COOLDOWN IN PROGRESS *
Diablo Canyon 1 100
Diablo Canyon 2 8 HOLDING POWER - ANTICIPATE GENERATOR ONLINE BY 0800 PDT *
Fort Calhoun 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 0 2008-03-28 DEFUELED
Palo Verde 3 100
River Bend 1 100
San Onofre 2 65 REDUCED FOR MAIN FEEDWATER PUMP REPAIR
San Onofre 3 99
South Texas 1 0 2008-03-29 DEFUELED
South Texas 2 100
Waterford 3 100
Wolf Creek 1 0 2008-03-17 DEFUELED

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.