UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Beaver Valley 1 |
100 |
|
|
|
|
| Beaver Valley 2 |
71 |
|
INCREASING POWER |
* |
|
| Calvert Cliffs 1 |
100 |
|
|
|
|
| Calvert Cliffs 2 |
100 |
|
|
|
|
| FitzPatrick |
100 |
|
|
|
|
| Ginna |
100 |
|
|
|
|
| Hope Creek 1 |
100 |
|
|
|
|
| Indian Point 2 |
100 |
|
|
|
|
| Indian Point 3 |
100 |
|
|
|
|
| Limerick 1 |
100 |
|
|
|
|
| Limerick 2 |
100 |
|
|
|
|
| Millstone 2 |
0 |
2006-10-06 |
STARTUP PREPARATIONS IN PROGRESS |
|
|
| Millstone 3 |
100 |
|
|
|
|
| Nine Mile Point 1 |
100 |
|
|
|
|
| Nine Mile Point 2 |
100 |
|
|
|
|
| Oyster Creek |
70 |
|
ROD FOR FLOW SWAP |
* |
|
| Peach Bottom 2 |
100 |
|
|
|
|
| Peach Bottom 3 |
100 |
|
|
|
|
| Pilgrim 1 |
100 |
|
|
|
|
| Salem 1 |
100 |
|
|
|
|
| Salem 2 |
100 |
|
|
|
|
| Seabrook 1 |
100 |
|
|
|
|
| Susquehanna 1 |
100 |
|
|
|
|
| Susquehanna 2 |
100 |
|
|
|
|
| Three Mile Island 1 |
100 |
|
|
|
|
| Vermont Yankee |
43 |
|
DOWNPOWER PERFORM PLANNED OUTAGE OF 345 KV LINE #381 AND WATERBOX CLEANING |
* |
|
Region 2
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Browns Ferry 1 |
0 |
1985-03-03 |
DEFUELED |
|
|
| Browns Ferry 2 |
100 |
|
2 (500 KV) OF 7 OFFSITE LINES OOS. |
|
|
| Browns Ferry 3 |
100 |
|
2 (500 KV) OF 7 OFFSITE LINES OOS. |
|
|
| Brunswick 1 |
100 |
|
|
|
|
| Brunswick 2 |
0 |
2006-11-01 |
SCRAM - SEE EN #42986 |
|
|
| Catawba 1 |
0 |
2006-11-10 |
REFUELING OUTAGE |
* |
|
| Catawba 2 |
100 |
|
|
|
|
| Crystal River 3 |
100 |
|
|
|
|
| Farley 1 |
100 |
|
|
|
|
| Farley 2 |
100 |
|
|
|
|
| Harris 1 |
100 |
|
|
|
|
| Hatch 1 |
100 |
|
|
|
|
| Hatch 2 |
100 |
|
|
|
|
| McGuire 1 |
100 |
|
|
|
|
| McGuire 2 |
95 |
|
HOLDING FOR HEATER DRAIN PUMP MAINTENANCE |
* |
|
| North Anna 1 |
0 |
2006-11-12 |
PLANNED MID-CYCLE OUTAGE FOR PZR MANWAY REPAIR |
|
|
| North Anna 2 |
100 |
|
|
|
|
| Oconee 1 |
0 |
2006-10-06 |
DEFUELED |
|
|
| Oconee 2 |
100 |
|
|
|
|
| Oconee 3 |
100 |
|
|
|
|
| Robinson 2 |
100 |
|
|
|
|
| Saint Lucie 1 |
100 |
|
|
|
|
| Saint Lucie 2 |
100 |
|
|
|
|
| Sequoyah 1 |
100 |
|
|
|
|
| Sequoyah 2 |
93 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
| Summer |
0 |
2006-10-13 |
REFUELING OUTAGE |
|
|
| Surry 1 |
100 |
|
|
|
|
| Surry 2 |
0 |
2006-10-07 |
STARTUP PREPARATIONS IN PROGRESS |
|
|
| Turkey Point 3 |
100 |
|
|
|
|
| Turkey Point 4 |
0 |
2006-10-30 |
DEFUELED |
|
|
| Vogtle 1 |
98 |
|
TURBINE VALVE LIMITED |
|
|
| Vogtle 2 |
100 |
|
|
|
|
| Watts Bar 1 |
0 |
2006-09-10 |
REFUELING OUTAGE |
* |
|
Region 3
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Braidwood 1 |
100 |
|
|
|
|
| Braidwood 2 |
100 |
|
|
* |
|
| Byron 1 |
100 |
|
U1 TRANSFORMER OUTAGE; SAFETY BUSES CROSS TIED TO U2 |
|
|
| Byron 2 |
100 |
|
SUPPORTING U1 TRANSFORMER OUTAGE WITH SAFETY BUS CROSS TIE TO U1 |
|
|
| Clinton |
96 |
|
100% ELECTRICAL CAPABILITY |
|
|
| D.C. Cook 1 |
47 |
|
PERFORMING DIGITAL TURBINE CONTROL TESTING |
* |
|
| D.C. Cook 2 |
100 |
|
|
|
|
| Davis-Besse |
100 |
|
|
|
|
| Dresden 2 |
85 |
|
83% ELECTRICAL CAPABILITY - HOLDING POWER DUE TO DAMAGED FEEDWATER HEATER |
|
|
| Dresden 3 |
0 |
2006-11-03 |
REFUELING OUTAGE |
|
|
| Duane Arnold |
98 |
|
100% ELECTRICAL CAPABILITY |
|
|
| Fermi 2 |
100 |
|
|
|
|
| Kewaunee |
40 |
|
INCREASING POWER |
* |
|
| La Salle 1 |
100 |
|
|
|
|
| La Salle 2 |
100 |
|
|
|
|
| Monticello |
100 |
|
|
|
|
| Palisades |
100 |
|
|
|
|
| Perry 1 |
100 |
|
|
|
|
| Point Beach 1 |
100 |
|
|
|
|
| Point Beach 2 |
0 |
2006-10-15 |
HEATING UP |
|
|
| Prairie Island 1 |
100 |
|
|
|
|
| Prairie Island 2 |
0 |
2006-11-14 |
REFUELING OUTAGE |
* |
|
| Quad Cities 1 |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
| Quad Cities 2 |
96 |
|
100% ELECTRICAL CAPABILITY |
|
|
Region 4
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Arkansas Nuclear 1 |
100 |
|
|
|
|
| Arkansas Nuclear 2 |
100 |
|
|
|
|
| Callaway |
100 |
|
|
|
|
| Columbia Generating Station |
100 |
|
|
|
|
| Comanche Peak 1 |
100 |
|
|
|
|
| Comanche Peak 2 |
100 |
|
|
|
|
| Cooper |
0 |
2006-10-20 |
REFUELING OUTAGE
REACTOR VESSEL HYDRO INPROGRESS |
* |
|
| Diablo Canyon 1 |
100 |
|
|
|
|
| Diablo Canyon 2 |
100 |
|
|
|
|
| Fort Calhoun |
0 |
2006-09-09 |
REFUELING OUTAGE |
|
|
| Grand Gulf 1 |
100 |
|
|
|
|
| Palo Verde 1 |
100 |
|
|
|
|
| Palo Verde 2 |
19 |
|
PHYSICS TESTING |
* |
|
| Palo Verde 3 |
100 |
|
|
|
|
| River Bend 1 |
74 |
|
PLANNED WATER BOX AND REACTOR WATER CLEANUP OUTAGE |
* |
|
| San Onofre 2 |
99 |
|
STEAM GENERATOR TUBE PLUGGING LIMITATION |
|
|
| San Onofre 3 |
0 |
2006-10-16 |
DEFUELED |
|
|
| South Texas 1 |
100 |
|
|
|
|
| South Texas 2 |
100 |
|
|
|
|
| Waterford 3 |
100 |
|
|
|
|
| Wolf Creek 1 |
100 |
|
|
|
|
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.