Power Reactor Status Report for November 10, 2006

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 0 2006-10-01 STARTUP PREPARATIONS IN PROGRESS *
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100 SOLAR ACTIVITY WARNING UNTIL 1100 EST *
Ginna 91 HOLDING FOR FW REG VALVE TUNING
Hope Creek 1 100
Indian Point 2 100
Indian Point 3 100
Limerick 1 100 ALTERNATE ELECTRICAL CONFIG WITH PLANNED OUTAGE OF #20 BUS
Limerick 2 100 ALTERNATE ELECTRICAL CONFIG WITH PLANNED OUTAGE OF #20 BUS
Millstone 2 0 2006-10-06 STARTUP PREPARATIONS IN PROGRESS *
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 100
Oyster Creek 0 2006-10-15 REFUELING OUTAGE
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 100
Salem 2 100
Seabrook 1 17 PREPARING TO CONTINUE STARTUP *
Susquehanna 1 100
Susquehanna 2 100
Three Mile Island 1 100
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 0 1985-03-03 DEFUELED
Browns Ferry 2 100 2 (500 KV) OF 7 OFFSITE LINES OOS.
Browns Ferry 3 100 2 (500 KV) OF 7 OFFSITE LINES OOS.
Brunswick 1 100
Brunswick 2 0 2006-11-01 STARTUP PREPARATIONS IN PROGRESS *
Catawba 1 95 HOLDING PRIOR TO BEGINNING SHUTDOWN TO ENTER REFUELING OUTAGE LATER IN THE DAY *
Catawba 2 100
Crystal River 3 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 100
Hatch 2 100
McGuire 1 100
McGuire 2 2 STARTUP IN PROGRESS *
North Anna 1 100
North Anna 2 100
Oconee 1 0 2006-10-06 DEFUELED
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 97 COASTDOWN TO REFUELING OUTAGE *
Summer 0 2006-10-13 REFUELING OUTAGE *
Surry 1 100
Surry 2 0 2006-10-07 STARTUP PREPARATIONS IN PROGRESS
Turkey Point 3 100
Turkey Point 4 0 2006-10-30 DEFUELED
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 0 2006-09-10 DEFUELED

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 99 HOLDING POWER FOR CLAD RELAXATION *
Byron 1 100
Byron 2 100
Clinton 96 100% ELECTRICAL CAPABILITY
D.C. Cook 1 0 2006-09-15 STARTUP IN PROGRESS - REACTOR IS CRITICAL *
D.C. Cook 2 100
Davis-Besse 100
Dresden 2 85 83% ELECTRICAL CAPABILITY - HOLDING POWER DUE TO DAMAGED FEEDWATER HEATER *
Dresden 3 0 2006-11-03 REFUELING OUTAGE
Duane Arnold 19 INCREASING POWER *
Fermi 2 100
Kewaunee 100
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 98 FEEDWATER HEATER MAINTENANCE - MAINTENANCE ON ONE OFFSITE POWER FEED TO SAFETY BUSES. *
Perry 1 100
Point Beach 1 100
Point Beach 2 0 2006-10-15 STARTUP PREPARATIONS IN PROGRESS
Prairie Island 1 100
Prairie Island 2 100 *
Quad Cities 1 97 100% ELECTRICAL CAPABILITY
Quad Cities 2 96 100% ELECTRICAL CAPABILITY

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 42 HOLDING POWER FOLLOWING TRIP OF THE "A" MFP - TROUBLESHOOTING/REPAIRS IN PROGRESS *
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100 *
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 0 2006-10-20 REFUELING OUTAGE - GRID STATUS YELLOW DUE TO 1 LOOP OF S/D COOLING UNAVAILABLE - RING BUS FEEDER WORK COMPLETED *
Diablo Canyon 1 100
Diablo Canyon 2 100
Fort Calhoun 0 2006-09-09 DEFUELED
Grand Gulf 1 100 SCHEDULED 500KV FRANKLIN TO BRASWELL LINE OUTAGE TIL 11/12 *
Palo Verde 1 99 REDUCED POWER FOR SG HIGH RATE BLOWDOWNS *
Palo Verde 2 0 2006-09-29 STARTUP PREPARATIONS IN PROGRESS *
Palo Verde 3 100
River Bend 1 100
San Onofre 2 99 STEAM GENERATOR TUBE PLUGGING LIMITATION
San Onofre 3 0 2006-10-16 DEFUELED
South Texas 1 100
South Texas 2 100
Waterford 3 100
Wolf Creek 1 4 STARTUP IN PROGRESS *

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.