Power Reactor Status Report for April 05, 2004

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 0 2004-03-20 MAINTENANCE OUTAGE.
Indian Point 2 100
Indian Point 3 100
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 0 2004-04-02 REFUELING OUTAGE
Nine Mile Point 1 100
Nine Mile Point 2 0 2004-03-15 REFUELING OUTAGE
Oyster Creek 100 *
Peach Bottom 2 100
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 0 2004-03-30 REFUELING OUTAGE *
Salem 2 97 HEATER DRAIN PUMP ISSUE
Seabrook 1 100
Susquehanna 1 0 2004-02-27 REFUELING OUTAGE
Susquehanna 2 100
Three Mile Island 1 100
Vermont Yankee 0 2004-04-03 REFUELING OUTAGE *

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 0 2004-02-16 DEFUELED
Browns Ferry 2 100
Browns Ferry 3 100 *
Brunswick 1 38 POWER ASCENSION TESTING *
Brunswick 2 96 100% ELECTRICAL CAPABILITY
Catawba 1 100
Catawba 2 100
Crystal River 3 100
Farley 1 100
Farley 2 0 2004-03-12 STARTUP PREPARATIONS IN PROGRESS *
Harris 1 100 *
Hatch 1 99 MAXIMUM OPERATING POWER (MOP) *
Hatch 2 98 MAXIMUM OPERATING POWER (MOP)
McGuire 1 0 2004-03-06 STARTUP PREPARATIONS IN PROGRESS *
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 0 2004-03-19 REFUELING OUTAGE DEFUELED
Oconee 3 100
Robinson 2 100
Saint Lucie 1 0 2004-03-21 DEFUELED
Saint Lucie 2 100
Sequoyah 1 100
Sequoyah 2 100
Summer 0 2004-03-30 SHUTDOWN FOR REACTOR COOLANT PUMP SEAL INJECTION LINE MAINTENANCE
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100 *
Byron 1 100
Byron 2 0 2004-03-22 REFUELING OUTAGE *
Clinton 92 100% ELECTRICAL CAPABILITY
D.C. Cook 1 0 2004-03-30 HEATUP IN PROGRESS
D.C. Cook 2 82 TURBINE CONTROL PROBLEM *
Davis-Besse 100
Dresden 2 96 100% ELECTRICAL CAPABILITY *
Dresden 3 98 100% ELECTRICAL CAPABILITY
Duane Arnold 94 100% ELECTRICAL CAPABILITY. *
Fermi 2 100
Kewaunee 100
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 0 2004-04-02 REFUELING OUTAGE
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100 *
Quad Cities 1 85 LIMITED IN POWER (STEAM DRYER MONITORING) *
Quad Cities 2 85 LIMITED IN POWER (STEAM DRYER MONITORING)

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100 *
Comanche Peak 1 0 2004-03-27 REFUELING OUTAGE
Comanche Peak 2 99 *
Cooper 100
Diablo Canyon 1 0 2004-03-22 DEFUELED
Diablo Canyon 2 100
Fort Calhoun 0 2004-03-26 RCP WORK COMPLETE - PREPARING TO START HEATUP
Grand Gulf 1 100
Palo Verde 1 0 2004-04-02 REFUELING OUTAGE
Palo Verde 2 100
Palo Verde 3 99 T-HOT LIMITED
River Bend 1 100
San Onofre 2 17 EMERGENT EQUIPMENT PROBLEMS MAY DOWNPOWER FOR REPAIR *
San Onofre 3 100
South Texas 1 100
South Texas 2 0 2004-03-31 REFUELING OUTAGE
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.