Skip to main content

Power Reactor Status Report for March 07, 2000

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 0 2000-02-15 REFUELING OUTAGE - FUEL OFFLOAD IN PROGRESS
Beaver Valley 2 100 *
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 92 INCREASING POWER AFTER REDUCING TO 90% POWER TO PERFORM A ROD SWAP *
Indian Point 2 0 2000-02-15 MAINTENANCE OUTAGE
Indian Point 3 100
Limerick 1 96 COASTDOWN TO REFUELING OUTAGE *
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 0 2000-03-03 REFUELING OUTAGE - REACTOR VESSEL HEAD REMOVED *
Oyster Creek 0 2000-03-01 MAINTENANCE OUTAGE
Peach Bottom 2 97 DECREASING TO 90% POWER TO PERFORM A ROD PATTERN ADJUSTMENT *
Peach Bottom 3 100
Pilgrim 1 100
Salem 1 100 *
Salem 2 100
Seabrook 1 100
Susquehanna 1 99 COASTDOWN TO REFUELING OUTAGE *
Susquehanna 2 100
Three Mile Island 1 100
Vermont Yankee 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 0 1985-03-03 DEFUELED
Browns Ferry 2 100
Browns Ferry 3 100
Brunswick 1 0 2000-02-25 REFUELING OUTAGE - FIRST PHASE OF FUEL SHUFFLE COMPLETE - PERFORMING CONTROL ROD DRIVE BLADE EXCHANGES *
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Crystal River 3 100
Farley 1 0 2000-03-04 REFUELING OUTAGE
Farley 2 100
Harris 1 100
Hatch 1 100
Hatch 2 0 2000-03-04 REFUELING OUTAGE *
McGuire 1 100
McGuire 2 100
North Anna 1 70 COASTDOWN TO REFUELING OUTAGE
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 0 2000-02-23 REFUELING OUTAGE - FUEL RELOAD IN PROGRESS
Sequoyah 2 100
Summer 90 HOLDING POWER AT THIS LEVEL TO PERFORM PLANNED FEEDWATER PUMP MAINTENANCE
Surry 1 100
Surry 2 100
Turkey Point 3 0 2000-02-27 REFUELING OUTAGE - FUEL OFFLOAD ON HOLD DUE TO A BENT ROD CLUSTER CONTROL ASSEMBLY
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Watts Bar 1 100

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 75 COASTDOWN TO REFUELING OUTAGE
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 100
D.C. Cook 1 0 1997-09-08 REFUELING OUTAGE - DEFUELED
D.C. Cook 2 0 1997-09-09 REFUELING OUTAGE - DEFUELED
Davis-Besse 100
Dresden 2 100
Dresden 3 100
Duane Arnold 95 HOLDING POWER AT THIS LEVEL TO PERFORM A ROD ADJUSTMENT FOR LOAD LINE *
Fermi 2 97
Kewaunee 97
La Salle 1 100
La Salle 2 100
Monticello 100
Palisades 100
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 100
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 0 2000-02-05 MAINTENANCE OUTAGE
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 0 2000-03-04 REFUELING OUTAGE *
Diablo Canyon 1 100
Diablo Canyon 2 100
Fort Calhoun 100
Grand Gulf 1 100
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend 1 0 2000-03-04 REFUELING OUTAGE - REACTOR VESSEL HEAD AND DRYER LIFTED *
San Onofre 2 100
San Onofre 3 100
South Texas 1 0 2000-03-01 REFUELING OUTAGE - FUEL OFFLOAD IN PROGRESS *
South Texas 2 100
Waterford 3 0 2000-03-06 TECH SPEC REQUIRED SHUTDOWN FROM 100% POWER DUE TO A SMALL UNISOLABLE LEAK (CRACK APPROXIMATELY ¼" LONG) LOCATED AT A WELDED JOINT IN THE SUCTION LINE OF THE 'A' CHARGING AND VOLUME CONTROL PUMP (REFER TO EVENT #36760) *
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.