UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Beaver Valley 1 |
100 |
|
|
|
|
| Beaver Valley 2 |
100 |
|
|
* |
|
| Calvert Cliffs 1 |
100 |
|
|
|
|
| Calvert Cliffs 2 |
100 |
|
|
|
|
| FitzPatrick |
100 |
|
|
|
|
| Ginna |
100 |
|
|
|
|
| Hope Creek 1 |
94 |
|
INCREASING REACTOR POWER AFTER COMPLETING HYDRAULIC CONTROL UNIT MAINTENANCE. |
* |
|
| Indian Point 2 |
99 |
|
|
|
|
| Indian Point 3 |
100 |
|
|
|
|
| Limerick 1 |
100 |
|
|
|
|
| Limerick 2 |
100 |
|
|
|
|
| Millstone 2 |
93 |
|
CHANNEL D OF REACTOR PROTECTION SYSTEM HAS BEEN TRIPPED AND THE LICENSEE IS TROUBLESHOOTING THE PROBLEM. |
* |
|
| Millstone 3 |
100 |
|
|
|
|
| Nine Mile Point 1 |
100 |
|
|
|
|
| Nine Mile Point 2 |
77 |
|
INCREASING REACTOR POWER LEVEL AFTER PERFORMING A REACTOR FEEDWATER PUMP SWAP AND A ROD SEQUENCE EXCHANGE. |
* |
|
| Oyster Creek |
100 |
|
|
|
|
| Peach Bottom 2 |
100 |
|
|
|
|
| Peach Bottom 3 |
100 |
|
|
|
|
| Pilgrim 1 |
100 |
|
|
|
|
| Salem 1 |
100 |
|
|
|
|
| Salem 2 |
100 |
|
|
|
|
| Seabrook 1 |
100 |
|
|
|
|
| Susquehanna 1 |
100 |
|
|
|
|
| Susquehanna 2 |
100 |
|
|
|
|
| Three Mile Island 1 |
100 |
|
|
|
|
| Vermont Yankee |
100 |
|
|
|
|
Region 2
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Browns Ferry 1 |
0 |
1985-03-03 |
DEFUELED |
|
|
| Browns Ferry 2 |
100 |
|
|
|
|
| Browns Ferry 3 |
100 |
|
|
|
|
| Brunswick 1 |
100 |
|
|
|
|
| Brunswick 2 |
100 |
|
|
|
|
| Catawba 1 |
100 |
|
|
|
|
| Catawba 2 |
100 |
|
|
|
|
| Crystal River 3 |
100 |
|
|
|
|
| Farley 1 |
100 |
|
|
|
|
| Farley 2 |
0 |
1999-10-15 |
EXITING REFUELING OUTAGE |
* |
|
| Harris 1 |
100 |
|
|
|
|
| Hatch 1 |
100 |
|
|
* |
|
| Hatch 2 |
98 |
|
MAXIMUM OPERATING POWER |
|
|
| McGuire 1 |
96 |
|
INCREASING REACTOR POWER |
* |
|
| McGuire 2 |
100 |
|
|
|
|
| North Anna 1 |
100 |
|
|
|
|
| North Anna 2 |
100 |
|
|
|
|
| Oconee 1 |
100 |
|
|
|
|
| Oconee 2 |
0 |
1999-11-04 |
EXITING REFUELING OUTAGE |
* |
|
| Oconee 3 |
100 |
|
|
|
|
| Robinson 2 |
100 |
|
|
|
|
| Saint Lucie 1 |
100 |
|
|
|
|
| Saint Lucie 2 |
100 |
|
|
|
|
| Sequoyah 1 |
100 |
|
|
|
|
| Sequoyah 2 |
100 |
|
|
|
|
| Summer |
100 |
|
|
|
|
| Surry 1 |
100 |
|
|
|
|
| Surry 2 |
100 |
|
|
|
|
| Turkey Point 3 |
100 |
|
|
|
|
| Turkey Point 4 |
100 |
|
|
|
|
| Vogtle 1 |
100 |
|
|
|
|
| Vogtle 2 |
100 |
|
|
|
|
| Watts Bar 1 |
100 |
|
|
|
|
Region 3
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Braidwood 1 |
100 |
|
|
* |
|
| Braidwood 2 |
100 |
|
|
|
|
| Byron 1 |
100 |
|
|
|
|
| Byron 2 |
100 |
|
|
|
|
| Clinton |
100 |
|
|
|
|
| D.C. Cook 1 |
0 |
1997-09-08 |
REFUELING OUTAGE - DEFUELED |
|
|
| D.C. Cook 2 |
0 |
1997-09-09 |
REFUELING OUTAGE - DEFUELED |
|
|
| Davis-Besse |
100 |
|
|
* |
|
| Dresden 2 |
100 |
|
|
|
|
| Dresden 3 |
12 |
|
STARTUP IN PROGRESS. SEE EVENT # 36501 FOR REACTOR SCRAM OVER WEEKEND. |
* |
|
| Duane Arnold |
100 |
|
|
* |
|
| Fermi 2 |
97 |
|
|
* |
|
| Kewaunee |
97 |
|
|
|
|
| La Salle 1 |
100 |
|
|
|
|
| La Salle 2 |
100 |
|
|
|
|
| Monticello |
90 |
|
COASTDOWN TO REFUELING OUTAGE |
|
|
| Palisades |
16 |
|
REDUCING REACTOR POWER TO TAKE THE UNIT OFF LINE TO REDUCE HIGH SODIUM LEVEL IN THE STEAM GENERATORS. LICENSEE BELIEVES THE SODIUM CAME FROM THEIR NEW LOW PRESSURE TURBINES. |
* |
|
| Perry 1 |
100 |
|
|
|
|
| Point Beach 1 |
63 |
|
INCREASING POWER LEVEL TO 69% TO VERIFY THAT THEIR MODERATOR TEMPERATURE COEFFICIENT IS NOT POSITIVE. |
* |
|
| Point Beach 2 |
100 |
|
|
* |
|
| Prairie Island 1 |
100 |
|
|
* |
|
| Prairie Island 2 |
100 |
|
|
|
|
| Quad Cities 1 |
100 |
|
|
* |
|
| Quad Cities 2 |
100 |
|
|
|
|
Region 4
| Unit |
Power |
Down |
Reason or Comment |
Change in Report (*) |
Scrams (#) |
| Arkansas Nuclear 1 |
100 |
|
|
|
|
| Arkansas Nuclear 2 |
100 |
|
|
|
|
| Callaway |
100 |
|
|
|
|
| Columbia Generating Station |
100 |
|
|
|
|
| Comanche Peak 1 |
100 |
|
|
|
|
| Comanche Peak 2 |
100 |
|
|
|
|
| Cooper |
100 |
|
|
* |
|
| Diablo Canyon 1 |
100 |
|
|
|
|
| Diablo Canyon 2 |
100 |
|
|
|
|
| Fort Calhoun |
100 |
|
|
|
|
| Grand Gulf 1 |
32 |
|
REDUCING POWER LEVEL TO TAKE THE MAIN TURBINE OFF LINE AGAIN TO REPAIR AN UNISOLABLE STEAM LEAK ON THE MAIN TURBINE FIRST STAGE PRESSURE SENSING LINE. THIS IS THE SECOND TIME IN 2 DAYS THAT THE SEAL WELD ON THIS SENSING LINE FITTING HAS FAILED. |
* |
|
| Palo Verde 1 |
100 |
|
|
|
|
| Palo Verde 2 |
100 |
|
|
|
|
| Palo Verde 3 |
100 |
|
|
|
|
| River Bend 1 |
100 |
|
|
|
|
| San Onofre 2 |
100 |
|
|
|
|
| San Onofre 3 |
100 |
|
|
|
|
| South Texas 1 |
100 |
|
|
|
|
| South Texas 2 |
100 |
|
|
|
|
| Waterford 3 |
100 |
|
|
|
|
| Wolf Creek 1 |
100 |
|
|
|
|
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.