Event Notification Report for September 29, 2019

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
09/28/2019 - 09/29/2019

EVENT NUMBERS
54299

Power Reactor
Event Number: 54299
Facility: FERMI
Region: 3     State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: PAUL ANGOVE
HQ OPS Officer: DONALD NORWOOD
Notification Date: 09/30/2019
Notification Time: 01:22 [ET]
Event Date: 09/29/2019
Event Time: 22:28 [EDT]
Last Update Date: 09/30/2019
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(C) - POT UNCNTRL RAD REL
Person (Organization):
ROBERT DALEY (R3DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
SECONDARY CONTAINMENT PRESSURE EXCEEDED TECHNICAL SPECIFICATION REQUIREMENT

"On September 29, 2019 at 2228 EDT, during a planned swap of Reactor Building HVAC trains, the exhaust fan discharge damper for the train being removed from service failed to close when the train was shutdown, which resulted in the Technical Specification (TS) for secondary containment pressure not being met for approximately 2 minutes and 15 seconds. The maximum secondary containment pressure observed during that time was approximately 0.1 inches of water gauge (positive).

"Secondary containment pressure was returned to within the TS operability limit of greater than or equal to 0.125 inches of vacuum water gauge (TS SR 3.6.4.1.1) by restarting the train of RBHVAC. Secondary containment pressure is currently stable. Secondary containment was declared Operable at 2235 EDT. There were no radiological releases associated with this event.

"Declaring secondary containment inoperable is reportable under 10 CFR 50.72(b)(3)(v)(C) as an event or condition that could have prevented the fulfillment of a safety function needed to control the release of radioactive material.

"The Licensee has notified the NRC Resident Inspector."