Event Notification Report for May 17, 2018

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
05/16/2018 - 05/17/2018

EVENT NUMBERS
534085340953406

Power Reactor
Event Number: 53408
Facility: PRAIRIE ISLAND
Region: 3     State: MN
Unit: [] [2] []
RX Type: [1] W-2-LP,[2] W-2-LP
NRC Notified By: WAYNE SEXSON
HQ OPS Officer: THOMAS KENDZIA
Notification Date: 05/17/2018
Notification Time: 17:33 [ET]
Event Date: 05/17/2018
Event Time: 11:15 [CDT]
Last Update Date: 05/17/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
KARLA STOEDTER (R3DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
AUTOMATIC ACTUATION OF EMERGENCY DIESEL GENERATOR

"At 1115 (CDT) on May 17, 2018 with Unit 2 in Mode 1 at 100% power, the station experienced an auto-start of Emergency Diesel Generator, D5. Preliminary information indicates that the Bus 25 Potential Transformer (PT) fuse drawer was inadvertently opened, causing Breaker 25-16 to open and de-energize bus 25. Operators were able to manually close the D5 EDG output breaker to re-energize bus 25. 22 Component Cooling (CC) Pump auto-started on the loss of 21 CC Pump due to low pressure in the CC system as designed. All equipment functioned as designed.

"This event is being reported in accordance with 10 CFR 50.72(b)(3)(iv)(A) as an event that results in a valid actuation of the EDG.

"There was no impact on the health and safety of the public or plant personnel.

"The NRC Senior Resident Inspector has been notified."


Power Reactor
Event Number: 53409
Facility: CLINTON
Region: 3     State: IL
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: DALE SHELTON
HQ OPS Officer: STEVEN VITTO
Notification Date: 05/17/2018
Notification Time: 23:02 [ET]
Event Date: 05/17/2018
Event Time: 15:03 [CDT]
Last Update Date: 05/17/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
Person (Organization):
KARLA STOEDTER (R3DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N N 0 Cold Shutdown 0 Cold Shutdown
Event Text
EMERGENCY DIESEL GENERATORS INOPERABLE

"On May 17, 2018, with the Unit in Mode 4, Clinton Power Station experienced the concurrent inoperability of two Emergency Diesel Generators (DG). This event is being reported as an 8-hour non-emergency notification per 10 CFR 50.72(b)(3)(v) as, 'Any event or condition that at the time of discovery could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident.'

"On May 17, 2018, at 15:03 CDT, it was identified that the Division 2 DG air start receiver isolation valves 1DG160 and 1DG161 were shut. With these valves shut, the Division 2 DG is inoperable. At the time, Division 1 DG was also inoperable for a 4160V 1A1 partial bus outage. The Technical Specification (TS) Actions for TS 3.8.2, AC Sources Shutdown, and TS 3.5.2, RPV Water Inventory Control, were entered as a result of the inoperability of the onsite AC power sources to isolation valves being credited to limit RPV DRAIN TIME.

"Division 2 DG air receivers were realigned at 15:45 CDT and the Division 2 DG auto start function was restored. Offsite power was available throughout this event and there was no impact to the health and safety of the public or plant personnel.

"Investigation is ongoing. It has been determined that the air start receiver isolation valves remained closed following system restoration on May 11, 2018. However, the Division 2 DG was not required to be Operable by TS until 00:45 CDT on May 14, 2018 when the Division 1 DG was made inoperable as a result of scheduled plant maintenance.

"The NRC Resident Inspector has been notified."


Power Reactor
Event Number: 53406
Facility: BRUNSWICK
Region: 2     State: NC
Unit: [1] [2] []
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: MICHAEL LONG
HQ OPS Officer: STEVEN VITTO
Notification Date: 05/17/2018
Notification Time: 14:26 [ET]
Event Date: 05/17/2018
Event Time: 10:45 [EDT]
Last Update Date: 05/17/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
ANTHONY MASTERS (R2DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 100 Power Operation
Event Text
EMERGENCY NOTIFICATION SIREN MALFUNCTIONING

"On May 17, 2018, at approximately 1045 Eastern Daylight Time (EDT), Duke Energy confirmed that one emergency notification siren (i.e., B03) located in Brunswick County was malfunctioning. The siren was making an abnormal sound, alternating between low and high pitch. At approximately 1103 EDT, the siren was deactivated. There are a total of 38 sirens located in Brunswick and New Hanover Counties. No other siren was affected.

"Duke Energy notified the State of North Carolina, Brunswick County, and New Hanover County of the issue.

"There was no impact on the health and safety of the public or plant personnel. The NRC Resident Inspector has been notified."