Event Notification Report for December 17, 2017

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
12/16/2017 - 12/17/2017

EVENT NUMBERS
531235312453246

!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Power Reactor
Event Number: 53123
Facility: BRUNSWICK
Region: 2     State: NC
Unit: [] [2] []
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: ALAN SCHULTZ
HQ OPS Officer: ANDREW WAUGH
Notification Date: 12/17/2017
Notification Time: 05:48 [ET]
Event Date: 12/17/2017
Event Time: 03:16 [EST]
Last Update Date: 01/29/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
Person (Organization):
BINOY DESAI (R2DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text


Power Reactor
Event Number: 53124
Facility: GINNA
Region: 1     State: NY
Unit: [1] [] []
RX Type: [1] W-2-LP
NRC Notified By: KIERAN REYNOLDS
HQ OPS Officer: BETHANY CECERE
Notification Date: 12/17/2017
Notification Time: 11:56 [ET]
Event Date: 12/17/2017
Event Time: 07:55 [EST]
Last Update Date: 12/17/2017
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
ART BURRITT (R1DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
OFFSITE NOTIFICATION FOLLOWING SULFRIC ACID SPILL

"Ginna notified New York State Department of Environmental Conservation of a sulfuric acid spill of approximately 270 gallons in the AVT, All Volatile Treatment, building. Ginna is currently contacting offsite support for hazardous chemical cleanup. The spilled sulfuric acid is currently contained within the secondary containment structure associated with the sulfuric acid tank. There is no release to the environment. There is no impact to habitability in the AVT building at this time."

The licensee notified the NRC Resident Inspector.


Part 21
Event Number: 53246
Rep Org: CRANE NUCLEAR, INC.
Licensee: CRANE NUCLEAR, INC.
Region: 3
City: BOLINGBROOK   State: IL
County:
License #:
Agreement: Y
Docket:
NRC Notified By: JOYCE HAMMAN
HQ OPS Officer: HOWIE CROUCH
Notification Date: 03/06/2018
Notification Time: 18:33 [ET]
Event Date: 12/17/2017
Event Time: 00:00 [CST]
Last Update Date: 03/22/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21(d)(3)(i) - DEFECTS AND NONCOMPLIANCE
Person (Organization):
DAN SCHROEDER (R1DO)
RANDY MUSSER (R2DO)
MICHAEL VASQUEZ (R4DO)
PART 21/50.55 REACTORS (EMAIL)
Event Text
PART 21 - UNDERSIZED PACKING GLANDS IN CERTAIN CRANE GATE VALVES

On 12/17/17, Brunswick Nuclear Plant experienced a packing gland blowout on an in-service Crane Nuclear, Inc., Figure Number 83 1/2 SPL, 10 inch by 8 inch by 10 inch, Bolted Bonnet Gate Valve. Crane Nuclear determined that component drawings for the 10 inch valve as well as the 6 inch by 4 inch by 6 inch Bolted Bonnet Gate Valve were in error. That error was corrected. Crane Nuclear is recommending that affected licensees replace the packing glands of the affected valves in their possession.

The affected licensees are Pilgrim Station, Cooper Nuclear Station, Browns Ferry Nuclear, and Brunswick Nuclear.

Should you have any questions regarding this matter, please contact Joyce Hamman, Director, Safety & Quality at (678) 451-2280, Burt Anderson, Site Leader, at (630) 226-4990, or Samson Kay, Engineering Manager at (630) 226-4983.

* * * UPDATE AT 1435 EDT ON 03/21/18 FROM SAMSON KAY TO DONG PARK * * *

The following information was provided as an update via fax:

"[Crane Nuclear, Inc.] Recommends one of the following actions be taken:

- The valve gland should be replaced to tighten clearances to meet MSS-SP-120 requirements.

- Install a packing washer in the current configuration that complies with MSS-SP-120 clearances. Use of a packing washer will allow for load to be evenly distributed across the packing to prevent extrusion through diametral clearances. Note, that existing drawings and bills of materials should be updated to match this configuration if this option is selected.

"Should you have any questions regarding this matter, please contact me, Joyce Hamman, Director, Safety & Quality at (678) 451-2280, Burt Anderson, Site Leader, at (630) 226-4990, or Samson Kay, Engineering Manager at (630) 226-4983."

Notified R1DO (McKinley), R2DO (Sandal), R4DO (Groom) and Part 21/50.55 Reactors via email.