Event Notification Report for February 27, 2017

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
02/26/2017 - 02/27/2017

EVENT NUMBERS
525785379952692

Non-Agreement State
Event Number: 52578
Rep Org: BAYER CROP SCIENCES
Licensee: BAYER CROP SCIENCES
Region: 3
City: KANSAS CITY   State: MO
County:
License #: 24-03830-01
Agreement: N
Docket:
NRC Notified By: STEVE SCHERICH
HQ OPS Officer: JEFF ROTTON
Notification Date: 02/27/2017
Notification Time: 16:04 [ET]
Event Date: 02/27/2017
Event Time: 14:05 [CST]
Last Update Date: 02/27/2017
Emergency Class: NON EMERGENCY
10 CFR Section:
30.50(b)(2) - SAFETY EQUIPMENT FAILURE
Person (Organization):
MARK JEFFERS (R3DO)
NMSS_EVENTS_NOTIFICA (EMAI)
Event Text
SOURCE HOLDER STUCK OPEN

Licensee reported that they were in the process of removing a Kay-Ray Model # 7062B source holder from an installed position. The device serial number is #24093 with a Cs-137 10 mCi source. They believed the source holder to be closed during the removal operation. While in the process of removing the source holder from its installed location, they received unexpected radiation levels on their survey meter and laid the source holder on the room floor with the source pointing in the down direction. They then used some lead shielding to cover the source device and moved it to a storage location. The current radiation levels in the vicinity of the source holder are normal background. The licensee plans on reviewing the radiation dose information when personal dosimetry is processed at the end of the quarter (March 15, 2017). The licensee also plans on contacting Berthold Technologies for disposal of the device.


Non-Agreement State
Event Number: 53799
Rep Org: FROEHLING AND ROBERTSON
Licensee: FROEHLING AND ROBERTSON
Region: 1
City: FORT BRAGG   State: NC
County:
License #: 45-08890-02
Agreement: Y
Docket:
NRC Notified By: BRETT CLARKE
HQ OPS Officer: MARK ABRAMOVITZ
Notification Date: 12/20/2018
Notification Time: 14:12 [ET]
Event Date: 02/27/2017
Event Time: 00:00 [EST]
Last Update Date: 12/20/2018
Emergency Class: NON EMERGENCY
10 CFR Section:
30.50(b)(2) - SAFETY EQUIPMENT FAILURE
Person (Organization):
DON JACKSON (R1DO)
NMSS_EVENTS_NOTIFICATION (EMAIL)
Event Text
DAMAGED MOISTURE DENSITY GAUGE

A technician did not secure the Troxler Moisture Density Gauge in his truck before moving from one job site to the next. The tailgate was open and the gauge fell from the truck onto the dirt road. Someone subsequently found the gauge and returned it to the technician approximately 20 minutes after losing the gauge. The sources remained in the stored position. Subsequent surveys and wipe tests determined that no damage had occurred to the sources however the case itself was cracked. The gauge was sent back to the manufacturer and the case was replaced.

Troxler model 3430 (S/N 23714)
Sources: Cs-137 at 8 mCi and Am-241 at 40 mCi


Part 21
Event Number: 52692
Rep Org: GE HITACHI NUCLEAR ENERGY
Licensee: GE HITACHI NUCLEAR ENERGY
Region: 1
City: WILMINGTON   State: NC
County:
License #:
Agreement: Y
Docket:
NRC Notified By: LISA SCHICHLEIN
HQ OPS Officer: BETHANY CECERE
Notification Date: 04/19/2017
Notification Time: 10:29 [ET]
Event Date: 02/27/2017
Event Time: 00:00 [EDT]
Last Update Date: 07/12/2017
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21(a)(2) - INTERIM EVAL OF DEVIATION
Person (Organization):
PHILIP McKENNA (R2DO)
LAURA KOZAK (R3DO)
RAY AZUA (R4DO)
PART 21/50.55 REACTO (EMAI)
Event Text
PART 21 REPORT - CONTROL ROD DRIVE MECHANISMS CONTAMINATED WITH CHLORIDES

Dale E. Porter
GE-Hitachi Nuclear Energy
Safety Evaluation Program Manager
3901 Castle Hayne Rd., Wilmington, NC 28401
(910) 819-4491
Dale.Porter@GE.Com

"The inappropriate addition of chlorinated water from container box desiccants into the CRDMs [Control Rod Drive Mechanisms] during leak testing after rebuild could potentially initiate Intergranular Stress Corrosion Cracking (IGSCC) or Transgranular Stress Corrosion Cracking (TGSCC). These two types of SCC could cause a separation of the stop piston or separation of the index tube contained within the CRDM. The stop piston separation could cause a slower scram speed and damage the drive so it could not be withdrawn. An index tube separation could result in a similar type of rod uncoupling event that would have the potential to result in a rod drop accident (RDA). The piston tube located within the CRDM is a reactor coolant pressure boundary (RCPB) and is an ASME component. There is a possibility of cracking causing a RCPB leak. SCC initiation on the Cylinder Tube and Flange (CTF) area of the CRDM could result in a separation that could prevent a scram or normal insertion of a CRDM.

"Reports have been issued to River Bend, LaSalle Unit 2, and Hatch Unit 2 providing the results of an evaluation that concludes that the condition will not create a substantial safety hazard or potentially cause a Technical Specification Safety Limit violation for a minimum of one operating cycle. The Browns Ferry Unit 2 drives were shipped but were not installed prior to recall, thus a short-term evaluation for Browns Ferry has not been completed.

"River Bend, Entergy, Shipped Date: 2017, Quantity Shipped: 15, Customer PO Number: 10478763
LaSalle Unit 2, Exelon, Shipped Date: 2017, Quantity Shipped: 24, Customer PO Number: 00414787-66
Hatch Unit 2, Southern Nuclear, Shipped Date: 2017, Quantity Shipped: 15, Customer PO Numbers: SNG50295-0001 & SNG50295-0002
Browns Ferry Unit 2, TVA, Shipped Date: 2017, Quantity Shipped: 32, Customer PO Number: 2424171"

* * * UPDATE ON 7/12/17 AT 1035 EDT FROM LISA SCHICHLEIN TO BETHANY CECERE * * *

"Pursuant to 10 CFR 21.21(d)(4), GEH is providing the final report with the conclusion that, in limited cases, the chloride contamination could create a substantial safety hazard. Attachment 1 identifies the potentially impacted plants and Attachment 2 contains the final report information. The enclosure provides additional details of the evaluation.

Updated Attachment 1 notes:
"A portion of the CRDMs at the Hatch Plant are Reportable while the remainder are not.

Summary of updates to Attachment 2:
"The inappropriate addition of chlorinated water from container box desiccants into the CRDMs during leak testing after rebuild could potentially initiate Intergranular Stress Corrosion Cracking (IGSCC) or Transgranular Stress Corrosion Cracking (TGSCC). These two types of SCC were initially considered for the potential to cause a separation of the stop piston or separation of the index tube contained within the CRDMs that are constructed of 304 Stainless steel. The completed evaluation indicates that a stop piston separation could cause a slower scram speed and damage the drive so it could not be withdrawn. The potential exists for the control rod to drift out. The piston tube located within the CRDM is a reactor coolant pressure boundary (RCPB) and is an ASME component. The possibility of cracking causing RCPB leakage was eliminated by the evaluation. An index tube separation was eliminated as a potential failure mode. Likewise, the potential for SCC initiation on the Cylinder Tube and Flange (CTF) area of the CRDM resulting in a separation that could prevent a scram or normal insertion/withdrawal of a CRD was eliminated.

"The long-term evaluation concluded there is no concern for TGSCC. This evaluation also determined the stop piston to piston tube separation is the only failure mechanism that could occur, and only if those components were manufactured from 304 SS.

"GEH initiated a Root Cause Evaluation (RCA) to determine why this event occurred and has implemented process changes to ensure that the condition does not reoccur. Actions to prevent recurrence, such as eliminating the desiccant material and flushing the closed loop water system, have been completed.

"For Hatch Unit 2, the 12 CRDMs that have the 304 SS piston tubes should be replaced prior to those CRDMs exceeding 10 years in service. See table below:
CRDM S/N, Piston Tube
SE0474, 304 SS
A8737, 304 SS
A9423, 304 SS
A6791, 304 SS
3095, 304 SS
A8729, 304 SS
7253, 304 SS
A6786, 304 SS
SE0368, 304 SS
A5409, 304 SS
7080, 304 SS
A9484, 304 SS

"Interim Reports were issued to River Bend, LaSalle Unit 2, and Hatch Unit 2 providing the results of an evaluation that concluded the condition would not create a substantial safety hazard or potentially cause a Technical Specification Safety Limit violation for a minimum of one operating cycle. The Browns Ferry Unit 2 drives were shipped but were not installed prior to recall, thus a short-term evaluation for Browns Ferry was not provided.

"GEH has completed the long-term CRDM evaluation with the following results:

"A Safety Information Communication is being issued to River Bend, LaSalle Unit 2, and Browns Ferry Unit 2 stating that the CRDMs exposed to the chloride intrusion will not cause a substantial safety hazard, or cause a Technical Specification Safety Limit violation and is therefore not reportable (see enclosure 1 for details).

"For Hatch Unit 2, the introduction of chlorides could cause a substantial safety hazard for the 12 CRDMs that were manufactured from 304 SS material, and is therefore a reportable condition per 10CFR 21.21(d); however, the 3 CRDMs manufactured from XM-19 material would be considered not reportable.

"The results of the short-term evaluations for all three plants where CRDMs were installed remains valid."

Notified the R2DO (Bonser), R3DO (Peterson), R4DO (Proulx), and Part 21/50.55 Reactors Group by email.