Skip to main content

Event Notification Report for August 03, 2013

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
08/02/2013 - 08/03/2013

EVENT NUMBERS
4923249234

Power Reactor
Event Number: 49232
Facility: FARLEY
Region: 2     State: AL
Unit: [1] [] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: JOHN ANDREWS
HQ OPS Officer: VINCE KLCO
Notification Date: 08/03/2013
Notification Time: 06:50 [ET]
Event Date: 08/03/2013
Event Time: 05:20 [CDT]
Last Update Date: 08/03/2013
Emergency Class: ALERT
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED
Person (Organization):
MICHAEL F. KING (R2DO)
PATRICK HILAND (NRR)
JASON KOZAL (IRD)
JENNIFER UHLE (NRR)
VICTOR MCCREE (R2)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
ALERT DECLARED DUE TO AN INADVERTENT CO2 FIRE PROTECTION SYSTEM DISCHARGE

"[On August 3, 2013, at 0520 CDT], Farley Unit 1 declared an ALERT emergency based on [EAL] HA3, 'Release of Toxic, Asphyxiant, or Flammable Gas'. This was due to a tagout of the CO2 Fire Protection System, which resulted in an unexpected discharge of CO2 on the Unit 1 Radiation Side of the Auxiliary Building. The 100 foot elevation level on Unit 1 had an oxygen concentration below the required amount. CO2 has been isolated at the source tank in order to terminated the leak. No personnel have been affected. There is no radiation release in progress. ERDS has been activated."

The licensee is assembling a team to enter the affected area and verify oxygen levels are within allowable limits in order to terminate the ALERT emergency.

The licensee has notified the NRC Resident Inspector and the State and local organizations.

Notified DHS SWO, DOE, FEMA, HHS, DHS NICC, USDA, EPA, FDA and NuclearSSA via email.

* * * UPDATE FROM JONATHAN MCCORY TO STEVE SANDIN AT 1215 EDT ON 08/03/13 * * *

Farley Unit 1 terminated from the ALERT at 1110 CDT on 8/3/13. Oxygen levels are acceptable in all areas of the plant. The CO2 tank has been isolated and is stable at 68%. Plant conditions are stable and improving and all necessary compensatory measures are in place.

The licensee has notified the NRC Resident Inspector and applicable state and local authorities.

Notified R2DO (King), NRR EO (Hiland), IRD (Kozal), and PAO (Couret), DHS SWO, DOE, FEMA, HHS, DHS NICC, USDA, EPA, FDA and NuclearSSA via email.


Part 21
Event Number: 49234
Rep Org: AMEC ENVIRONMENTAL & INFRASTRUCTURE
Licensee: CTLGROUP
Region: 1
City: DURHAM   State: NC
County:
License #:
Agreement: Y
Docket:
NRC Notified By: ANDY KOTTENSTETTE
HQ OPS Officer: JOHN SHOEMAKER
Notification Date: 08/03/2013
Notification Time: 14:36 [ET]
Event Date: 08/03/2013
Event Time: 00:00 [EDT]
Last Update Date: 08/26/2013
Emergency Class: NON EMERGENCY
10 CFR Section:
21.21(a)(2) - INTERIM EVAL OF DEVIATION
Person (Organization):
MICHAEL F. KING (R2DO)
PART 21 REACTORS (EMAI)
Event Text
INTERIM REPORT REGARDING LABORATORY TEST DATA FOR SAFETY CLASS C CONCRETE AND GROUT

An interim report was made, as required per 10CFR21.21 (a)(2), of a deviation identified by AMEC Environment & Infrastructure, Inc. The CTLGroup, a supplier of AMEC, did not initially provide all the traceable calibration information required for all the chemicals used in performance of procured tests in regard to laboratory test data of screening tests for constituents related to Safety Class C concrete and grout. An evaluation is underway, but could not be completed within 60 days of discovery. AMEC anticipates that the evaluation will be completed within two weeks of this correspondence, August 17, 2013.

Affected plants;
Vogtle Units 3 & 4 Safety Class C Concrete and Grout and VC Summer Units 2 & 3 Safety Class C Concrete and Grout.

Name and address of the individual or individuals informing the Commission.

Donald B. Chandler
AMEC Environment & Infrastructure, Inc.
4021 Stirrup Creek Drive, Suite 100
Durham, NC 27703
Phone # 919-381-9908

* * * UPDATE ON 8/26/13 AT 1323 EDT FROM CHANDLER TO HUFFMAN * * *

The following update was received from the licensee via facsimile:

"The purpose of this letter is to follow up on the Interim Report of the Evaluation of a Deviation Pursuant to 10 CFR 21.21(a)(2) provided to the Commission on August 3, 2013. The August 3rd report informed the Commission of a deviation identified by AMEC Environment & Infrastructure, Inc. (AMEC) where an evaluation was underway, but could not be completed within 60 days of discovery. The evaluation was completed by AMEC on August 8, 2013 and it was determined that the nonconformance did not represent a defect."

Notified R2DO (Haag) and sent copy to the Part 21 e-mail group.