Event Notification Report for January 30, 2013
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
01/29/2013 - 01/30/2013
EVENT NUMBERS
48709
Fuel Cycle Facility
Event Number: 48709
Facility: GLOBAL NUCLEAR FUEL - AMERICAS
Region: 2 State: NC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
Comments: LEU CONVERSION (UF6 TO UO2)
LEU FABRICATION
LWR COMMERICAL FUEL
NRC Notified By: SCOTT MURRAY
HQ OPS Officer: JOHN SHOEMAKER
Region: 2 State: NC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
Comments: LEU CONVERSION (UF6 TO UO2)
LEU FABRICATION
LWR COMMERICAL FUEL
NRC Notified By: SCOTT MURRAY
HQ OPS Officer: JOHN SHOEMAKER
Notification Date: 01/31/2013
Notification Time: 14:00 [ET]
Event Date: 01/30/2013
Event Time: 15:30 [EST]
Last Update Date: 01/31/2013
Notification Time: 14:00 [ET]
Event Date: 01/30/2013
Event Time: 15:30 [EST]
Last Update Date: 01/31/2013
Emergency Class: NON EMERGENCY
10 CFR Section:
PART 70 APP A (b)(1) - UNANALYZED CONDITION
10 CFR Section:
PART 70 APP A (b)(1) - UNANALYZED CONDITION
Person (Organization):
ROBERT HAAG (R2DO)
EARL EASTON (NMSS)
ROBERT HAAG (R2DO)
EARL EASTON (NMSS)
COMPLETION OF INTEGRATED SAFETY ANALYSIS ACTION PLAN BALANCE OF PLANT MILESTONE
"In response to a Notice of Violation [NOV] (VIO 70-1113/2010-003), Global Nuclear Fuel Americas, LLC (GNF-A) committed to perform a review of the existing Integrated Safety Analysis (ISA). An ISA action plan and schedule for performing the ISA review was described in GNF-A's response to the NOV and the third milestone (balance of plant) was scheduled for completion by January 31, 2013.
"On January 30, 2013, GNF-A completed the ISA reviews for the balance of plant and has identified an additional 110 items relied on for safety (IROFS) for these areas which were existing safety controls. Implementation of the revised safety basis, IROFS, and application of management measures to the IROFS will be completed by March 31, 2013 per the current ISA action plan schedule.
"Because the revised ISA has designated existing safety controls as additional IROFS, GNF-A is making a report of this completion pursuant to the reporting requirements of 10CFR70 Appendix A(b)(1) within 24 hours.
"There was no event or plant condition that resulted in a degraded safety condition.
"Existing balance of plant area safety controls have been identified as IROFS per ISA action plan controls [continue to] perform their intended safety function.
"Balance of Plant Area milestone complete per ISA action plan."
The licensee will notify the R2 NRC Inspector (Thomas), North Carolina Division of Radiation Protection, and New Hanover County.
"In response to a Notice of Violation [NOV] (VIO 70-1113/2010-003), Global Nuclear Fuel Americas, LLC (GNF-A) committed to perform a review of the existing Integrated Safety Analysis (ISA). An ISA action plan and schedule for performing the ISA review was described in GNF-A's response to the NOV and the third milestone (balance of plant) was scheduled for completion by January 31, 2013.
"On January 30, 2013, GNF-A completed the ISA reviews for the balance of plant and has identified an additional 110 items relied on for safety (IROFS) for these areas which were existing safety controls. Implementation of the revised safety basis, IROFS, and application of management measures to the IROFS will be completed by March 31, 2013 per the current ISA action plan schedule.
"Because the revised ISA has designated existing safety controls as additional IROFS, GNF-A is making a report of this completion pursuant to the reporting requirements of 10CFR70 Appendix A(b)(1) within 24 hours.
"There was no event or plant condition that resulted in a degraded safety condition.
"Existing balance of plant area safety controls have been identified as IROFS per ISA action plan controls [continue to] perform their intended safety function.
"Balance of Plant Area milestone complete per ISA action plan."
The licensee will notify the R2 NRC Inspector (Thomas), North Carolina Division of Radiation Protection, and New Hanover County.