Event Notification Report for November 28, 2011

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
11/27/2011 - 11/28/2011

EVENT NUMBERS
474814748247483

Power Reactor
Event Number: 47481
Facility: SAN ONOFRE
Region: 4     State: CA
Unit: [] [2] []
RX Type: [1] W-3-LP,[2] CE,[3] CE
NRC Notified By: CHUCK HAIDAR
HQ OPS Officer: BILL HUFFMAN
Notification Date: 11/28/2011
Notification Time: 12:34 [ET]
Event Date: 11/28/2011
Event Time: 06:00 [PST]
Last Update Date: 11/28/2011
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
THOMAS FARNHOLTZ (R4DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
OFFSITE NOTIFICATION OF UNPLANNED ACIDIC SOLUTION DISCHARGE

"During the regeneration of the Unit 2 full flow condensate polishing demineralizer (FFCPD) resin, 5 percent sulfuric acid briefly overflowed from the bermed area. The majority of the acid went into the floor drains in the FFCPD area and then to the turbine building sump system.

"An estimated quantity of 2 gallons of sulfuric acid was released into the storm drains that discharged into the circulating water system. The quantity released was well below the reportable quantity. The fire department and environmental/hazmat team were contacted and responded.

"Precautionary notifications were made by SCE to:
- California Emergency Management Agency
- San Diego Dept. of Environmental Health."

The cause of the leak has been corrected and no additional discharge is anticipated. The licensee will notify the NRC Resident Inspector.


Power Reactor
Event Number: 47482
Facility: INDIAN POINT
Region: 1     State: NY
Unit: [2] [] []
RX Type: [2] W-4-LP,[3] W-4-LP
NRC Notified By: MATT JOHNSON
HQ OPS Officer: CHARLES TEAL
Notification Date: 11/28/2011
Notification Time: 18:40 [ET]
Event Date: 11/28/2011
Event Time: 16:50 [EST]
Last Update Date: 11/28/2011
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
WAYNE SCHMIDT (R1DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
2 N Y 100 Power Operation 100 Power Operation
Event Text
OFFSITE NOTIFICATION OF OIL SHEEN IN DISCHARGE CANAL

"At approximately 1650 EST on 11/28/2011 an oil sheen of about 20 ft. in diameter was observed in the Unit 2 discharge canal. The source of the oil is unknown at this time. There is no adverse impact on the plant. All required notifications have been made, including the New York State Dept. of Environmental Conservation, Westchester County Dept. of Health, and the U.S. Coast Guard National Response Center."

The NRC Resident Inspector has been informed.


Fuel Cycle Facility
Event Number: 47483
Facility: PADUCAH GASEOUS DIFFUSION PLANT
Region: 2     State: KY
Unit: [] [] []
RX Type: URANIUM ENRICHMENT FACILITY
Comments: 2 DEMOCRACY CENTER
6903 ROCKLEDGE DRIVE
BETHESDA, MD 20817 (301)564-3200
NRC Notified By: BILLY WALLACE
HQ OPS Officer: BILL HUFFMAN
Notification Date: 11/28/2011
Notification Time: 19:12 [ET]
Event Date: 11/28/2011
Event Time: 09:30 [CST]
Last Update Date: 11/28/2011
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
SCOTT FREEMAN (R2DO)
THOMAS HILTZ (NMSS)
Event Text
24-HOUR REPORT CONCERNING A LOCALIZED LOSS OF A GEOMETRY CRITICALITY CONTROL CONTINGENCY

"At 0930 CST on 11-28-11, during annual inspection of the C-400/C-409 floor drains and sumps according to procedure CP4-CU-CH6021, a chemical operator identified that an eye wash drain was no longer properly sealed around the concrete base and would not prevent solutions from entering the drain if challenged. NCSA [Nuclear Criticality Safety Assessment] CHM-001 requires specific drains to be sealed to prevent the accumulation of fissile material in the unsafe geometry drain system. In violation of NCSA CHM-001, the poured concrete base surrounding the eye wash drain #147 in C-400 was discovered to be broken loose from the floor so that it could no longer provide a seal against spilled uranium solution getting into the drain system.

SAFETY SIGNIFICANCE OF EVENTS
"Although the concrete block has broken loose from the floor, only a small crack exists at the base of the concrete block which would present a torturous solution path to the drain. Therefore, a large release will be prevented from transporting a significant amount of solution to the drain system. While the Safety Related Item failed, no fissile material was released onto the C-400 building floor and no fissile material entered the drain system through this drain.

POTENTIAL CRITICALITY PATHWAYS INVOLVED
"In order for a criticality to occur a release of greater than a safe mass of uranium onto the floor of C-400 would have to occur. A solution containing greater than a safe mass would then have to migrate to the drain, leak into the drain system, and accumulate in an unfavorable geometry.

CONTROLLED PARAMETERS
"The two process conditions relied upon for double contingency for this scenario are mass and geometry.

ESTIMATED AMOUNT, ENRICHMENT, FORM OF LICENSED MATERIAL
"Process is designed to handle uranium contaminated solutions with a maximum assay of 5.5 wt.% U235.

NUCLEAR CRITICALITY SAFETY CONTROL AND DESCRIPTION OF THE FAILURES OR DEFICIENCIES
"The first leg of double contingency is based on the mass of uranium in solution form that leaks out of the system. The analysis credits both the integrity of the system and the fact that the tanks and piping are inspected for leakage. Small leaks will be identified and fixed before they have leaked enough uranium mass in solution to be a concern. Since no leakage has occurred, this control was not violated. The second leg of double contingency relies on the integrity of the floor drain seals to prevent uranium solution from getting into the unsafe geometry drain system. Since a pathway from the floor to the drain system exists, this control was violated and the parameter was not maintained. Because the parameter was not maintained double contingency was not maintained. Double contingency was not maintained because the geometry parameter was not maintained.

CORRECTIVE ACTIONS
"1. Stop fissile solution operations in the vicinity of the eyewash drain. This was completed at 1000 CST on
11-28-11.
2. Restore the seal to this drain. Pending
3. Upon successful restoration of the seal for the eyewash drain #147, fissile solution operations may be
resumed. Pending

"Since one leg of double contingency was lost, this is being reported to the NRC as a 24-hour Event Report in accordance with NRC BL 91-01 Supplement 1.

"The NRC Resident Inspector has been notified of this event.

"PGDP Problem Report No. ATRC-11-3171 and PGDP Event Report No. PAD-2011-20."