45947

Power Reactor
Event Number: 45947
Facility: HATCH
Region: 2     State: GA
Unit: [1] [2] []
RX Type: [1] GE-4,[2] GE-4
NRC Notified By: AL MANNING
HQ OPS Officer: PETE SNYDER
Notification Date: 05/23/2010
Notification Time: 21:52 [ET]
Event Date: 05/23/2010
Event Time: 16:30 [EDT]
Last Update Date: 05/23/2010
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
DEBORAH SEYMOUR (R2DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
2 N Y 100 Power Operation 100 Power Operation
Event Text
NONFUNCTIONAL TECHNICAL SUPPORT CENTER VENTILATION

"The Technical Support Center (TSC) ventilation system was found to be non-functional on 5/23/10 at 1630 EDT. The system repair was complete at 1747 EDT on 5/23/10. The time period that the TSC ventilation system was non-functional exceeded the 30 minute time limit that is delineated in the Technical Requirements Manual section T 3.10.1. This event is reportable per 10 CFR 50.72 (b)(3)(xiii) as described in NUREG 1022 Rev. 1 since this issue affected an emergency response facility. Also, this 8 hour notification is being made in accordance with the Technical Requirements Manual section T 3.10.1.B.2.

"The alternate TSC facility remained functional during this entire time period."

The licensee notified the NRC Resident Inspector.