Event Notification Report for January 25, 2010
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
01/24/2010 - 01/25/2010
Fuel Cycle Facility
Event Number: 46168
Facility: GLOBAL NUCLEAR FUEL - AMERICAS
Region: 2 State: NC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
Comments: LEU CONVERSION (UF6 TO UO2)
LEU FABRICATION
LWR COMMERICAL FUEL
NRC Notified By: SCOTT MURRAY
HQ OPS Officer: VINCE KLCO
Region: 2 State: NC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
Comments: LEU CONVERSION (UF6 TO UO2)
LEU FABRICATION
LWR COMMERICAL FUEL
NRC Notified By: SCOTT MURRAY
HQ OPS Officer: VINCE KLCO
Notification Date: 08/11/2010
Notification Time: 14:45 [ET]
Event Date: 01/25/2010
Event Time: 09:50 [EDT]
Last Update Date: 08/11/2010
Notification Time: 14:45 [ET]
Event Date: 01/25/2010
Event Time: 09:50 [EDT]
Last Update Date: 08/11/2010
Emergency Class: NON EMERGENCY
10 CFR Section:
PART 70 APP A (b)(2) - LOSS OR DEGRADED SAFETY ITEMS
10 CFR Section:
PART 70 APP A (b)(2) - LOSS OR DEGRADED SAFETY ITEMS
Person (Organization):
BINOY DESAI (R2DO)
LARRY CAMPBELL (NMSS)
BINOY DESAI (R2DO)
LARRY CAMPBELL (NMSS)
DEGRADATION OF AN ITEM RELIED ON FOR SAFETY
"On January 25, 2010 during normal operation of a slugger press in the Fuel Manufacturing Building, a tube connecting the feed hood to the press became disconnected. After starting the vibrating feeder, an operator discovered the feed tube was slightly misaligned and some [uranium] powder had spilled into the hood. The operator immediately used the emergency stop button and the equipment was shutdown. A total of 6.9 kg was removed from the hood. An investigation determined that a clamp on the feed tube came loose, allowing the tube to separate from the fit up device.
"The two controlled parameters for criticality safety for this equipment are moderation and geometry and Items Relied on for Safety (IROFS) are established for both. When the tube became misaligned, one geometry related IROFS became unavailable to perform its intended safety function. Additional lROFS on geometry and moderation remained available to perform their intended safety functions and were not challenged. Therefore, this did not result in an unsafe condition.
"GNF-A's [Global Nuclear Fuel-Americas] initial review determined this event was not reportable. However, during an inspection February 22 to 26, 2010, NRC evaluated the event and determined that during the period when the tube was misaligned, one IROFS was not available to perform its intended safety function. Therefore, facility performance requirements were not met and a report to the NRC was required.
"The NRC issued a notice of violation to GNF-A on March 26, 2010 (70-1113/2010-002-01) for failure to report the event pursuant to 10CFR70 Appendix A(b)(2). The event is now being reported retroactively to satisfy this reporting requirement."
The licensee notified the NRC Region 2 Office, the North Carolina Radiation Protection Section and the New Hanover County Emergency Response Organization.
"On January 25, 2010 during normal operation of a slugger press in the Fuel Manufacturing Building, a tube connecting the feed hood to the press became disconnected. After starting the vibrating feeder, an operator discovered the feed tube was slightly misaligned and some [uranium] powder had spilled into the hood. The operator immediately used the emergency stop button and the equipment was shutdown. A total of 6.9 kg was removed from the hood. An investigation determined that a clamp on the feed tube came loose, allowing the tube to separate from the fit up device.
"The two controlled parameters for criticality safety for this equipment are moderation and geometry and Items Relied on for Safety (IROFS) are established for both. When the tube became misaligned, one geometry related IROFS became unavailable to perform its intended safety function. Additional lROFS on geometry and moderation remained available to perform their intended safety functions and were not challenged. Therefore, this did not result in an unsafe condition.
"GNF-A's [Global Nuclear Fuel-Americas] initial review determined this event was not reportable. However, during an inspection February 22 to 26, 2010, NRC evaluated the event and determined that during the period when the tube was misaligned, one IROFS was not available to perform its intended safety function. Therefore, facility performance requirements were not met and a report to the NRC was required.
"The NRC issued a notice of violation to GNF-A on March 26, 2010 (70-1113/2010-002-01) for failure to report the event pursuant to 10CFR70 Appendix A(b)(2). The event is now being reported retroactively to satisfy this reporting requirement."
The licensee notified the NRC Region 2 Office, the North Carolina Radiation Protection Section and the New Hanover County Emergency Response Organization.
Power Reactor
Event Number: 45653
Facility: COOK
Region: 3 State: MI
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: RICH KRESS
HQ OPS Officer: DONALD NORWOOD
Region: 3 State: MI
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: RICH KRESS
HQ OPS Officer: DONALD NORWOOD
Notification Date: 01/25/2010
Notification Time: 09:09 [ET]
Event Date: 01/25/2010
Event Time: 09:30 [EST]
Last Update Date: 01/25/2010
Notification Time: 09:09 [ET]
Event Date: 01/25/2010
Event Time: 09:30 [EST]
Last Update Date: 01/25/2010
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
PATTY PELKE (R3DO)
PATTY PELKE (R3DO)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
EMERGENCY RESPONSE DATA SYSTEM UNAVAILABLE DUE TO PLANT PROCESS COMPUTER MAINTENANCE
"At 0930 on Monday, January 25, 2010, the Cook Nuclear Plant (CNP) Unit 1 Plant Process Computer (PPC) will be removed from service for scheduled maintenance which will take the Emergency Response Data System (ERDS) out of service. The scheduled maintenance is planned from 0930 hours EST until 1530 hours EST. Personnel will be performing computer system backups and maintenance.
"Compensatory measures exist within the CNP Emergency Response procedure to provide plant data via the Emergency Notification System until the ERDS can be returned to service.
"The licensee has notified the NRC Senior Resident Inspector.
"This notification is being made in accordance with NUREG 1022 Revision 2 for CFR 50.72(b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system)."
* * * UPDATE FROM RICH KRESS TO JOE O'HARA AT 1207 EST ON 1/25/10 * * *
"The Unit 1 Plant Process Computer and the Emergency Response Data System (ERDS) were returned to functional Status at 11:35 on Monday, January 25, 2010.
"This follow up notification is being made to provide closure from the initial notification under CFR 50.72 (b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system)."
The NRC Resident Inspector has been notified.
Notified R3DO(Lipa)
"At 0930 on Monday, January 25, 2010, the Cook Nuclear Plant (CNP) Unit 1 Plant Process Computer (PPC) will be removed from service for scheduled maintenance which will take the Emergency Response Data System (ERDS) out of service. The scheduled maintenance is planned from 0930 hours EST until 1530 hours EST. Personnel will be performing computer system backups and maintenance.
"Compensatory measures exist within the CNP Emergency Response procedure to provide plant data via the Emergency Notification System until the ERDS can be returned to service.
"The licensee has notified the NRC Senior Resident Inspector.
"This notification is being made in accordance with NUREG 1022 Revision 2 for CFR 50.72(b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system)."
* * * UPDATE FROM RICH KRESS TO JOE O'HARA AT 1207 EST ON 1/25/10 * * *
"The Unit 1 Plant Process Computer and the Emergency Response Data System (ERDS) were returned to functional Status at 11:35 on Monday, January 25, 2010.
"This follow up notification is being made to provide closure from the initial notification under CFR 50.72 (b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system)."
The NRC Resident Inspector has been notified.
Notified R3DO(Lipa)
Fuel Cycle Facility
Event Number: 45655
Facility: WESTINGHOUSE ELECTRIC CORPORATION
Region: 2 State: SC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
NRC Notified By: GERALD COUTURE
HQ OPS Officer: JOE O'HARA
Region: 2 State: SC
Unit: [] [] []
RX Type: URANIUM FUEL FABRICATION
NRC Notified By: GERALD COUTURE
HQ OPS Officer: JOE O'HARA
Notification Date: 01/25/2010
Notification Time: 18:33 [ET]
Event Date: 01/25/2010
Event Time: 11:30 [EST]
Last Update Date: 09/30/2010
Notification Time: 18:33 [ET]
Event Date: 01/25/2010
Event Time: 11:30 [EST]
Last Update Date: 09/30/2010
Emergency Class: NON EMERGENCY
10 CFR Section:
PART 70 APP A (b)(1) - UNANALYZED CONDITION
10 CFR Section:
PART 70 APP A (b)(1) - UNANALYZED CONDITION
Person (Organization):
MARVIN SYKES (R2DO)
BRIAN SMITH (NMSS)
MARVIN SYKES (R2DO)
BRIAN SMITH (NMSS)
UNANALYZED CONDITION - OVERFLOW OF URANIUM BEARING AMMONIATED WASTEWATER
"It was reported to the EH&S Management that on January 24, 2010 a spill of approximately 200 gallons of uranium bearing ammoniated (5-7%) wastewater overflowed from the 'Q' tanks into the diked area below the tanks. These tanks are the final filtration prior to transfer of this liquid effluent to the outside treatment facility. Operators received a high level alarm and responded by shutting down the process in accordance with the operational procedure, with the overflow occurring for approximately six minutes. This event was the result of a pump failure in the tank discharge line. Notification was made to the on duty Health Physics (HP) staff and the on duty Incident Commander. Health Physics staff responded within minutes and used a Drager counter to determine the ammonia concentrations present. Readings in the immediate area of the dike were as high as 256 ppm ammonia. Readings in adjacent areas of the facility were approximately 150 ppm ammonia. Non-essential personnel were evacuated and essential personnel were instructed to don PPE-respirators with ammonia cartridges.
"Operations cleanup of the area was completed and with normal plant ventilation running the ppm ammonia concentrations were returned to < 25 ppm within approximately two hours. The failed pump has been repaired and returned to service. Based on the quick response of the HP staff, evacuations and appropriate use of PPE, no workers were exposed to significant concentrations and no medical attention was necessary.
"Notification is made based on 10CFR70 Appendix A (b)(1) 'Any event or condition that results in the facility being in a state that was not analyzed, was improperly analyzed, or is different from that analyzed in the Integrated Safety Analysis, and which results in failure to meet the performance requirements of 10CFR70.61.' The potential for a loss of containment was recognized and evaluated in one of the Process Hazards Analysis (PHA) which constitutes the Integrated Safety Analysis for this system. The PHA identified several initiating events which could lead to a high level and loss of containment event. The appropriate safeguards were identified, including the procedural responses, the evacuation during such an emergency of the workers in the enclosed chemical area, and the use of appropriate PPE. The consequences of the event were identified as a potential for personnel inhalation and exposure hazard from the uranium bearing ammoniated wastewater. However, the PHA did not specifically indentify that the potential existed for the consequences to exceed the Intermediate Consequence criteria for credible events. In accordance with SNM-1107 License Requirements for the Columbia Plant Intermediate Consequences are those that have the potential for a worker to receive greater than or equal to ERPG-2 chemical exposures. (ERPG-2 value for ammonia is 150 ppm.) Since the Q-Tank contains comingled uranium and chemicals, the Intermediate Consequences of 10CFR70.61 apply. Failure to identify that an Intermediate Consequence event was credible led to that event not being included in the Conversion ISA Summary ISA-03 and not designating Items Relied on For Safety (IROFS) for that accident sequence.
"Corrective Actions: As stated previously, the pump which failed has been repaired and returned to service. Actions taken by the staff to mitigate the event were appropriate and in accordance with approved procedures. Normal ventilation system operation reduced the concentrations to acceptable levels. [These actions are] complete.
"The safeguards identified in the PHA will be evaluated in the ISA and appropriate selections of IROFS will be made based on that evaluation and included in the ISA summary. [These actions are] in progress."
* * * UPDATE AT 1053 ON 9/30/2010 FROM GERARD COUTURE TO ERIC SIMPSON * * *
"Time and Date of Event: September 30, 2010, 0800.
"Previously Westinghouse had reported to the Nuclear Regulatory Commission (NRC) in Licensee Event Report #45655, that the conversion Integrated Safety Analysis (ISA) did not specifically indentify that the potential existed for the consequences of overflows or spills in the conversion wastewater system to exceed the Intermediate Consequence criteria for credible events based on chemical exposure. In accordance with SNM-1107 License Requirements for the Columbia Plant intermediate consequences are those that have the potential for a worker to receive greater than or equal to ERPG-2 chemical exposures. In the required written follow up to that event (LTR-RAC-10-16, February 23, 2010). Westinghouse committed to perform an extent of condition review of other chemical release scenarios and designate necessary Items Relied On For Safety (IROFS). Westinghouse further provided NRC the casual analysis related to that event, (LTR-RAC-10-28, April 6, 2010) which identified the need to quantitatively evaluate chemical release scenarios. Westinghouse has completed the necessary evaluations and determined that additional scenarios exist which have the potential to exceed the performance requirements of 10 CFR 70.61. EH&S Management has now determined that these analyses, the necessary ISA and ISA Summary revisions, and the identification of appropriate IROFS are complete. For these new ISAs the necessary controls, procedures and equipment are in place and the performance requirements are met in a fully compliant manner taking into account the newly identified IROFS.
"The extent of condition review identified additional areas within the facility where chemical releases have the potential to exceed consequence thresholds for facility workers. There is one area where potential consequences could challenge off-site receptor chemical consequence criteria. The areas covered by the extent of condition review impacted by this updated chemical analysis are Conversion, the Scrap Uranium Processing, the Solvent Extraction System, and the facility Wastewater Tanks.
"Notification is made based on 10CFR70 Appendix A (b)(1) 'Any event or condition that results in the facility being in a state that was not analyzed, was improperly analyzed, or is different from that analyzed in the Integrated Safety Analysis, and which results in failure to meet the performance requirements of 10CFR70.61.' The potential for a loss of containment was recognized and evaluated in the applicable Process Hazards Analysis (PHA) which constitutes the Integrated Safety Analysis. The PHAs identified initiating events which could lead to loss of containment. The appropriate safeguards were identified, including the procedural responses, the evacuation during such an emergency of the workers in the enclosed chemical area, and the use of appropriate PPE. Failure to identify in the areas mentioned above those chemical release consequences could exceed 10CFR70.61 criteria led to these events not being included in the applicable ISA Summary and not designating Items Relied on For Safety (IROFS) for these accident sequences.
"Corrective Actions: As stated previously, the associated Integrated Safety Analysis, Integrated Safety Analysis Summaries, and designation of IROFS to ensure the performance requirements are satisfied is complete for the extent of condition reviews previously committed to by Westinghouse.
"Full implementation of the revised ISA Summaries, to include all required procedure revisions and appropriate training will be completed by October 30, 2010."
Notified R2DO (Lesser) and NMSS EO (Rubenstone).
"It was reported to the EH&S Management that on January 24, 2010 a spill of approximately 200 gallons of uranium bearing ammoniated (5-7%) wastewater overflowed from the 'Q' tanks into the diked area below the tanks. These tanks are the final filtration prior to transfer of this liquid effluent to the outside treatment facility. Operators received a high level alarm and responded by shutting down the process in accordance with the operational procedure, with the overflow occurring for approximately six minutes. This event was the result of a pump failure in the tank discharge line. Notification was made to the on duty Health Physics (HP) staff and the on duty Incident Commander. Health Physics staff responded within minutes and used a Drager counter to determine the ammonia concentrations present. Readings in the immediate area of the dike were as high as 256 ppm ammonia. Readings in adjacent areas of the facility were approximately 150 ppm ammonia. Non-essential personnel were evacuated and essential personnel were instructed to don PPE-respirators with ammonia cartridges.
"Operations cleanup of the area was completed and with normal plant ventilation running the ppm ammonia concentrations were returned to < 25 ppm within approximately two hours. The failed pump has been repaired and returned to service. Based on the quick response of the HP staff, evacuations and appropriate use of PPE, no workers were exposed to significant concentrations and no medical attention was necessary.
"Notification is made based on 10CFR70 Appendix A (b)(1) 'Any event or condition that results in the facility being in a state that was not analyzed, was improperly analyzed, or is different from that analyzed in the Integrated Safety Analysis, and which results in failure to meet the performance requirements of 10CFR70.61.' The potential for a loss of containment was recognized and evaluated in one of the Process Hazards Analysis (PHA) which constitutes the Integrated Safety Analysis for this system. The PHA identified several initiating events which could lead to a high level and loss of containment event. The appropriate safeguards were identified, including the procedural responses, the evacuation during such an emergency of the workers in the enclosed chemical area, and the use of appropriate PPE. The consequences of the event were identified as a potential for personnel inhalation and exposure hazard from the uranium bearing ammoniated wastewater. However, the PHA did not specifically indentify that the potential existed for the consequences to exceed the Intermediate Consequence criteria for credible events. In accordance with SNM-1107 License Requirements for the Columbia Plant Intermediate Consequences are those that have the potential for a worker to receive greater than or equal to ERPG-2 chemical exposures. (ERPG-2 value for ammonia is 150 ppm.) Since the Q-Tank contains comingled uranium and chemicals, the Intermediate Consequences of 10CFR70.61 apply. Failure to identify that an Intermediate Consequence event was credible led to that event not being included in the Conversion ISA Summary ISA-03 and not designating Items Relied on For Safety (IROFS) for that accident sequence.
"Corrective Actions: As stated previously, the pump which failed has been repaired and returned to service. Actions taken by the staff to mitigate the event were appropriate and in accordance with approved procedures. Normal ventilation system operation reduced the concentrations to acceptable levels. [These actions are] complete.
"The safeguards identified in the PHA will be evaluated in the ISA and appropriate selections of IROFS will be made based on that evaluation and included in the ISA summary. [These actions are] in progress."
* * * UPDATE AT 1053 ON 9/30/2010 FROM GERARD COUTURE TO ERIC SIMPSON * * *
"Time and Date of Event: September 30, 2010, 0800.
"Previously Westinghouse had reported to the Nuclear Regulatory Commission (NRC) in Licensee Event Report #45655, that the conversion Integrated Safety Analysis (ISA) did not specifically indentify that the potential existed for the consequences of overflows or spills in the conversion wastewater system to exceed the Intermediate Consequence criteria for credible events based on chemical exposure. In accordance with SNM-1107 License Requirements for the Columbia Plant intermediate consequences are those that have the potential for a worker to receive greater than or equal to ERPG-2 chemical exposures. In the required written follow up to that event (LTR-RAC-10-16, February 23, 2010). Westinghouse committed to perform an extent of condition review of other chemical release scenarios and designate necessary Items Relied On For Safety (IROFS). Westinghouse further provided NRC the casual analysis related to that event, (LTR-RAC-10-28, April 6, 2010) which identified the need to quantitatively evaluate chemical release scenarios. Westinghouse has completed the necessary evaluations and determined that additional scenarios exist which have the potential to exceed the performance requirements of 10 CFR 70.61. EH&S Management has now determined that these analyses, the necessary ISA and ISA Summary revisions, and the identification of appropriate IROFS are complete. For these new ISAs the necessary controls, procedures and equipment are in place and the performance requirements are met in a fully compliant manner taking into account the newly identified IROFS.
"The extent of condition review identified additional areas within the facility where chemical releases have the potential to exceed consequence thresholds for facility workers. There is one area where potential consequences could challenge off-site receptor chemical consequence criteria. The areas covered by the extent of condition review impacted by this updated chemical analysis are Conversion, the Scrap Uranium Processing, the Solvent Extraction System, and the facility Wastewater Tanks.
"Notification is made based on 10CFR70 Appendix A (b)(1) 'Any event or condition that results in the facility being in a state that was not analyzed, was improperly analyzed, or is different from that analyzed in the Integrated Safety Analysis, and which results in failure to meet the performance requirements of 10CFR70.61.' The potential for a loss of containment was recognized and evaluated in the applicable Process Hazards Analysis (PHA) which constitutes the Integrated Safety Analysis. The PHAs identified initiating events which could lead to loss of containment. The appropriate safeguards were identified, including the procedural responses, the evacuation during such an emergency of the workers in the enclosed chemical area, and the use of appropriate PPE. Failure to identify in the areas mentioned above those chemical release consequences could exceed 10CFR70.61 criteria led to these events not being included in the applicable ISA Summary and not designating Items Relied on For Safety (IROFS) for these accident sequences.
"Corrective Actions: As stated previously, the associated Integrated Safety Analysis, Integrated Safety Analysis Summaries, and designation of IROFS to ensure the performance requirements are satisfied is complete for the extent of condition reviews previously committed to by Westinghouse.
"Full implementation of the revised ISA Summaries, to include all required procedure revisions and appropriate training will be completed by October 30, 2010."
Notified R2DO (Lesser) and NMSS EO (Rubenstone).