Event Notification Report for November 21, 2009
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
11/20/2009 - 11/21/2009
EVENT NUMBERS
45512455134551445585
Power Reactor
Event Number: 45512
Facility: FERMI
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: GREGG MILLER
HQ OPS Officer: VINCE KLCO
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: GREGG MILLER
HQ OPS Officer: VINCE KLCO
Notification Date: 11/21/2009
Notification Time: 05:58 [ET]
Event Date: 11/21/2009
Event Time: 05:00 [EST]
Last Update Date: 11/22/2009
Notification Time: 05:58 [ET]
Event Date: 11/21/2009
Event Time: 05:00 [EST]
Last Update Date: 11/22/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
ERIC DUNCAN (R3DO)
ERIC DUNCAN (R3DO)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | Y | 100 | Power Operation | 100 | Power Operation |
TECHNICAL SUPPORT CENTER OUT OF SERVICE DUE TO PLANNED ELECTRICAL MAINTENANCE
"On November 21, 2009, Fermi 2 [removed] the Technical Support Center (TSC) from operation to facilitate maintenance on the facilities' 480-volt AC power supply. This work affects TSC lighting, computers, and ventilation. During this work, which is expected to last over 8 hours, the TSC will be unavailable. In the event TSC activation is necessary, the Emergency Operations Facility (EOF) will be used for the TSC function. Activation and use of the EOF as a backup for the TSC is included in Fermi 2's Radiological Emergency Response Preparedness Plan. The Emergency Call Out System (ECOS) is designed to facilitate contacting TSC personnel to respond directly to the EOF in the event of an emergency. Fermi 2 is making this notification in accordance with 10 CFR 50.72(b)(3)(xiii). Fermi 2 will notify the NRC upon completion of this work. Fermi 2 will notify the NRC Resident Inspector."
* * * UPDATE FROM GREG MILLER TO VINCE KLCO ON 11/22/2009 AT 0036 EST * * *
The planned maintenance has been completed and the TSC has been restored as an Emergency Response Facility.
The licensee will notify the NRC Resident Inspector.
"On November 21, 2009, Fermi 2 [removed] the Technical Support Center (TSC) from operation to facilitate maintenance on the facilities' 480-volt AC power supply. This work affects TSC lighting, computers, and ventilation. During this work, which is expected to last over 8 hours, the TSC will be unavailable. In the event TSC activation is necessary, the Emergency Operations Facility (EOF) will be used for the TSC function. Activation and use of the EOF as a backup for the TSC is included in Fermi 2's Radiological Emergency Response Preparedness Plan. The Emergency Call Out System (ECOS) is designed to facilitate contacting TSC personnel to respond directly to the EOF in the event of an emergency. Fermi 2 is making this notification in accordance with 10 CFR 50.72(b)(3)(xiii). Fermi 2 will notify the NRC upon completion of this work. Fermi 2 will notify the NRC Resident Inspector."
* * * UPDATE FROM GREG MILLER TO VINCE KLCO ON 11/22/2009 AT 0036 EST * * *
The planned maintenance has been completed and the TSC has been restored as an Emergency Response Facility.
The licensee will notify the NRC Resident Inspector.
Power Reactor
Event Number: 45513
Facility: SURRY
Region: 2 State: VA
Unit: [1] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: GEOFFREY HILL
HQ OPS Officer: PETE SNYDER
Region: 2 State: VA
Unit: [1] [2] []
RX Type: [1] W-3-LP,[2] W-3-LP
NRC Notified By: GEOFFREY HILL
HQ OPS Officer: PETE SNYDER
Notification Date: 11/21/2009
Notification Time: 16:02 [ET]
Event Date: 11/21/2009
Event Time: 00:00 [EST]
Last Update Date: 11/21/2009
Notification Time: 16:02 [ET]
Event Date: 11/21/2009
Event Time: 00:00 [EST]
Last Update Date: 11/21/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
JONATHAN BARTLEY (R2DO)
JONATHAN BARTLEY (R2DO)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | Y | 100 | Power Operation | 100 | Power Operation |
| 2 | N | N | 0 | Refueling | 0 | Refueling |
NOTIFICATION OF RESCUE SQUAD FOR OFFSITE INJURY OF HUNTERS
"On 11/21/2009 at 14:27, two individuals arrived at the Surry Power Station Security Checkpoint with an accidental gun shot victim. The three individuals were hunting approximately one mile offsite when one individual was accidentally struck by gun fire. The other two individuals transported the injured individual to the Security Checkpoint at the station. Station personnel contacted the local Sheriff's Department, local Volunteer Rescue Squad, Virginia State Police, and Air Ambulance for assistance. Wounds do not appear to be life threatening, and the individual is being transported offsite via Air Ambulance.
"The site NRC Resident has been notified.
"This notification is being transmitted due to notification of other Government Agencies in accordance with 10CFR50.72(b)(2)(xi)."
"On 11/21/2009 at 14:27, two individuals arrived at the Surry Power Station Security Checkpoint with an accidental gun shot victim. The three individuals were hunting approximately one mile offsite when one individual was accidentally struck by gun fire. The other two individuals transported the injured individual to the Security Checkpoint at the station. Station personnel contacted the local Sheriff's Department, local Volunteer Rescue Squad, Virginia State Police, and Air Ambulance for assistance. Wounds do not appear to be life threatening, and the individual is being transported offsite via Air Ambulance.
"The site NRC Resident has been notified.
"This notification is being transmitted due to notification of other Government Agencies in accordance with 10CFR50.72(b)(2)(xi)."
Power Reactor
Event Number: 45514
Facility: THREE MILE ISLAND
Region: 1 State: PA
Unit: [1] [] []
RX Type: [1] B&W-L-LP,[2] B&W-L-LP
NRC Notified By: ROGER BARNES
HQ OPS Officer: BILL HUFFMAN
Region: 1 State: PA
Unit: [1] [] []
RX Type: [1] B&W-L-LP,[2] B&W-L-LP
NRC Notified By: ROGER BARNES
HQ OPS Officer: BILL HUFFMAN
Notification Date: 11/22/2009
Notification Time: 01:13 [ET]
Event Date: 11/21/2009
Event Time: 22:45 [EST]
Last Update Date: 12/18/2009
Notification Time: 01:13 [ET]
Event Date: 11/21/2009
Event Time: 22:45 [EST]
Last Update Date: 12/18/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
10 CFR Section:
50.72(b)(2)(xi) - OFFSITE NOTIFICATION
Person (Organization):
RAYMOND MCKINLEY (R1DO)
SAMSON LEE (NRR)
SAM COLLINS (R1 R)
JOHN GROBE (NRR)
MICHAEL JOHNSON (EDO)
RAYMOND MCKINLEY (R1DO)
SAMSON LEE (NRR)
SAM COLLINS (R1 R)
JOHN GROBE (NRR)
MICHAEL JOHNSON (EDO)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | N | N | 0 | Refueling | 0 | Refueling |
RADIATION RELEASE IN CONTAINMENT ASSOCIATED WITH STEAM GENERATOR REMOVAL
"This event is being reported via the ENS to the NRC Operations Center within four hours after notifications were made to the Pennsylvania Emergency Management Agency and local counties for an event of potential public interest. This notification was made at 22:45 on November 21, 2009, after the occurrence of an event related to the safety and health of onsite personnel for which a press release has been made. The press release was made following the event of potential public interest notifications. This report is being made under 10 CFR 72.75(b)(2).
"At approximately 16:00 on Saturday November 21, 2009, low levels of radiation activity were measured on radiation monitors installed in the TMI-1 reactor building. Personnel were directed to immediately leave the reactor building until the source of the activity could be identified. Surveys directly outside of the reactor building construction opening indicated a slight increase in activity. Levels have returned to normal. No contamination was identified outside of the reactor building. Approximately 150 workers were monitored for exposure to the radiation activity. No worker approached or exceeded any exposure limits. The sources of the activity are believed to be from maintenance tasks related to cutting lines in preparation for removal of the 'B' Steam Generator."
The licensee is still investigating the cause of the event but indicated that the radiation release is no longer in progress. Containment Ventilation is established to provide an inflow into containment to the extent possible (considering the openings in containment).
The licensee contacted state and local authorities and the Pennsylvania Emergency Management Agency (PEMA). The licensee notified the NRC Resident Inspector. The licensee has also issued a press release.
* * * UPDATE FROM NEFF TO TEAL AT 1824 EST ON 12/18/2009 * * *
"This provides an update to notification EN #45514 that reported a non-emergency offsite notification for an event on November 21, 2009, at the Three Mile island Nuclear Station.
"Updated news release and notifications to local, state and federal elected and regulatory officials were performed today, December 18, 2009, that provide an outage update as well as communication the results of analysis of Offsite Environmental Monitors following the November 21, 2009 event."
The licensee notified NRC Region I. Notified R1DO (Barkley).
"This event is being reported via the ENS to the NRC Operations Center within four hours after notifications were made to the Pennsylvania Emergency Management Agency and local counties for an event of potential public interest. This notification was made at 22:45 on November 21, 2009, after the occurrence of an event related to the safety and health of onsite personnel for which a press release has been made. The press release was made following the event of potential public interest notifications. This report is being made under 10 CFR 72.75(b)(2).
"At approximately 16:00 on Saturday November 21, 2009, low levels of radiation activity were measured on radiation monitors installed in the TMI-1 reactor building. Personnel were directed to immediately leave the reactor building until the source of the activity could be identified. Surveys directly outside of the reactor building construction opening indicated a slight increase in activity. Levels have returned to normal. No contamination was identified outside of the reactor building. Approximately 150 workers were monitored for exposure to the radiation activity. No worker approached or exceeded any exposure limits. The sources of the activity are believed to be from maintenance tasks related to cutting lines in preparation for removal of the 'B' Steam Generator."
The licensee is still investigating the cause of the event but indicated that the radiation release is no longer in progress. Containment Ventilation is established to provide an inflow into containment to the extent possible (considering the openings in containment).
The licensee contacted state and local authorities and the Pennsylvania Emergency Management Agency (PEMA). The licensee notified the NRC Resident Inspector. The licensee has also issued a press release.
* * * UPDATE FROM NEFF TO TEAL AT 1824 EST ON 12/18/2009 * * *
"This provides an update to notification EN #45514 that reported a non-emergency offsite notification for an event on November 21, 2009, at the Three Mile island Nuclear Station.
"Updated news release and notifications to local, state and federal elected and regulatory officials were performed today, December 18, 2009, that provide an outage update as well as communication the results of analysis of Offsite Environmental Monitors following the November 21, 2009 event."
The licensee notified NRC Region I. Notified R1DO (Barkley).
Power Reactor
Event Number: 45585
Facility: DIABLO CANYON
Region: 4 State: CA
Unit: [] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: MURRELL EVANS
HQ OPS Officer: PETE SNYDER
Region: 4 State: CA
Unit: [] [2] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: MURRELL EVANS
HQ OPS Officer: PETE SNYDER
Notification Date: 12/22/2009
Notification Time: 11:14 [ET]
Event Date: 11/21/2009
Event Time: 21:13 [PST]
Last Update Date: 12/22/2009
Notification Time: 11:14 [ET]
Event Date: 11/21/2009
Event Time: 21:13 [PST]
Last Update Date: 12/22/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
10 CFR Section:
50.73(a)(1) - INVALID SPECIF SYSTEM ACTUATION
Person (Organization):
WAYNE WALKER (R4DO)
WAYNE WALKER (R4DO)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | Y | 100 | Power Operation | 100 | Power Operation |
UNEXPECTED AUTOMATIC START OF THE 2-1 EMERGENCY DIESEL GENERATOR (EDG)
"This notification is being made in accordance with 10 CFR 50.73(a)(i), which states, in part; that in case of an invalid actuation reported under 10 CFR 50.73(a)(2)(iv)(A), other than the actuation of the Reactor Protection System when the reactor is critical, the licensee may provide a telephone notification to the NRC within 60 days after discovery of the event instead of submitting a written Licensee Event Report.
"On November 21, 2009, at 2113 PST, EDG 2-1 automatically started, but did not load, due to an attempted replacement of an indicating light that caused a control circuit electrical short and opening the power supply fuse. EDG 2-2 and EDG 2-3 were unaffected by this event. Plant operators entered TS 3.8.1, AC Sources - Operating, due to the loss of the Startup Feeder indication circuit. No actual condition requiring the start of EDG 2-1 existed.
"The EDG 2-1 4kV Bus Start up Transfer Feeder Undervoltage Relay was placed in bypass (knife switch #10 for relay 27 HGU opened), the EDG was shutdown at 2147 PST and placed in standby operation at 2148 PST. This inadvertent start relay input is not a required safety function, but provides an anticipatory start of the EDG. The actuated relay input is not required for operability, thus the EDG was operable at 2148 PST.
"Electrical Maintenance replaced the affected sensing relay circuit fuse (52HG14 "UA" fuses), tightened the indicating light socket for SUT 2 2 Potential C A Phase, and reset 27HGU (Startup Feeder UV for 4kV Bus G). On November 22, 2009, at 0729 PST, TS 3.8.1 was exited.
"The consequences of this event were limited to the unplanned start of EDG 2-1. The EDG started and functioned in accordance with its design. Since no valid signal which required the EDG to start, and since the start occurred inadvertently as the result of a known maintenance action (resulting in a single component failure, a protective fuse opening), this event has been classified as an invalid actuation.
"The licensee has notified the NRC Resident Inspector."
"This notification is being made in accordance with 10 CFR 50.73(a)(i), which states, in part; that in case of an invalid actuation reported under 10 CFR 50.73(a)(2)(iv)(A), other than the actuation of the Reactor Protection System when the reactor is critical, the licensee may provide a telephone notification to the NRC within 60 days after discovery of the event instead of submitting a written Licensee Event Report.
"On November 21, 2009, at 2113 PST, EDG 2-1 automatically started, but did not load, due to an attempted replacement of an indicating light that caused a control circuit electrical short and opening the power supply fuse. EDG 2-2 and EDG 2-3 were unaffected by this event. Plant operators entered TS 3.8.1, AC Sources - Operating, due to the loss of the Startup Feeder indication circuit. No actual condition requiring the start of EDG 2-1 existed.
"The EDG 2-1 4kV Bus Start up Transfer Feeder Undervoltage Relay was placed in bypass (knife switch #10 for relay 27 HGU opened), the EDG was shutdown at 2147 PST and placed in standby operation at 2148 PST. This inadvertent start relay input is not a required safety function, but provides an anticipatory start of the EDG. The actuated relay input is not required for operability, thus the EDG was operable at 2148 PST.
"Electrical Maintenance replaced the affected sensing relay circuit fuse (52HG14 "UA" fuses), tightened the indicating light socket for SUT 2 2 Potential C A Phase, and reset 27HGU (Startup Feeder UV for 4kV Bus G). On November 22, 2009, at 0729 PST, TS 3.8.1 was exited.
"The consequences of this event were limited to the unplanned start of EDG 2-1. The EDG started and functioned in accordance with its design. Since no valid signal which required the EDG to start, and since the start occurred inadvertently as the result of a known maintenance action (resulting in a single component failure, a protective fuse opening), this event has been classified as an invalid actuation.
"The licensee has notified the NRC Resident Inspector."