Event Notification Report for July 07, 2009

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
07/06/2009 - 07/07/2009

EVENT NUMBERS
45188

!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Fuel Cycle Facility
Event Number: 45188
Facility: PORTSMOUTH GASEOUS DIFFUSION PLANT
Region: 2     State: OH
Unit: [] [] []
RX Type: URANIUM ENRICHMENT FACILITY
Comments: 2 DEMOCRACY CENTER
6903 ROCKLEDGE DRIVE
BETHESDA, MD 20817 (301)564-3200
NRC Notified By: RON CRABTREE
HQ OPS Officer: DONALD NORWOOD
Notification Date: 07/07/2009
Notification Time: 01:57 [ET]
Event Date: 07/07/2009
Event Time: 00:54 [EDT]
Last Update Date: 07/09/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
Person (Organization):
RANDY MUSSER (R2DO)
EARL EASTON (NMSS)
Event Text
4-HOUR REPORT DUE TO NOTIFICATION OF OHIO EPA BECAUSE OF BOILER OPACITY LIMIT BEING EXCEEDED

"At 2130 hours, 07/06/09, the PORTS Plant Shift Superintendent's (PSS) Office was notified of an operational upset at the X-600 Steam Plant Facility due to a loss of power on the #3 (operating) Boiler. The operational upset resulted in three separate six minute periods, where the permissible opacity limit was exceeded, while power was being restored to the boiler. The PORTS PSS Office notified the Ohio Environmental Protection Agency (OEPA) of this incident, at 0054 hours, 07/07/09. This notification to another government agency is reportable to the NRC as a 4-hour Event, per the United States Enrichment Corporation (USEC) Nuclear Regulatory Event Reporting Procedure UE2-RA-RE1030, Appendix D, Section P (Miscellaneous) which states: 'USEC shall notify NRC of any event or situation, related to the health and safety of the public or on-site personnel, or protection of the environment, for which a news release is planned or notification to other government agencies has been or will be made. Such an event may include an on-site fatality or inadvertent release of radioactively contaminated materials'."

The licensee notified the Paducah NRC Resident Inspector.

* * * RETRACTION FROM ERIC SPAETH TO JOE O'HARA AT 1427 EDT ON 7/9/09 * * *

"PORTS [Nuclear Regulatory Affairs] NRA has reviewed the basis for the above NRC event notification and recommends that event notification #45188 be retracted. The following provides the basis for this recommendation. NUREG-1022, Event Reporting Guidelines 10 CFR 50.72 and 50.73 was reviewed. In essence, the following sentence from the NUREG provides sufficient clarification of the reporting criteria to assess the applicability of the steam plant opacity exceedances: 'The purpose of this criterion is to ensure the NRC is made aware of issues that will cause heightened public or government concern related to the radiological health and safety of the public or on-site personnel or protection of the environment.' The significance of opacity exceedances as they might impact the public or on-site workers was discussed with environmental compliance personnel. It was concluded that beyond any regulatory issues, opacity exceedances of limited duration pose no significant health or environmental concerns. Based on the specifics of this event and the additional guidance provided by the NRC, more specifically that NRC is most concerned about events or situations that would cause heightened public or government concern, the opacity exceedances reported to the OEPA should not trigger a 4 hour NRC report."

The licensee notified the NRC Resident Inspector.

Notified R2DO(Nease) and NMSS EO(Tschiltz)