Skip to main content

Event Notification Report for April 25, 2009

U.S. Nuclear Regulatory Commission
Operations Center

EVENT REPORTS FOR
04/24/2009 - 04/25/2009

EVENT NUMBERS
4502045021

Power Reactor
Event Number: 45020
Facility: BYRON
Region: 3     State: IL
Unit: [1] [] []
RX Type: [1] W-4-LP,[2] W-4-LP
NRC Notified By: KEN HETZEL
HQ OPS Officer: BILL HUFFMAN
Notification Date: 04/25/2009
Notification Time: 16:02 [ET]
Event Date: 04/25/2009
Event Time: 10:48 [CDT]
Last Update Date: 04/25/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
JAMNES CAMERON (R3DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 N Y 100 Power Operation 100 Power Operation
Event Text
ERDS UNAVAILABILITY DUE TO PLANT PROCESS COMPUTER FAILURE

"The Unit One Plant Process Computer failed at 1048 CDT. The failure disabled plant data information inputs to the NRC Emergency Response Data System (ERDS). ERDS unavailability was validated by the NRC. ERDS was not restored within one hour, which necessitates this ENS notification per 50.72(b)(3)(xiii). The Plant Process Computer was restored at 1342, which restored ERDS."

The NRC Resident Inspector has been notified.


Power Reactor
Event Number: 45021
Facility: OYSTER CREEK
Region: 1     State: NJ
Unit: [1] [] []
RX Type: [1] GE-2
NRC Notified By: HERB TRITT
HQ OPS Officer: BILL HUFFMAN
Notification Date: 04/25/2009
Notification Time: 20:50 [ET]
Event Date: 04/25/2009
Event Time: 18:05 [EDT]
Last Update Date: 04/25/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
PAUL KROHN (R1DO)
Power Reactor Unit Info
Unit SCRAM Code RX Crit Initial PWR Initial RX Mode Current PWR Current RX Mode
1 M/R Y 100 Power Operation 0 Hot Shutdown
Event Text
MANUAL SCRAM FOLLOWING LOSS OF COOLING TO MAIN TRANSFORMER

"Oyster Creek inserted a manual reactor scram due to a loss of cooling to one of its main transformers. All systems responded normally during the reactor scram. The NRC Resident Inspector has been notified. "

The manual scram was described as uncomplicated. All control rods fully inserted. No safeties or PORVs lifted during the transient. There were no electrical power issues besides the problem associated with the main transformer cooling. Normal feedwater cooling was maintained to the reactor and decay heat removal is to the main condenser. There were no ESF actions during the transient.

The loss of cooling was to one of Oyster Creeks' two main transformers. Power to the transformer cooling system components (oil cooling pumps and cooling fans) was lost when the control power transformer to the cooling system components failed. The licensee manually scrammed because sustained operation at power would not be possible with loss of cooling to the main transformer and operation with one of the main transformers de-energized is also not possible.

The licensee will continue to cold shutdown to perform other maintenance activities while shutdown.

The NRC Resident Inspector has been notified.