Event Notification Report for April 11, 2009
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
04/10/2009 - 04/11/2009
Power Reactor
Event Number: 44984
Facility: FERMI
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: ROBERT MATUSZAK
HQ OPS Officer: DONALD NORWOOD
Region: 3 State: MI
Unit: [2] [] []
RX Type: [2] GE-4
NRC Notified By: ROBERT MATUSZAK
HQ OPS Officer: DONALD NORWOOD
Notification Date: 04/11/2009
Notification Time: 14:27 [ET]
Event Date: 04/11/2009
Event Time: 12:10 [EDT]
Last Update Date: 05/01/2009
Notification Time: 14:27 [ET]
Event Date: 04/11/2009
Event Time: 12:10 [EDT]
Last Update Date: 05/01/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
10 CFR Section:
50.72(b)(3)(xiii) - LOSS COMM/ASMT/RESPONSE
Person (Organization):
ROBERT DALEY (R3)
ROBERT DALEY (R3)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | N | N | 0 | Refueling | 0 | Refueling |
LOSS OF EMERGENCY ASSESSMENT CAPABILITY - TECHNICAL SUPPORT CENTER VENTILATION UNAVAILABLE
"Notified by Engineering that Technical Support Center (TSC) emergency charcoal sample failed acceptance criteria. Declared TSC ventilation unavailable at 12:10 PM EDT, 4/11/09. TSC ventilation supports RERP radiological habitability function and as such represents a major loss of emergency assessment capability, offsite response capability, or offsite communications capability in accordance with 10CFR50.72(b)(3)(xiii). Notified all Shift Managers if an emergency event is declared (Alert or higher), Shift Managers will need to modify emergency call out service so that TSC staffing report to Emergency Operating Facility (EOF). The use of the EOF as a backup facility for the TSC is included in Fermi's RERP Plan. Fermi will notify the NRC upon completion of corrective maintenance."
The licensee notified the NRC Resident Inspector.
* * * UPDATE FROM ROBERT MATUSZAK TO DONALD NORWOOD ON 5/1/09 AT 1621 EDT * * *
"Regarding Technical Support Center (TSC) ventilation unavailability: Corrective maintenance to restore HVAC system has been completed satisfactorily. TSC has been restored as an Emergency Response facility."
The TSC was declared operable at 1457 EDT. Corrective maintenance included replacing the out-of-spec charcoal filters and satisfactory follow-up tests.
The licensee notified the NRC Resident Inspector. Notified R3DO (Hills).
"Notified by Engineering that Technical Support Center (TSC) emergency charcoal sample failed acceptance criteria. Declared TSC ventilation unavailable at 12:10 PM EDT, 4/11/09. TSC ventilation supports RERP radiological habitability function and as such represents a major loss of emergency assessment capability, offsite response capability, or offsite communications capability in accordance with 10CFR50.72(b)(3)(xiii). Notified all Shift Managers if an emergency event is declared (Alert or higher), Shift Managers will need to modify emergency call out service so that TSC staffing report to Emergency Operating Facility (EOF). The use of the EOF as a backup facility for the TSC is included in Fermi's RERP Plan. Fermi will notify the NRC upon completion of corrective maintenance."
The licensee notified the NRC Resident Inspector.
* * * UPDATE FROM ROBERT MATUSZAK TO DONALD NORWOOD ON 5/1/09 AT 1621 EDT * * *
"Regarding Technical Support Center (TSC) ventilation unavailability: Corrective maintenance to restore HVAC system has been completed satisfactorily. TSC has been restored as an Emergency Response facility."
The TSC was declared operable at 1457 EDT. Corrective maintenance included replacing the out-of-spec charcoal filters and satisfactory follow-up tests.
The licensee notified the NRC Resident Inspector. Notified R3DO (Hills).
General Information or Other
Event Number: 45661
Rep Org: PA BUREAU OF RADIATION PROTECTION
Licensee: ST. LUKE'S HOSPITAL
Region: 1
City: BETHLEHAM State: PA
County:
License #: PA-0073
Agreement: Y
Docket:
NRC Notified By: DAVID ALLARD
HQ OPS Officer: JOHN KNOKE
Licensee: ST. LUKE'S HOSPITAL
Region: 1
City: BETHLEHAM State: PA
County:
License #: PA-0073
Agreement: Y
Docket:
NRC Notified By: DAVID ALLARD
HQ OPS Officer: JOHN KNOKE
Notification Date: 01/25/2010
Notification Time: 22:37 [ET]
Event Date: 04/11/2009
Event Time: 00:00 [EST]
Last Update Date: 01/25/2010
Notification Time: 22:37 [ET]
Event Date: 04/11/2009
Event Time: 00:00 [EST]
Last Update Date: 01/25/2010
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
SAM HANSELL (R1DO)
LARRY CAMPER (FSME)
SAM HANSELL (R1DO)
LARRY CAMPER (FSME)
AGREEMENT STATE REPORT - DOSE TO AN EMBRYO / FETUS
The following excerpted information was received by facsimile:
"Notifications: DEP [PA Department of Environmental Protection] received a letter dated May 1, 2009; Received May 8, 2009 from St. Luke's describing the incident, corrective actions, effects and notification to the patient.
"A patient was administered a therapeutic dose of 134 mCi of I-131 for thyroid carcinoma on April 11, 2008. She had previous negative pregnancy tests on April 6, 2008 and April 10, 2008. Following treatment the patient suspected she was pregnant and returned to the hospital an April 28, 2008. Subsequent testing indicated she became pregnant approximately 4 to 6 days following her treatment. Calculated dose to the fetus was 35 rad, whole body dose. Patient and referring physician both notified. The event occurred because the patient didn't follow the contraceptive plan outlined in the procedure she signed prior to treatment. The hospital staff followed procedure for therapeutic administration of I-131, however corrective actions involve procedure modifications such as over-emphasizing the risks associated with becoming pregnant following administration of radioiodine to prevent further occurrence."
Event Report ID No: PA080016
The following excerpted information was received by facsimile:
"Notifications: DEP [PA Department of Environmental Protection] received a letter dated May 1, 2009; Received May 8, 2009 from St. Luke's describing the incident, corrective actions, effects and notification to the patient.
"A patient was administered a therapeutic dose of 134 mCi of I-131 for thyroid carcinoma on April 11, 2008. She had previous negative pregnancy tests on April 6, 2008 and April 10, 2008. Following treatment the patient suspected she was pregnant and returned to the hospital an April 28, 2008. Subsequent testing indicated she became pregnant approximately 4 to 6 days following her treatment. Calculated dose to the fetus was 35 rad, whole body dose. Patient and referring physician both notified. The event occurred because the patient didn't follow the contraceptive plan outlined in the procedure she signed prior to treatment. The hospital staff followed procedure for therapeutic administration of I-131, however corrective actions involve procedure modifications such as over-emphasizing the risks associated with becoming pregnant following administration of radioiodine to prevent further occurrence."
Event Report ID No: PA080016