Event Notification Report for February 08, 2009
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
02/07/2009 - 02/08/2009
Power Reactor
Event Number: 44839
Facility: COLUMBIA GENERATING STATION
Region: 4 State: WA
Unit: [2] [] []
RX Type: [2] GE-5
NRC Notified By: BRANDON ABNEY
HQ OPS Officer: VINCE KLCO
Region: 4 State: WA
Unit: [2] [] []
RX Type: [2] GE-5
NRC Notified By: BRANDON ABNEY
HQ OPS Officer: VINCE KLCO
Notification Date: 02/08/2009
Notification Time: 18:08 [ET]
Event Date: 02/08/2009
Event Time: 11:25 [PST]
Last Update Date: 02/08/2009
Notification Time: 18:08 [ET]
Event Date: 02/08/2009
Event Time: 11:25 [PST]
Last Update Date: 02/08/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
10 CFR Section:
50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
JEFF CLARK (R4)
JEFF CLARK (R4)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 2 | A/R | Y | 75 | Power Operation | 0 | Hot Shutdown |
AUTOMATIC REACTOR SCRAM DUE TO A GOVERNOR VALVE FAST CLOSURE SIGNAL
"Following a downpower to 75% for replacement of DEH-SV-TRIP/B (solenoid for quadvoter valve) a reactor SCRAM occurred during the performance of the DEH [Digital Electric Hydraulic] quadvoter valve testing. The cause of the reactor SCRAM was Governor Valve Fast Closure signal due to DEH trip header pressure fluctuation. The cause of the DEH trip header pressure fluctuation is unknown and being investigated. All rods fully inserted. MSIVs remained open. No SRVs opened. RPV level is being controlled in the normal band using the feedwater and condensate systems. RPV pressure is being controlled in the normal band using the Bypass valves and Main Steam Line drains. All other safety systems operated as designed. Off-site power is available. All three emergency diesel generators are operable and available."
The licensee will be making a press release.
The licensee notified the NRC Resident Inspector.
"Following a downpower to 75% for replacement of DEH-SV-TRIP/B (solenoid for quadvoter valve) a reactor SCRAM occurred during the performance of the DEH [Digital Electric Hydraulic] quadvoter valve testing. The cause of the reactor SCRAM was Governor Valve Fast Closure signal due to DEH trip header pressure fluctuation. The cause of the DEH trip header pressure fluctuation is unknown and being investigated. All rods fully inserted. MSIVs remained open. No SRVs opened. RPV level is being controlled in the normal band using the feedwater and condensate systems. RPV pressure is being controlled in the normal band using the Bypass valves and Main Steam Line drains. All other safety systems operated as designed. Off-site power is available. All three emergency diesel generators are operable and available."
The licensee will be making a press release.
The licensee notified the NRC Resident Inspector.
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
!!!!! THIS EVENT HAS BEEN RETRACTED !!!!!
Research Reactor
Event Number: 44840
Rep Org: REED COLLEGE
Licensee: REED INSTITUTE
Region: 4
City: PORTLAND State: OR
County: MULTNOMAH
License #: R-112
Agreement: Y
Docket: 05000288
NRC Notified By: STEPHEN FRANTZ
HQ OPS Officer: VINCE KLCO
Licensee: REED INSTITUTE
Region: 4
City: PORTLAND State: OR
County: MULTNOMAH
License #: R-112
Agreement: Y
Docket: 05000288
NRC Notified By: STEPHEN FRANTZ
HQ OPS Officer: VINCE KLCO
Notification Date: 02/08/2009
Notification Time: 20:18 [ET]
Event Date: 02/08/2009
Event Time: 16:02 [PST]
Last Update Date: 02/11/2009
Notification Time: 20:18 [ET]
Event Date: 02/08/2009
Event Time: 16:02 [PST]
Last Update Date: 02/11/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
JEFF CLARK (R4)
DAN HUGHES (NRR)
JEFF CLARK (R4)
DAN HUGHES (NRR)
TEST REACTOR EXCEEDED LICENSED POWER LIMIT DURING CALIBRATION
"Performing routine thermal power calibration of nuclear instruments at indicated power of 230 kW per SOP-33. Calculation indicated actual power of 263 kW after collecting data. Licensed power limit is 250 kW.
"No apparent cause for the calibration error. [The previous] calibration was successfully done on January 16, 2009."
The reactor was shutdown. All systems functioned as required. The licensee noted that the pool temperature was about 7 degrees Celsius cooler than the historical pool temperature.
The licensee will notify the NRR Project Manager and the State of Oregon.
* * * RETRACTION AT 1850 EST ON 2/11/09 FROM FRANTZ TO HUFFMAN * * *
The licensee re-performed the thermal calibration per SOP-33 to check results obtained on 2-08-09. The difference this time is the licensee extended the calibration for a much longer period (approximately 7 hours). The licensee has determined that data obtained during the first 30 to 60 minutes of calibration indicated erratic information.
"[The licensee has] concluded that when [the reactor was] operating on 2-08-09 at an indicated power of 230 KW, actual power was 245 KW. [This power] is less than [the reactor's] licensed limit of 250 KW. Thus Reed did not violate its licensed power limit on 2-08-09 as previously reported. SOP-33 will be revised to avoid this error in the future."
Notified the NRR PM (Hughes via e-mail) and NRR EO (Lee). R4DO (Miller) was notified for information.
"Performing routine thermal power calibration of nuclear instruments at indicated power of 230 kW per SOP-33. Calculation indicated actual power of 263 kW after collecting data. Licensed power limit is 250 kW.
"No apparent cause for the calibration error. [The previous] calibration was successfully done on January 16, 2009."
The reactor was shutdown. All systems functioned as required. The licensee noted that the pool temperature was about 7 degrees Celsius cooler than the historical pool temperature.
The licensee will notify the NRR Project Manager and the State of Oregon.
* * * RETRACTION AT 1850 EST ON 2/11/09 FROM FRANTZ TO HUFFMAN * * *
The licensee re-performed the thermal calibration per SOP-33 to check results obtained on 2-08-09. The difference this time is the licensee extended the calibration for a much longer period (approximately 7 hours). The licensee has determined that data obtained during the first 30 to 60 minutes of calibration indicated erratic information.
"[The licensee has] concluded that when [the reactor was] operating on 2-08-09 at an indicated power of 230 KW, actual power was 245 KW. [This power] is less than [the reactor's] licensed limit of 250 KW. Thus Reed did not violate its licensed power limit on 2-08-09 as previously reported. SOP-33 will be revised to avoid this error in the future."
Notified the NRR PM (Hughes via e-mail) and NRR EO (Lee). R4DO (Miller) was notified for information.