Event Notification Report for September 01, 2008
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
08/31/2008 - 09/01/2008
Power Reactor
Event Number: 44456
Facility: SAN ONOFRE
Region: 4 State: CA
Unit: [] [] [3]
RX Type: [1] W-3-LP,[2] CE,[3] CE
NRC Notified By: SUSAN GARDNER
HQ OPS Officer: PETE SNYDER
Region: 4 State: CA
Unit: [] [] [3]
RX Type: [1] W-3-LP,[2] CE,[3] CE
NRC Notified By: SUSAN GARDNER
HQ OPS Officer: PETE SNYDER
Notification Date: 09/01/2008
Notification Time: 17:03 [ET]
Event Date: 09/01/2008
Event Time: 10:35 [PDT]
Last Update Date: 09/01/2008
Notification Time: 17:03 [ET]
Event Date: 09/01/2008
Event Time: 10:35 [PDT]
Last Update Date: 09/01/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
50.72(b)(2)(i) - PLANT S/D REQD BY TS
10 CFR Section:
50.72(b)(2)(i) - PLANT S/D REQD BY TS
Person (Organization):
VIVIAN CAMPBELL (R4)
VIVIAN CAMPBELL (R4)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 3 | N | Y | 100 | Power Operation | 46 | Power Operation |
SHUTDOWN DUE TO EMERGENCY DIESEL GENERATOR SHORTING RING CRACKS
"On September 1, 2008, at about 1035 PDT, Southern California Edison (SCE) began a planned shutdown of San Onofre Unit 3. This shutdown is in anticipation of exceeding the Allowed Outage Time (AOT) of 14 days of Technical Specification 3.8.1 Action B.4 for an inoperable Diesel Generator (Train B). The AOT is due to expire on September 2, 2008 at about 0200. If the system cannot be restored within the allowed outage time, a plant shutdown is required. The initiation of this shutdown is being reported in accordance with 10CFR50.72(b)(2)(i).
"An inspection of the DG generator revealed cracks in the shorting ring, requiring replacement of the generator. Post maintenance testing performed after replacement revealed anomalous readings. SCE determined that problem identification, repair and post test could not be performed before expiration of the AOT. Consequently, shutdown has been initiated.
"At the initiation of the shutdown, SONGS Unit 3 was operating at full power. SONGS Unit 2 is operating at approximately 99 percent power.
"The NRC Resident Inspectors have been briefed on the shutdown plans and will be provided with a copy of this report."
"On September 1, 2008, at about 1035 PDT, Southern California Edison (SCE) began a planned shutdown of San Onofre Unit 3. This shutdown is in anticipation of exceeding the Allowed Outage Time (AOT) of 14 days of Technical Specification 3.8.1 Action B.4 for an inoperable Diesel Generator (Train B). The AOT is due to expire on September 2, 2008 at about 0200. If the system cannot be restored within the allowed outage time, a plant shutdown is required. The initiation of this shutdown is being reported in accordance with 10CFR50.72(b)(2)(i).
"An inspection of the DG generator revealed cracks in the shorting ring, requiring replacement of the generator. Post maintenance testing performed after replacement revealed anomalous readings. SCE determined that problem identification, repair and post test could not be performed before expiration of the AOT. Consequently, shutdown has been initiated.
"At the initiation of the shutdown, SONGS Unit 3 was operating at full power. SONGS Unit 2 is operating at approximately 99 percent power.
"The NRC Resident Inspectors have been briefed on the shutdown plans and will be provided with a copy of this report."
Power Reactor
Event Number: 44457
Facility: RIVER BEND
Region: 4 State: LA
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: TIM SCHENK
HQ OPS Officer: VINCE KLCO
Region: 4 State: LA
Unit: [1] [] []
RX Type: [1] GE-6
NRC Notified By: TIM SCHENK
HQ OPS Officer: VINCE KLCO
Notification Date: 09/01/2008
Notification Time: 23:33 [ET]
Event Date: 09/01/2008
Event Time: 18:02 [CDT]
Last Update Date: 09/01/2008
Notification Time: 23:33 [ET]
Event Date: 09/01/2008
Event Time: 18:02 [CDT]
Last Update Date: 09/01/2008
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
VIVIAN CAMPBELL (R4)
VIVIAN CAMPBELL (R4)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | M/R | Y | 27 | Power Operation | 0 | Hot Shutdown |
PLANNED MANUAL PLANT SHUTDOWN DUE TO GRID CONDITIONS
"Voluntary Report of Planned Manual Plant Shutdown. At 1802 on September 1, 2008, River Bend Station [RBS] completed a planned manual shutdown of the unit. This shutdown was determined to be necessary based on the conditions of the grid due to Hurricane Gustav. Evaluation of grid conditions determined that removing the unit from power operation would improve the reliability of the grid and thus the decision was made to shutdown. Offsite power was declared inoperable at 1520 on September 1 based on notification of grid status by the grid operator. It is expected that offsite power will be restored to an operable status within the 24 hour LCO Required Action Completion Time. In addition, damage to turbine building siding was reported. Assessment of this condition is being conducted. RBS had previously activated the Outage Control Center prior to the arrival of Hurricane Gustav. Additional resources are available on site to respond to plant conditions. A comprehensive assessment of the condition of the plant and other site facilities will be completed prior to restart. At this time, a schedule for restart has not been established."
The licensee contacted the NRC Resident Inspector.
"Voluntary Report of Planned Manual Plant Shutdown. At 1802 on September 1, 2008, River Bend Station [RBS] completed a planned manual shutdown of the unit. This shutdown was determined to be necessary based on the conditions of the grid due to Hurricane Gustav. Evaluation of grid conditions determined that removing the unit from power operation would improve the reliability of the grid and thus the decision was made to shutdown. Offsite power was declared inoperable at 1520 on September 1 based on notification of grid status by the grid operator. It is expected that offsite power will be restored to an operable status within the 24 hour LCO Required Action Completion Time. In addition, damage to turbine building siding was reported. Assessment of this condition is being conducted. RBS had previously activated the Outage Control Center prior to the arrival of Hurricane Gustav. Additional resources are available on site to respond to plant conditions. A comprehensive assessment of the condition of the plant and other site facilities will be completed prior to restart. At this time, a schedule for restart has not been established."
The licensee contacted the NRC Resident Inspector.
General Information or Other
Event Number: 45164
Rep Org: TEXAS DEPARTMENT OF HEALTH
Licensee: FLINT HILLS RESOURCES LP
Region: 4
City: PORT ARTHUR State: TX
County:
License #: 00547
Agreement: Y
Docket:
NRC Notified By: ART TUCKER
HQ OPS Officer: BILL HUFFMAN
Licensee: FLINT HILLS RESOURCES LP
Region: 4
City: PORT ARTHUR State: TX
County:
License #: 00547
Agreement: Y
Docket:
NRC Notified By: ART TUCKER
HQ OPS Officer: BILL HUFFMAN
Notification Date: 06/26/2009
Notification Time: 11:57 [ET]
Event Date: 09/01/2008
Event Time: 00:00 [CDT]
Last Update Date: 06/26/2009
Notification Time: 11:57 [ET]
Event Date: 09/01/2008
Event Time: 00:00 [CDT]
Last Update Date: 06/26/2009
Emergency Class: NON EMERGENCY
10 CFR Section:
10 CFR Section:
Person (Organization):
DALE POWERS (R4DO)
ANGELA MCINTOSH (FSME)
DALE POWERS (R4DO)
ANGELA MCINTOSH (FSME)
AGREEMENT STATE REPORT - GAUGE SHUTTER FAILED TO CLOSE
The following information was received from the State via e-mail:
"On June 25, 2009, at 1630 the Agency was notified by the licensee that while looking for information requested by the State for a previous gauge failure ( EN 44981), the licensee discovered an additional event. This event occurred in early September, 2008, and had not been reported as required. The event involved an Ohmart/VEGA Model SH-F2 level gauge containing a 300 millicurie ( 228 mCi calculated current activity) Cesium (Cs) - 137 source. The gauge shutter would not close due to a sheared shutter rotor. The manufacturer was notified, and a technician arrived at the facility [located in Odessa, TX] on September 30, 2009. The technician replaced the rotor, cleaned and lubricated the gauge, and the gauge operated normally. The technician found that a great deal of material had collected in the source holder causing the failure. The licensee has removed all of their nuclear gauges and is in the process of terminating their license."
Texas Incident Report # I-8642
The following information was received from the State via e-mail:
"On June 25, 2009, at 1630 the Agency was notified by the licensee that while looking for information requested by the State for a previous gauge failure ( EN 44981), the licensee discovered an additional event. This event occurred in early September, 2008, and had not been reported as required. The event involved an Ohmart/VEGA Model SH-F2 level gauge containing a 300 millicurie ( 228 mCi calculated current activity) Cesium (Cs) - 137 source. The gauge shutter would not close due to a sheared shutter rotor. The manufacturer was notified, and a technician arrived at the facility [located in Odessa, TX] on September 30, 2009. The technician replaced the rotor, cleaned and lubricated the gauge, and the gauge operated normally. The technician found that a great deal of material had collected in the source holder causing the failure. The licensee has removed all of their nuclear gauges and is in the process of terminating their license."
Texas Incident Report # I-8642